FY 24 District Seal Coat Markings
Bowie County · est $3.7M
Bowie County · est $3.7M
7 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | STRIPE-A-ZONE, LLC | $3,631,142.74 | — |
| 2 | GREY SKY CONSTRUCTION LLC | $3,771,507.99 | $140,365.25 |
| 3 | STRIPING TECHNOLOGY, L.P. | $4,089,437.72 | $458,294.98 |
| 4 | TRP INFRASTRUCTURE SERVICES, LLC | $5,537,122.83 | $1,905,980.09 |
| 5 | STRIPE LINES, INC. | $5,746,075.48 | $2,114,932.74 |
| 6 | LAKEY, INC. | $6,004,399.79 | $2,373,257.05 |
| 7 | INTERSTATE BARRICADES & MARKINGS, INC. | $6,825,153.85 | $3,194,011.11 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 666-7315 ALL-WTHER PM TY I (Y)6"(SLD)(100MIL) | 1,738,077 LF | $0.52 | $904k | 25% |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 1,249,684 LF | $0.71 | $887k | 24% |
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 211,611 LF | $3.1 | $656k | 18% |
| 666-7309 ALL-WTHER PM TY I (W)6"(SLD)(100MIL) | 1,080,376 LF | $0.51 | $551k | 15% |
| 668-7137 PRFB RUMBLE STRIP (BLK)(1')(EDGELINE) | 173,221 LF | $3.1 | $537k | 15% |
| 666-7316 ALL-WTHER PM TY I (Y)6"(BRK)(100MIL) | 132,190 LF | $0.53 | $70k | 2% |
| 666-7310 ALL-WTHER PM TY I (W)6"(BRK)(100MIL) | 22,070 LF | $0.53 | $12k | 0% |
| 668-7089 PREFAB PM TY C (W)(24")(SLD) | 285 LF | $15 | $4k | 0% |
| 666-7425 ALL-WTHER PM TY I (W) 8"(SLD)(100MIL) | 3,334 LF | $0.95 | $3k | 0% |
| 500-7001 MOBILIZATION | 1 LS | $2,500 | $3k | 0% |