Route 140 Intersection Improvements at Burbank Road
Tolland County
Bid dateWednesday, December 6—
Awarded toGuerrera Construction Company Inc$6.15M
Project scope
Bid form · CTDOT
1 . Cat Alt Set: Cat Alt Member:100%
Top items by winning bid
Item
Qty
Unit price
Extended
%
0202315DISPOSAL OF CONTROLLED MATERIALS ** See Special Provisions **
18,298 ton
$75
$1.37M
22%
0202000EARTH EXCAVATION
20,702 c.y.
$27
$559k
9%
0406171HMA S0.5
3,264 ton
$158
$516k
8%
0202100ROCK EXCAVATION
12,568 c.y.
$40
$503k
8%
0975004MOBILIZATION AND PROJECT CLOSEOUT
1 LS
$333,000
$333k
5%
0969054CONTRACTOR QUALITY CONTROL PROGRAM LEVEL 1 ** See Special Provisions **
Project details
Type of work
Signals
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
1 LS
$200,000
$200k
3%
0304002PROCESSED AGGREGATE BASE
3,793 c.y.
$52
$197k
3%
0969030PROJECT COORDINATOR (MINIMUM BID) ** See Special Provisions **