SH 174; Wicker Hill to Elk Dr
Johnson County · est $20M
Johnson County · est $20M
8 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | REYES TX, INC. | $19,812,334.00 | — |
| 2 | JAY MILLS CONTRACTING, INCORPORATED | $20,139,332.41 | $326,998.41 |
| 3 | FOUTSCO PAVING COMPANY, LLC | $20,530,952.76 | $718,618.76 |
| 4 | RAGLE CONSTRUCTION, INC. | $21,055,631.20 | $1,243,297.20 |
| 5 | OVERLAND CORPORATION | $21,808,765.88 | $1,996,431.88 |
| 6 | TEXAS MATERIALS GROUP, INC. | $21,835,404.46 | $2,023,070.46 |
| 7 | ED BELL CONSTRUCTION COMPANY | $22,787,416.88 | $2,975,082.88 |
| 8 | COPASA INC | $24,437,941.64 | $4,625,607.64 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 344-7024 SP MIXES SP-C SAC-A PG70-28 | 13,905 TON | $165 | $2.29M | 12% |
| 500-7001 MOBILIZATION | 1 LS | $1,826,000 | $1.83M | 9% |
| 100-7002 PREPARING ROW | 105 STA | $14,148 | $1.49M | 7% |
| 344-7001 SP MIXES SP-B PG64-22 | 7,987 TON | $117 | $934k | 5% |
| 247-7113 FL BS (CMP IN PLC)(TY A GR 1-2) (12") | 38,230 SY | $23 | $879k | 4% |
| 529-7009 CONC CURB & GUTTER (TY II) | 21,876 LF | $35 | $766k | 4% |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 16,880 LF | $36 | $608k | 3% |
| 505-7003 TMA (MOBILE OPERATION) | 230 DAY | $2,610 | $600k | 3% |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 19,200 CY | $28 | $538k | 3% |
| 344-7055 SP MIXES SP-D SAC-B PG70-22 (LEVEL-UP) | 3,600 TON | $147 | $529k |
| 3% |