Route 140 Geometry Improvements
Tolland County
Bid dateWednesday, December 18—
Low bidBaltazar Contractors Inc$8.30M
Tolland County
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
Bid tab · CTDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 0202328 MANAGEMENT OF REUSABLE CONTROLLED MATERIAL ** See Special Provisions ** | 1 LS | $1,800,000 | $1.80M | 22% |
| 0406171 HMA S0.5 | 5,715 ton | $188 | $1.07M | 13% |
| 0202000 EARTH EXCAVATION | 25,060 c.y. | $20 | $501k | 6% |
| 0202100 ROCK EXCAVATION | 5,125 c.y. | $90 | $461k | 6% |
| 1118101 TEMPORARY SIGNALIZATION ** See Special Provisions ** | 1 LS | $350,000 | $350k | 4% |
| 0304002 PROCESSED AGGREGATE BASE | 6,245 c.y. | $48 | $300k | 4% |
| 0971001 MAINTENANCE AND PROTECTION OF TRAFFIC ** See Special Provisions ** | 1 LS | $205,000 | $205k | 2% |
| 0944000 FURNISHING AND PLACING TOPSOIL | 25,155 s.y. | $8 | $201k | 2% |
| 0975004 MOBILIZATION AND PROJECT CLOSEOUT | 1 LS | $200,000 | $200k | 2% |
| 0910300 |
| 5,212 l.f. |
| $33 |
| $172k |
| 2% |