CR 234 (C Meyer Rd) at Bee Creek
Fort Bend County · est $2.5M
Fort Bend County · est $2.5M
9 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | TREVWAY, INC. | $1,818,854.14 | — |
| 2 | JFO SERVICES, LLC | $2,028,455.00 | $209,600.86 |
| 3 | R CONSTRUCTION CIVIL, LLC | $2,096,930.41 | $278,076.27 |
| 4 | CASTILLO ARANDA LLC | $2,310,480.20 | $491,626.06 |
| 5 | SKYLINE BRIDGE LLC | $2,320,679.50 | $501,825.36 |
| 6 | MC2 CIVIL, LLC | $2,337,228.86 | $518,374.72 |
| 7 | TALBERT COMPANIES LLC | $2,378,259.92 | $559,405.78 |
| 8 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $2,557,496.50 | $738,642.36 |
| 9 | STX CIVIL | $2,665,634.47 | $846,780.33 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
Source check time unavailable
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 292-7006 ASPHALT TRT BASE (GR 2)(PG 64) | 1,334 TON | $189.47 | $253k | 14% |
| 416-7006 DRILL SHAFT (36 IN) | 536 LF | $360.1 | $193k | 11% |
| 500-7001 MOBILIZATION | 1 LS | $180,000 | $180k | 10% |
| 432-7002 RIPRAP (CONC)(5 IN) | 447 CY | $287 | $128k | 7% |
| 425-7001 PRESTR CONC GIRDER (TX28) | 435.65 LF | $266.69 | $116k | 6% |
| 341-7050 D-GR HMA TY-D SAC-B PG70-22 | 485 TON | $233.68 | $113k | 6% |
| 422-7001 REINF CONC SLAB | 4,264 SF | $22.49 | $96k | 5% |
| 420-7012 CL C CONC (ABUT) | 119 CY | $510.69 | $61k | 3% |
| 425-7016 PRESTR CONC SLAB BEAM (4SB12) | 265.34 LF | $205 | $54k | 3% |
| 400-7010 CEM STABIL BKFL | 340 CY | $148.76 | $51k | 3% |