VA: 0915-00-306; Lse
Bexar County · est $2.6M
Bexar County · est $2.6M
5 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | CENTRAL NORTH CONSTRUCTION, LLC | $2,101,093.30 | — |
| 2 | APEX LANDSCAPE & IRRIGATION, LLC | $2,935,021.40 | $833,928.10 |
| 3 | ABESCAPE LANDSCAPING, LLC | $2,950,182.80 | $849,089.50 |
| 4 | YELLOWSTONE LANDSCAPE - CENTRAL, INC. | $3,291,814.70 | $1,190,721.40 |
| 5 | TIGHT LINE CONSTRUCTION, LLC | $3,391,190.00 | $1,290,096.70 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 193-7026 LANDSCAPE TREAT (TY II) | 8 CYC | $38,500 | $308k | 15% |
| 192-7033 PLANT MATERIAL (65 GAL) | 378 EA | $800 | $302k | 14% |
| 192-7039 PLANT MATERIAL (30 GAL) (TREE) | 629 EA | $400 | $252k | 12% |
| 193-7001 LANDSCAPE ESTABLISH | 24 MO | $10,000 | $240k | 11% |
| 162-7002 BLOCK SODDING | 16,741 SY | $6 | $100k | 5% |
| 500-7001 MOBILIZATION | 1 LS | $100,000 | $100k | 5% |
| 170-7008 IRRIGATION SYSTEM (LOC A) | 1 EA | $77,456 | $77k | 4% |
| 180-7001 WILDFLOWER SEEDING | 22.74 AC | $2,900 | $66k | 3% |
| 161-7008 EROSION CONTROL COMPOST (VEH) | 1,154 CY | $45 | $52k | 2% |
| 170-7009 IRRIGATION SYSTEM (LOC B) | 1 EA | $50,000 | $50k | 2% |