Replace FM 1835 Bridge Double MTN Fork
Stonewall County · est $8.3M
Stonewall County · est $8.3M
10 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | HODGES AND SON CONSTRUCTION COMPANY, INC. | $3,884,350.00 | — |
| 2 | L & N BRIDGE, LLC | $3,981,565.74 | $97,215.74 |
| 3 | RAGLE CONSTRUCTION, INC. | $4,267,208.80 | $382,858.80 |
| 4 | URBAN INFRACONSTRUCTION LLC | $4,626,000.00 | $741,650.00 |
| 5 | COPPELL CONSTRUCTION CO., INC. | $5,402,560.88 | $1,518,210.88 |
| 6 | EARTH BUILDERS, L.P. | $6,183,843.20 | $2,299,493.20 |
| 7 | JAMES CONSTRUCTION GROUP, LLC | $7,085,132.00 | $3,200,782.00 |
| 8 | ALTUS CONSTRUCTION LLC | $7,280,123.45 | $3,395,773.45 |
| 9 | C. E. BARKER, LTD. | $7,449,534.71 | $3,565,184.71 |
| 10 | GILVIN-TERRILL, LTD. | $7,624,494.88 | $3,740,144.88 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 425-7004 PRESTR CONC GIRDER (TX46) | 3,135 LF | $275 | $862k | 22% |
| 422-7002 REINF CONC SLAB (HPC) | 22,680 SF | $30.5 | $692k | 18% |
| 500-7001 MOBILIZATION | 1 LS | $350,000 | $350k | 9% |
| 416-7006 DRILL SHAFT (36 IN) | 825 LF | $285 | $235k | 6% |
| 496-7011 REMOV STR (BRIDGE 500 - 999 FT LENGTH) | 1 EA | $200,000 | $200k | 5% |
| 450-7009 RAIL (TY T223)(HPC) | 1,324 LF | $150 | $199k | 5% |
| 420-7023 CL C CONC (CAP)(HPC) | 79.5 CY | $2,200 | $175k | 5% |
| 432-7008 RIPRAP (CONC)(CL B)(5 IN) | 201 CY | $750 | $151k | 4% |
| 420-7039 CL C CONC (COLUMN)(HPC) | 92 CY | $1,400 | $129k | 3% |
| 508-7001 CONSTRUCTING DETOURS | 1,493 SY | $62 | $93k | 2% |