US 183 from SH 138 to N of CR 254
Williamson County · est $20M
Williamson County · est $20M
8 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | JOE BLAND CONSTRUCTION LLC | $14,639,581.45 | — |
| 2 | TEXAS MATERIALS GROUP, INC. | $14,682,822.17 | $43,240.72 |
| 3 | HUNTER INDUSTRIES, LTD. | $15,140,468.24 | $500,886.79 |
| 4 | DAN WILLIAMS COMPANY | $15,440,401.85 | $800,820.40 |
| 5 | POSILLICO CIVIL, INC. | $15,578,367.00 | $938,785.55 |
| 6 | AARON CONCRETE CONTRACTORS, LLC | $15,679,939.43 | $1,040,357.98 |
| 7 | CHASCO CONSTRUCTORS | $15,689,948.00 | $1,050,366.55 |
| 8 | TEXAS ROAD LLC | $16,484,000.59 | $1,844,419.14 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 341-7056 D-GR HMA TY-D PG76-22 | 18,969 TON | $95 | $1.80M | 12% |
| 247-7179 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | 26,046 CY | $68 | $1.77M | 12% |
| 341-7001 D-GR HMA TY-B PG64-22 | 18,945 TON | $80 | $1.52M | 10% |
| 347-7002 TOM-C PG76-22 SAC-B | 12,942 TON | $117 | $1.51M | 10% |
| 341-7059 D-GR HMA TY-D PG76-22 (LEVEL-UP) | 6,611 TON | $108 | $714k | 5% |
| 432-7002 RIPRAP (CONC)(5 IN) | 1,581 CY | $385 | $609k | 4% |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 608 CY | $715 | $435k | 3% |
| 110-7001 EXCAV (ROADWAY) | 28,582 CY | $15 | $429k | 3% |
| 500-7001 MOBILIZATION | 1 LS | $425,000 | $425k | 3% |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 6,283 SY | $55 | $346k | 2% |