FM 104 Widening
Cottle County · est $6.1M
Cottle County · est $6.1M
8 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | ZACK BURKETT CO. | $6,279,570.48 | — |
| 2 | RK HALL, LLC | $6,587,854.34 | $308,283.86 |
| 3 | A. L. HELMCAMP, INC. | $6,868,027.41 | $588,456.93 |
| 4 | J. LEE MILLIGAN, INC. | $6,993,551.55 | $713,981.07 |
| 5 | OVERLAND CORPORATION | $7,276,182.79 | $996,612.31 |
| 6 | DUININCK, INC. | $7,520,462.22 | $1,240,891.74 |
| 7 | L A FULLER & SONS CONSTRUCTION, LTD. | $8,086,444.52 | $1,806,874.04 |
| 8 | GILVIN-TERRILL, LTD. | $8,114,353.73 | $1,834,783.25 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
Source check time unavailable
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 341-7053 D-GR HMA TY-D SAC-A PG70-28 | 20,499 TON | $128 | $2.62M | 42% |
| 341-7009 D-GR HMA TY-B PG70-28 | 11,585 TON | $135 | $1.56M | 25% |
| 500-7001 MOBILIZATION | 1 LS | $423,500 | $424k | 7% |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 48 EA | $3,850 | $185k | 3% |
| 112-7001 SUBGR WIDEN (OC) | 533 STA | $292 | $156k | 2% |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 161 CY | $825 | $133k | 2% |
| 480-7001 CLEAN EXIST CULVERTS | 22 EA | $5,500 | $121k | 2% |
| 314-7011 EMULS ASPH (EROSN CONT)(CSS-1H) | 28,977 GAL | $3.95 | $114k | 2% |
| 134-7004 BACKFILL (TY A OR B) | 559 STA | $150 | $84k | 1% |
| 110-7002 EXCAV (CHANNEL) | 5,550 CY | $15 | $83k | 1% |