I-95 Southbound Safety Improvements
New London County
Bid dateWednesday, November 8—
Low bidEmpire Paving Inc$36.9M
New London County
Bid tab · CTDOT
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 0406159 PMA S0.5 | 70,400 ton | $110 | $7.74M | 21% |
| 0406160 PMA S1 | 58,000 ton | $112.5 | $6.53M | 18% |
| 0975004 MOBILIZATION AND PROJECT CLOSEOUT | 1 LS | $3,600,000 | $3.60M | 10% |
| 0910300 METAL BEAM RAIL (R-B MASH) | 68,500 l.f. | $24.7 | $1.69M | 5% |
| 0409006 COARSE MILLING OF BITUMINOUS CONCRETE (GREATER THAN 4" UP TO 8") | 167,400 s.y. | $10 | $1.67M | 5% |
| 0822100.01 TEMPORARY TRAFFIC BARRIER | 15,000 l.f. | $110 | $1.65M | 4% |
| 0971001 MAINTENANCE AND PROTECTION OF TRAFFIC ** See Special Provisions ** | 1 LS | $1,000,000 | $1.00M | 3% |
| 0305000 PROCESSED AGGREGATE | 18,843 ton | $50 | $942k | 3% |
| 0219001 SEDIMENTATION CONTROL SYSTEM ** See Special Provisions ** | 145,300 l.f. | $4.8 | $697k | 2% |
| 1001001 TRENCHING AND BACKFILLING | 14,620 l.f. | $33 | $482k | 1% |