2025-02 Nacogdoches MBGF
Nacogdoches County · est $130k
Nacogdoches County · est $130k
5 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | ACE CONTRACTORS, INC. | $98,012.00 | — |
| 2 | AAD CONTRACTING INC. | $119,360.00 | $21,348.00 |
| 3 | BK FIELD OPERATIONS LLC | $125,279.00 | $27,267.00 |
| 4 | LAKEY, INC. | $167,319.92 | $69,307.92 |
| 5 | ISI CONTRACTING, INC. | $246,893.00 | $148,881.00 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 770-7001 REPLACE RAIL ELEMENT (W-BEAM) | 700 LF | $35 | $25k | 25% |
| 770-7013 REM OBSOLETE GET & REPL W/ SGT | 3 EA | $6,000 | $18k | 18% |
| 544-7001 GUARDRAIL END TREATMENT (INSTALL) | 7 EA | $2,000 | $14k | 14% |
| 505-7001 TMA (STATIONARY) | 30 DAY | $400 | $12k | 12% |
| 500-7002 MOBILIZATION (CALLOUT) | 10 EA | $750 | $8k | 8% |
| 774-7032 REPAIR (WIDE QUAD) | 2 LF | $2,500 | $5k | 5% |
| 540-7005 MTL BEAM GD FEN TRANS (THRIE-BEAM) | 2 EA | $1,250 | $3k | 3% |
| 778-7001 CONCRETE RAIL REPAIR (IN-KIND) | 50 LF | $50 | $3k | 3% |
| 770-7016 REPLACE SINGLE GDRAIL TERMINAL RAIL | 60 LF | $40 | $2k | 2% |
| 770-7015 REPL SINGLE GDRAIL TERM IMPACT HEAD | 4 EA | $500 | $2k |
| 2% |