FM 2555 from SH 22 to West Park Row
Navarro County · est $2.0M
Navarro County · est $2.0M
7 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | TEXAS MATERIALS GROUP, INC. | $1,627,075.18 | — |
| 2 | KNIFE RIVER CORPORATION - SOUTH | $1,685,000.00 | $57,924.82 |
| 3 | BIG CREEK CONSTRUCTION, LTD. | $1,731,593.40 | $104,518.22 |
| 4 | PEACHTREE CONSTRUCTION, LTD. | $1,884,640.90 | $257,565.72 |
| 5 | FIREMAN EXCAVATING, INC. | $1,904,237.48 | $277,162.30 |
| 6 | GREY SKY CONSTRUCTION LLC | $2,041,346.00 | $414,270.82 |
| 7 | GARRET SHIELDS INFRASTRUCTURE | $2,385,500.30 | $758,425.12 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
Source check time unavailable
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 344-7011 SP MIXES SP-C SAC-B PG64-22 | 5,607 TON | $123 | $690k | 42% |
| 361-7069 FULL - DEPTH REPAIR CRCP (11"-12") | 533 SY | $395.32 | $211k | 13% |
| 530-7010 DRIVEWAYS (ACP) | 1,812 SY | $75 | $136k | 8% |
| 500-7001 MOBILIZATION | 1 LS | $100,000 | $100k | 6% |
| 354-7051 PLANE ASPH CONC PAV(2") | 48,517 SY | $1.8 | $87k | 5% |
| 464-7010 RC PIPE (CL III)(42 IN) | 186 LF | $315 | $59k | 4% |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 36 CY | $900 | $32k | 2% |
| 464-7005 RC PIPE (CL III)(24 IN) | 342 LF | $92 | $31k | 2% |
| 467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P) | 16 EA | $1,780 | $28k | 2% |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 20 EA | $1,360 | $27k | 2% |