SL 335 B-2: New Location Ama Loop, PH V
Randall County · est $50M
Randall County · est $50M
5 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | J. LEE MILLIGAN, INC. | $42,220,204.15 | — |
| 2 | L A FULLER & SONS CONSTRUCTION, LTD. | $44,477,635.09 | $2,257,430.94 |
| 3 | RAGLE CONSTRUCTION, INC. | $48,810,034.55 | $6,589,830.40 |
| 4 | GILVIN-TERRILL, LTD. | $51,748,002.72 | $9,527,798.57 |
| 5 | WEBBER, LLC | $52,073,758.00 | $9,853,553.85 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 132-7004 EMBANK (FNL)(DC)(TY B) | 230,572 CY | $25 | $5.76M | 14% |
| 423-7001 RETAINING WALL (MSE) | 96,735 SF | $52 | $5.03M | 12% |
| 500-7001 MOBILIZATION | 1 LS | $4,644,800 | $4.64M | 11% |
| 344-7006 SP MIXES SP-B PG70-28 | 26,924 TON | $135 | $3.63M | 9% |
| 346-7010 STONE-MTRX-ASPH SMA-D SAC-A PG76-28 | 8,303 TON | $185 | $1.54M | 4% |
| 613-7006 HI MST IL POLE (150 FT)(100 MPH) | 20 EA | $68,200 | $1.36M | 3% |
| 464-7005 RC PIPE (CL III)(24 IN) | 7,379 LF | $175 | $1.29M | 3% |
| 531-7001 CONC SIDEWALKS (4") | 14,765 SY | $81.5 | $1.20M | 3% |
| 425-7005 PRESTR CONC GIRDER (TX54) | 3,486 LF | $310 | $1.08M | 3% |
| 422-7001 REINF CONC SLAB | 41,796 SF | $25.5 | $1.07M | 3% |