Route 140 Intersection Improvements at Burbank Road
Tolland County
Bid dateWednesday, December 6—
Low bidGuerrera Construction Company Inc$6.15M
Tolland County
Bid tab · CTDOT
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 0202315 DISPOSAL OF CONTROLLED MATERIALS ** See Special Provisions ** | 18,298 ton | $75 | $1.37M | 22% |
| 0202000 EARTH EXCAVATION | 20,702 c.y. | $27 | $559k | 9% |
| 0406171 HMA S0.5 | 3,264 ton | $158 | $516k | 8% |
| 0202100 ROCK EXCAVATION | 12,568 c.y. | $40 | $503k | 8% |
| 0975004 MOBILIZATION AND PROJECT CLOSEOUT | 1 LS | $333,000 | $333k | 5% |
| 0969054 CONTRACTOR QUALITY CONTROL PROGRAM LEVEL 1 ** See Special Provisions ** | 1 LS | $200,000 | $200k | 3% |
| 0304002 PROCESSED AGGREGATE BASE | 3,793 c.y. | $52 | $197k | 3% |
| 0969030 PROJECT COORDINATOR (MINIMUM BID) ** See Special Provisions ** | 1 LS | $150,000 | $150k | 2% |
| 0822101.02 RELOCATED TEMPORARY TRAFFIC BARRIER (PINNED) | 2,740 l.f. | $48 | $132k | 2% |
| 0686000.15 15'' R.C. PIPE - 0' - 10' DEEP | 1,472 l.f. | $86 | $127k | 2% |