Stenger Concrete Path
Cameron County · est $1.9M
Cameron County · est $1.9M
8 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | EARTHWORKS ENTERPRISE | $1,627,355.47 | — |
| 2 | LUCANIA CONTRACTORS LLC | $1,753,151.60 | $125,796.13 |
| 3 | ASAGO, LLC | $1,783,265.98 | $155,910.51 |
| 4 | ARTILLERY L.L.C. | $1,949,780.00 | $322,424.53 |
| 5 | TEXAS CORDIA CONSTRUCTION, LLC | $2,254,598.00 | $627,242.53 |
| 6 | CLORE EQUIPMENT LLC | $2,338,468.13 | $711,112.66 |
| 7 | P & C OIL FIELD SERVICE LLC | $2,879,208.65 | $1,251,853.18 |
| 8 | FOREMOST PAVING, INC. | $3,376,912.51 | $1,749,557.04 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
Source check time unavailable
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 462-7052 CONC BOX CULV (12 FT X 9 FT) | 116 LF | $2,500 | $290k | 18% |
| 531-7025 CONC SIDEWALKS (SPECIAL) | 3,718 SY | $75 | $279k | 17% |
| 530-7006 DRIVEWAYS (CONC) | 1,067 SY | $79 | $84k | 5% |
| 529-7009 CONC CURB & GUTTER (TY II) | 1,760 LF | $43 | $76k | 5% |
| 260-7005 LIME (COM OR QK)(SLURRY) | 176 TON | $370 | $65k | 4% |
| 160-7002 FURN & PLACE TOPSOIL (4") | 7,864 SY | $7.25 | $57k | 4% |
| 531-7010 CURB RAMPS (TY 7) | 30 EA | $1,870 | $56k | 3% |
| 644-7025 IN SM RD SN SUP&AM TYS80(1)SA(P) | 36 EA | $1,180 | $42k | 3% |
| 432-7002 RIPRAP (CONC)(5 IN) | 95 CY | $400 | $38k | 2% |
| 500-7001 MOBILIZATION | 1 LS | $30,000 | $30k | 2% |