Kings Gate Rd: at Clear Fork Trinity Rv
Parker County · est $1.8M
Parker County · est $1.8M
8 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | Westfield Insurance Company | $1,536,598.58 | — |
| 2 | STX CIVIL | $1,656,064.00 | $119,465.42 |
| 3 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $1,734,885.00 | $198,286.42 |
| 4 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC | $1,796,217.80 | $259,619.22 |
| 5 | PMCO CONSTRUCTION LLC | $1,807,523.90 | $270,925.32 |
| 6 | TEXAS STEEL INDUSTRIAL PLACING, LLC | $1,819,233.43 | $282,634.85 |
| 7 | SKYLINE BRIDGE LLC | $1,867,514.30 | $330,915.72 |
| 8 | ED BELL CONSTRUCTION COMPANY | $1,947,946.25 | $411,347.67 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 1,070 CY | $192.5 | $206k | 13% |
| 500-7001 MOBILIZATION | 1 LS | $167,400 | $167k | 11% |
| 425-7004 PRESTR CONC GIRDER (TX46) | 651.3 LF | $235.08 | $153k | 10% |
| 422-7002 REINF CONC SLAB (HPC) | 4,796 SF | $30.8 | $148k | 10% |
| 360-7001 CONC PVMT (CRCP) (7") | 1,233 SY | $118.81 | $146k | 10% |
| 416-7006 DRILL SHAFT (36 IN) | 545 LF | $254.1 | $138k | 9% |
| 420-7013 CL C CONC (ABUT)(HPC) | 65.4 CY | $1,320 | $86k | 6% |
| 422-7013 APPROACH SLAB | 80.4 CY | $825 | $66k | 4% |
| 400-7010 CEM STABIL BKFL | 240 CY | $221.17 | $53k | 3% |
| 450-7009 RAIL (TY T223)(HPC) | 282 LF | $183.7 | $52k | 3% |