REPLACE BRIDGE CR 314 at DRAW
Nolan County · est $1.2M
Nolan County · est $1.2M
8 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | DELGADO'S CONTRACTORS, LLC | $918,428.50 | — |
| 2 | SKYLINE BRIDGE LLC | $929,934.80 | $11,506.30 |
| 3 | C & W SOUTHERN LLC | $944,491.00 | $26,062.50 |
| 4 | COPPELL CONSTRUCTION CO., INC. | $1,044,657.00 | $126,228.50 |
| 5 | STX CIVIL | $1,117,845.00 | $199,416.50 |
| 6 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $1,158,615.30 | $240,186.80 |
| 7 | C. E. BARKER, LTD. | $1,229,981.87 | $311,553.37 |
| 8 | TEXAS STEEL INDUSTRIAL PLACING, LLC | $1,314,519.72 | $396,091.22 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
Source check time unavailable
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 425-7019 PRESTR CONC SLAB BEAM (5SB15) | 495 LF | $315 | $156k | 17% |
| 416-7004 DRILL SHAFT (24 IN) | 360 LF | $255 | $92k | 10% |
| 500-7001 MOBILIZATION | 1 LS | $80,250 | $80k | 9% |
| 420-7012 CL C CONC (ABUT) | 44 CY | $1,800 | $79k | 9% |
| 422-7007 REINF CONC SLAB (SLAB BEAM) | 2,600 SF | $30 | $78k | 8% |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 2 EA | $35,000 | $70k | 8% |
| 247-7064 FL BS (CMP IN PLC)(TY A OR B GR 4)(6") | 1,721 SY | $35 | $60k | 7% |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 236 CY | $225 | $53k | 6% |
| 450-7008 RAIL (TY T223) | 252 LF | $180 | $45k | 5% |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 8 EA | $3,500 | $28k | 3% |