SH 11 from US 59 to FM 130
Cass County · est $2.5M
Cass County · est $2.5M
10 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | SKYLINE BRIDGE LLC | $1,793,826.32 | — |
| 2 | THK CONSTRUCTION LLC | $1,946,198.78 | $152,372.46 |
| 3 | H. V. CAVER, INC. | $1,979,077.78 | $185,251.46 |
| 4 | GARRET SHIELDS INFRASTRUCTURE | $2,142,638.55 | $348,812.23 |
| 5 | ICOS MANAGEMENT, LLC | $2,341,940.01 | $548,113.69 |
| 6 | CDM HOLDINGS | $2,568,347.25 | $774,520.93 |
| 7 | DRAKE COMPANIES LLC | $2,577,843.61 | $784,017.29 |
| 8 | LONGVIEW BRIDGE AND ROAD, LTD. | $2,933,013.60 | $1,139,187.28 |
| 9 | 3LW CIVIL LLC | $3,012,612.46 | $1,218,786.14 |
| 10 | A R BROTHERS CONSTRUCTION SERVICES, INC. | $3,304,122.55 | $1,510,296.23 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 100-7002 PREPARING ROW | 381.41 STA | $650 | $248k | 14% |
| 500-7001 MOBILIZATION | 1 LS | $150,000 | $150k | 8% |
| 464-7003 RC PIPE (CL III)(18 IN) | 2,652 LF | $53.75 | $143k | 8% |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 295 CY | $475 | $140k | 8% |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 190 EA | $700 | $133k | 7% |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 3,212.5 LF | $27.56 | $89k | 5% |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 24 EA | $3,180 | $76k | 4% |
| 464-7005 RC PIPE (CL III)(24 IN) | 1,051 LF | $70.25 | $74k | 4% |
| 467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P) | 45 EA | $1,165 | $52k | 3% |
| 530-7008 DRIVEWAYS (CONC) (TY 1) | 543 SY | $86 | $47k | 3% |