FUA Erosion Repair
Lamar County · est $424k
Lamar County · est $424k
9 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | SHALOM SERVICES CORPORATION | $309,933.00 | — |
| 2 | BECK-REIT & SONS, LTD. | $321,479.00 | $11,546.00 |
| 3 | RHINO EQUITY, LLC | $384,711.00 | $74,778.00 |
| 4 | PATHFIELD INVESTMENTS LLC | $387,461.00 | $77,528.00 |
| 5 | SCOUT 5 CONSTRUCTION LLC | $396,733.40 | $86,800.40 |
| 6 | GARRET SHIELDS INFRASTRUCTURE | $418,278.00 | $108,345.00 |
| 7 | CROSS PLUS CONSTRUCTION, LLC | $480,667.00 | $170,734.00 |
| 8 | THK CONSTRUCTION LLC | $498,563.00 | $188,630.00 |
| 9 | HIGHWAY 19 CONSTRUCTION LLC | $506,925.00 | $196,992.00 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 895 CY | $175 | $157k | 51% |
| 432-7001 RIPRAP (CONC)(4 IN) | 38 CY | $800 | $30k | 10% |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 103 SF | $195 | $20k | 6% |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 100 CY | $200 | $20k | 6% |
| 401-7001 FLOWABLE BACKFILL | 42 CY | $450 | $19k | 6% |
| 500-7001 MOBILIZATION | 1 LS | $15,000 | $15k | 5% |
| 162-7002 BLOCK SODDING | 17 SY | $500 | $9k | 3% |
| 132-7015 EMBANK (VEH)(OC)(TY B) | 239 CY | $33 | $8k | 3% |
| 540-7027 MTL BM GD FEN (LONG SPAN SYSTEM) | 3 EA | $2,500 | $8k | 2% |
| 104-7006 REMOV CONC (RIPRAP) | 349 SY | $20 | $7k | 2% |