US 69_FM 1270 to Jasper County Line
Angelina County · est $1.7M
Angelina County · est $1.7M
7 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | MASSANA CONSTRUCTION INC. | $1,511,792.00 | — |
| 2 | H. V. CAVER, INC. | $1,736,467.08 | $224,675.08 |
| 3 | GRATIOT CONSTRUCTION, LTD. | $1,745,352.06 | $233,560.06 |
| 4 | ROADWAY SPECIALTIES, INC. | $1,800,962.95 | $289,170.95 |
| 5 | W. M. MILLER CONSTRUCTION COMPANY, INC. | $1,827,554.85 | $315,762.85 |
| 6 | HJC FARMS, INC. | $1,950,776.20 | $438,984.20 |
| 7 | SCR CIVIL CONSTRUCTION, LLC | $2,051,818.56 | $540,026.56 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 1,547 CY | $330 | $511k | 34% |
| 543-7002 CABLE BARRIER SYSTEM (INSTALL)(TL-4) | 42,326 LF | $11 | $466k | 31% |
| 500-7001 MOBILIZATION | 1 LS | $202,800 | $203k | 13% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 11 MO | $7,500 | $83k | 5% |
| 543-7018 CABLE BARRIER TERM SEC (INSTL)(TL-4) | 42 EA | $1,500 | $63k | 4% |
| 132-7015 EMBANK (VEH)(OC)(TY B) | 1,188 CY | $36 | $43k | 3% |
| 432-7003 RIPRAP (CONC)(6 IN) | 68 CY | $480 | $33k | 2% |
| 150-7001 BLADING | 437 STA | $55 | $24k | 2% |
| 505-7001 TMA (STATIONARY) | 286 DAY | $75 | $21k | 1% |
| 506-7021 CONSTRUCTION EXITS (INSTALL) (TY 2) | 356 SY | $44 | $16k | 1% |