US 183 - Detention Pond
Williamson County · est $1.1M
Williamson County · est $1.1M
4 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | AARON CONCRETE CONTRACTORS, LLC | $922,697.00 | — |
| 2 | DAN WILLIAMS COMPANY | $937,603.72 | $14,906.72 |
| 3 | AUSTIN ENGINEERING CO., INC. | $1,245,746.00 | $323,049.00 |
| 4 | YOKO EXCAVATING, LLC | $1,359,357.55 | $436,660.55 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 432-7003 RIPRAP (CONC)(6 IN) | 470 CY | $700 | $329k | 36% |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 3,640 CY | $65 | $237k | 26% |
| 500-7001 MOBILIZATION | 1 LS | $90,000 | $90k | 10% |
| 7031-7001 BATCH DETENTION SYSTEM | 1 EA | $65,000 | $65k | 7% |
| 458-7001 WATERPROOFING (TY 1) | 282 SY | $110 | $31k | 3% |
| 476-7004 JACK BOR OR TUN PIPE(16 IN)(STL CASING) | 27 LF | $1,000 | $27k | 3% |
| 628-7327 ELC SRV TY T 120/240 000(NS)GS(N)SP(U) | 1 EA | $18,000 | $18k | 2% |
| 618-7037 CONDT (PVC) (SCH 40) (3") (BORE) | 280 LF | $53 | $15k | 2% |
| 110-7003 EXCAV (SPECIAL) | 100 CY | $135 | $14k | 1% |
| 505-7001 TMA (STATIONARY) | 92 DAY | $125 | $12k | 1% |