Leopard Drive Shared Use Path and Pedest
Bowie County · est $1.2M
Bowie County · est $1.2M
11 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | THK CONSTRUCTION LLC | $942,425.98 | — |
| 2 | HIGHWAY 19 CONSTRUCTION LLC | $1,054,303.00 | $111,877.02 |
| 3 | CDM HOLDINGS | $1,093,184.77 | $150,758.79 |
| 4 | SKYLINE BRIDGE LLC | $1,118,110.00 | $175,684.02 |
| 5 | GARRET SHIELDS INFRASTRUCTURE | $1,132,559.00 | $190,133.02 |
| 6 | EAST TEXAS BRIDGE, INC. | $1,198,651.25 | $256,225.27 |
| 7 | 3LW CIVIL LLC | $1,238,262.12 | $295,836.14 |
| 8 | STX CIVIL | $1,271,023.67 | $328,597.69 |
| 9 | GHB EQUIPMENT COMPANY, L.L.C. | $1,332,727.22 | $390,301.24 |
| 10 | TI-ZACK CONCRETE, LLC | $1,384,537.10 | $442,111.12 |
| 11 | ICOS MANAGEMENT, LLC | $1,438,797.75 | $496,371.77 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
Source check time unavailable
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 531-7001 CONC SIDEWALKS (4") | 3,881 SY | $74 | $287k | 30% |
| 530-7006 DRIVEWAYS (CONC) | 1,393 SY | $85 | $118k | 13% |
| 500-7001 MOBILIZATION | 1 LS | $95,000 | $95k | 10% |
| 450-7062 RAIL (HANDRAIL)(TY E) | 502 LF | $110.54 | $55k | 6% |
| 162-7002 BLOCK SODDING | 7,331 SY | $5.57 | $41k | 4% |
| 275-7028 CEMENT TRT (SUBGRADE)(10") | 3,318 SY | $10 | $33k | 4% |
| 505-7001 TMA (STATIONARY) | 126 DAY | $200 | $25k | 3% |
| 531-7010 CURB RAMPS (TY 7) | 7 EA | $3,500 | $25k | 3% |
| 529-7022 CONC CURB (TY F3) | 191 LF | $120 | $23k | 2% |
| 506-7039 TEMP SEDMT CONT FENCE (INSTALL) | 4,830 LF | $4 | $19k | 2% |