Southington Rest Area Truck Parking Improvements
Hartford County
Bid dateWednesday, December 10—
Awarded toTilcon Connecticut Inc$7.90M
Hartford County
Bid form · CTDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 0406170 HMA S1 | 8,925 ton | $120 | $1.07M | 14% |
| 0406159 PMA S0.5 | 7,250 ton | $128 | $928k | 12% |
| 0304002 PROCESSED AGGREGATE BASE | 7,675 c.y. | $76 | $583k | 7% |
| 0202000 EARTH EXCAVATION | 14,400 c.y. | $28 | $403k | 5% |
| 0202315 DISPOSAL OF CONTROLLED MATERIALS ** See Special Provisions ** | 6,400 ton | $62 | $397k | 5% |
| 0975004 MOBILIZATION AND PROJECT CLOSEOUT | 1 LS | $371,351 | $371k |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 5% |
| 0813012 5'' X 18'' GRANITE STONE CURBING | 4,930 l.f. | $60 | $296k | 4% |
| 0944000 FURNISHING AND PLACING TOPSOIL | 16,550 s.y. | $12 | $199k | 3% |
| 0406002 TEMPORARY PAVEMENT ** See Special Provisions ** | 2,100 s.y. | $92 | $193k | 2% |
| 0751710 4'' UNDERDRAIN | 3,100 l.f. | $55 | $171k | 2% |