0514271PRECAST CONCRETE/STEEL COMPOSITE SUPERSTRUCTURE ** See Special Provisions **
6,470 s.f.
$610
$3.95M
31%
0503001REMOVAL OF SUPERSTRUCTURE ** See Special Provisions **
1 LS
$1,300,000
$1.30M
10%
0971001MAINTENANCE AND PROTECTION OF TRAFFIC ** See Special Provisions **
1 LS
$1,250,000
$1.25M
10%
0406171HMA S0.5
3,018 ton
$185
$558k
4%
0975004MOBILIZATION AND PROJECT CLOSEOUT
1 LS
$500,000
$500k
4%
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
0514717PRECAST APPROACH SLAB ** See Special Provisions **
322 s.y.
$1,500
$483k
4%
0822101.01RELOCATED TEMPORARY TRAFFIC BARRIER
19,000 l.f.
$20
$380k
3%
0207000BORROW
8,400 c.y.
$40
$336k
3%
0601107HIGH EARLY STRENGTH CONCRETE ** See Special Provisions **