| Position | Project | County | Bid date | Published bid | Low bid |
|---|---|---|---|---|---|
| Rank 3of 3 | Hot Mix CL - DeWitt Co. (Materials Only) | DE WITT | 2026-09-22 | $597,000.00 | $510,000.00 |
| Low bidof 4 | FM 1331 - W of FM 619 to Milam C/L | WILLIAMSON | 2026-09-02 | $2,174,856.36 | $2,174,856.36 |
| Rank 2of 4 | FY 27 West Hot Mix Cold-Laid | BLANCO | 2026-09-02 | $3,005,750.00 | $2,803,000.00 |
| Rank 2of 4 | FY 27 East Hot Mix Cold-Laid | HAYS | 2026-09-02 | $2,290,500.00 | $2,219,000.00 |
| Rank 4of 6 | US 57:0276-07-035; OV | FRIO | 2026-08-05 | $8,989,699.88 | $7,430,847.08 |
| Rank 2of 4 | HOT-MIX (MAT ONLY) SAN SABA COUNTY | SAN SABA | 2026-07-15 | $218,000.00 | $178,980.00 |
| Low bidof 3 | FY26 Milam HMA - 07 | MILAM | 2026-07-14 | $372,300.00 | $372,300.00 |
| Rank 4of 7 | US 59 Goliad Fort St to SH 239 Rehab | GOLIAD | 2026-07-01 | $2,473,962.20 | $2,132,369.40 |
| Rank 8of 8 | US 87: 0143-01-068; OV | BEXAR | 2026-07-01 | $3,556,084.15 | $2,314,231.60 |
| Rank 3of 4 | Hot Mix - Bell and Falls | BELL | 2026-07-01 | $1,381,000.00 | $1,302,581.00 |
| Rank 2of 4 | Hot Mix - Coryell and Hamilton | CORYELL | 2026-07-01 | $1,247,925.00 | $1,194,787.50 |
| Rank 3of 5 | FY26 Robertson Hot Mix - 06 | ROBERTSON | 2026-06-10 | $384,125.00 | $330,664.00 |
| Low bidof 3 | Asphalt Repair FY 26-2 | HAYS | 2026-05-13 | $890,313.75 | $890,313.75 |
| Rank 5of 7 | SS 536: 0073-02-092: OV | BEXAR | 2026-05-07 | $1,459,000.87 | $1,105,676.65 |
| Low bidof 5 | FY26 - Calvert Mill & Inlay | ROBERTSON | 2026-05-07 | $2,266,507.80 | $2,266,507.80 |
| Rank 4of 4 | OV | US 77 | FM 3148 | LP 340 | MCLENNAN | 2026-05-06 | $8,080,109.58 | $5,957,587.85 |
| Rank 5of 5 | VA: 0915-00-313: SC Prep | BEXAR | 2026-05-06 | $6,147,287.50 | $4,426,974.30 |
| Rank 3of 6 | SL 368: 0016-08-049; OV | BEXAR | 2026-04-07 | $4,957,514.77 | $3,947,711.24 |
| Low bidof 4 | SH 29 - FM 1660 to SH 95 | WILLIAMSON | 2026-04-07 | $2,388,456.46 | $2,388,456.46 |
| Low bidof 4 | FM 619 from FM 1331 to US 79 | WILLIAMSON | 2026-04-07 | $1,567,486.66 | $1,567,486.66 |
| Rank 4of 4 | Hot Mix - DeWitt (Materials Only) | DE WITT | 2026-03-24 | $1,074,000.00 | $936,000.00 |
| Rank 3of 5 | Hot Mix - Lavaca (Materials Only) | LAVACA | 2026-03-24 | $1,058,000.00 | $943,000.00 |
| Rank 4of 5 | Hot Mix CL - Lavaca (Materials Only) | LAVACA | 2026-03-24 | $478,750.00 | $430,000.00 |
| Rank 4of 4 | Hot Mix - Gonzales (Materials Only) | GONZALES | 2026-03-24 | $983,250.00 | $862,500.00 |
| Rank 4of 4 | Hot Mix CL - Gonzales (Materials Only) | GONZALES | 2026-03-24 | $452,500.00 | $405,000.00 |