FY 2026 BPM
El Paso County · est $861k
El Paso County · est $861k
7 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | PREMIER CONTRACTORS LLC | $555,941.00 | — |
| 2 | ICOS MANAGEMENT, LLC | $681,375.00 | $125,434.00 |
| 3 | SCR CIVIL CONSTRUCTION, LLC | $778,377.00 | $222,436.00 |
| 4 | SYNERGY PROJECT CONTRACTORS, INC. | $830,733.81 | $274,792.81 |
| 5 | HAWK CONSTRUCTION | $857,040.50 | $301,099.50 |
| 6 | INTERNATIONAL EAGLE ENTERPRISES, INC. | $877,926.00 | $321,985.00 |
| 7 | STRUCTURAL INTEGRITY GROUP LLC | $914,108.00 | $358,167.00 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 830 SF | $300 | $249k | 45% |
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 1,194 LF | $50 | $60k | 11% |
| 785-7009 BRIDGE JOINT REPLACEMENT (CONCRETE) | 260 LF | $200 | $52k | 9% |
| 500-7001 MOBILIZATION | 1 LS | $50,000 | $50k | 9% |
| 780-7003 CONC CRCK REPR(DISCRETE)(ROUT AND SEAL) | 747 LF | $50 | $37k | 7% |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 625 LF | $30 | $19k | 3% |
| 785-7001 BRIDGE JOINT REPAIR (CONCRETE) | 92 LF | $200 | $18k | 3% |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 36 SF | $500 | $18k | 3% |
| 785-7013 BRIDGE JOINT REPLACEMENT (HEADER) | 40 LF | $400 | $16k | 3% |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) |
| 4 EA |
| $2,800 |
| $11k |
| 2% |