PostOakRD Goliad At Manahuilla Cr Bridge
Goliad County · est $1.2M
Goliad County · est $1.2M
13 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | DELGADO'S CONTRACTORS, LLC | $1,135,007.50 | — |
| 2 | GARRET SHIELDS INFRASTRUCTURE | $1,138,135.00 | $3,127.50 |
| 3 | R CONSTRUCTION CIVIL, LLC | $1,149,885.00 | $14,877.50 |
| 4 | PRESIDIO CONTRACTING, LLC | $1,171,268.05 | $36,260.55 |
| 5 | E-Z BEL CONSTRUCTION, LLC | $1,194,888.00 | $59,880.50 |
| 6 | LUCANIA CONTRACTORS LLC | $1,280,548.00 | $145,540.50 |
| 7 | HUNTER INDUSTRIES, LTD. | $1,290,348.57 | $155,341.07 |
| 8 | ACME BRIDGE COMPANY, INC. | $1,334,440.40 | $199,432.90 |
| 9 | J. CARROLL WEAVER, INC. | $1,450,414.82 | $315,407.32 |
| 10 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $1,474,491.00 | $339,483.50 |
| 11 | JAMES CONSTRUCTION GROUP, LLC | $1,499,416.50 | $364,409.00 |
| 12 | CK NEWBERRY, LLC | $1,696,578.00 | $561,570.50 |
| 13 | FOREMOST PAVING, INC. | $1,974,928.19 | $839,920.69 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 425-7003 PRESTR CONC GIRDER (TX40) | 714 LF | $225 | $161k | 14% |
| 416-7006 DRILL SHAFT (36 IN) | 480 LF | $300 | $144k | 13% |
| 422-7001 REINF CONC SLAB | 4,680 SF | $27.5 | $129k | 11% |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 1,507 CY | $45 | $68k | 6% |
| 420-7012 CL C CONC (ABUT) | 43.8 CY | $1,500 | $66k | 6% |
| 450-7008 RAIL (TY T223) | 420 LF | $150 | $63k | 6% |
| 341-7001 D-GR HMA TY-B PG64-22 | 220 TON | $250 | $55k | 5% |
| 500-7001 MOBILIZATION | 1 LS | $52,000 | $52k | 5% |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 203 CY | $205 | $42k | 4% |
| 422-7013 APPROACH SLAB | 40 CY | $1,000 | $40k | 4% |