McVoid Rd: at Tributary of Walnut Creek
Parker County · est $940k
Parker County · est $940k
8 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | Westfield Insurance Company | $829,672.57 | — |
| 2 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $870,896.00 | $41,223.43 |
| 3 | PMCO CONSTRUCTION LLC | $919,219.55 | $89,546.98 |
| 4 | TEXAS STEEL INDUSTRIAL PLACING, LLC | $938,906.27 | $109,233.70 |
| 5 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC | $1,045,741.84 | $216,069.27 |
| 6 | STX CIVIL | $1,053,361.70 | $223,689.13 |
| 7 | ED BELL CONSTRUCTION COMPANY | $1,210,337.05 | $380,664.48 |
| 8 | COPPELL CONSTRUCTION CO., INC. | $1,311,653.31 | $481,980.74 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 664 CY | $200.51 | $133k | 16% |
| 500-7001 MOBILIZATION | 1 LS | $105,000 | $105k | 13% |
| 425-7017 PRESTR CONC SLAB BEAM (5SB12) | 367.12 LF | $231.75 | $85k | 10% |
| 416-7004 DRILL SHAFT (24 IN) | 222 LF | $242 | $54k | 6% |
| 422-7002 REINF CONC SLAB (HPC) | 1,950 SF | $27.5 | $54k | 6% |
| 422-7014 APPROACH SLAB (HPC) | 50.8 CY | $880 | $45k | 5% |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $10,560 | $42k | 5% |
| 450-7009 RAIL (TY T223)(HPC) | 178 LF | $181.5 | $32k | 4% |
| 341-7001 D-GR HMA TY-B PG64-22 | 149 TON | $212.3 | $32k | 4% |
| 420-7013 CL C CONC (ABUT)(HPC) | 20.6 CY | $1,375 | $28k | 3% |