RM 3404 - FY 25 SSWP
Llano County · est $1.3M
Llano County · est $1.3M
5 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | HUNTER INDUSTRIES, LTD. | $1,179,799.95 | — |
| 2 | AARON CONCRETE CONTRACTORS, LLC | $1,284,000.05 | $104,200.10 |
| 3 | ALLEN KELLER COMPANY | $1,327,789.71 | $147,989.76 |
| 4 | ACME BRIDGE COMPANY, INC. | $1,389,352.72 | $209,552.77 |
| 5 | CK NEWBERRY, LLC | $1,597,086.50 | $417,286.55 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $108,996 | $109k | 9% |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 1,794 SY | $59.66 | $107k | 9% |
| 247-7179 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | 900 CY | $92.88 | $84k | 7% |
| 530-7016 DRIVEWAYS (SURF TREAT) | 1,657 SY | $48.95 | $81k | 7% |
| 464-7005 RC PIPE (CL III)(24 IN) | 422 LF | $162 | $68k | 6% |
| 530-7010 DRIVEWAYS (ACP) | 1,350 SY | $48.95 | $66k | 6% |
| 464-7003 RC PIPE (CL III)(18 IN) | 459 LF | $128.25 | $59k | 5% |
| 100-7002 PREPARING ROW | 73 STA | $756.9 | $55k | 5% |
| 341-7059 D-GR HMA TY-D PG76-22 (LEVEL-UP) | 237 TON | $224.4 | $53k | 5% |
| 467-7307 SET (TY II) (18 IN) (RCP) (6: 1) (C) | 20 EA | $2,632 | $53k | 4% |