FM1472 Concrete PVMT
Webb County · est $3.4M
Webb County · est $3.4M
7 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | JAMES CONSTRUCTION GROUP, LLC | $2,951,706.36 | — |
| 2 | J. CARROLL WEAVER, INC. | $3,107,870.83 | $156,164.47 |
| 3 | ANDERSON COLUMBIA CO., INC. | $3,278,449.19 | $326,742.83 |
| 4 | STX CIVIL | $3,336,891.73 | $385,185.37 |
| 5 | LUCANIA CONTRACTORS LLC | $3,419,724.02 | $468,017.66 |
| 6 | ACME BRIDGE COMPANY, INC. | $3,595,756.96 | $644,050.60 |
| 7 | CK NEWBERRY, LLC | $4,132,645.25 | $1,180,938.89 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
Source check time unavailable
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 360-7076 CONC PVMT (CRCP)(FAST TRK) (12") | 5,682 SY | $128.42 | $730k | 25% |
| 346-7001 STONE-MTRX-ASPH SMA-C SAC-A PG76-22 | 2,710 TON | $185 | $501k | 17% |
| 500-7001 MOBILIZATION | 1 LS | $295,000 | $295k | 10% |
| 100-7002 PREPARING ROW | 25 STA | $10,850 | $271k | 9% |
| 341-7007 D-GR HMA TY-B SAC-B PG70-22 | 1,260 TON | $160 | $202k | 7% |
| 508-7001 CONSTRUCTING DETOURS | 1,839 SY | $77.14 | $142k | 5% |
| 247-7176 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS) | 835 CY | $122.5 | $102k | 3% |
| 545-7006 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3) | 2 EA | $27,100 | $54k | 2% |
| 132-7002 EMBANK (FNL)(DC)(TY A) | 2,917 CY | $16.25 | $47k | 2% |
| 480-7001 CLEAN EXIST CULVERTS | 6 EA | $7,110 | $43k | 1% |