BPM Lamar FY26
Lamar County · est $335k
Lamar County · est $335k
4 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | BK FIELD OPERATIONS LLC | $224,665.00 | — |
| 2 | GARRET SHIELDS INFRASTRUCTURE | $313,714.00 | $89,049.00 |
| 3 | GREY SKY CONSTRUCTION LLC | $387,620.00 | $162,955.00 |
| 4 | CATOCON, INC. | $536,890.00 | $312,225.00 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 292 CY | $210 | $61k | 27% |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 223 CY | $210 | $47k | 21% |
| 446-7008 CLEAN & PAINT EXIST PILING (SYSTEM II) | 1 LS | $37,950 | $38k | 17% |
| 500-7001 MOBILIZATION | 1 LS | $28,000 | $28k | 12% |
| 420-7060 CL C CONC (PILE ENCASEMENT) | 3 CY | $9,000 | $27k | 12% |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 167 SF | $120 | $20k | 9% |
| 401-7001 FLOWABLE BACKFILL | 4 CY | $300 | $1k | 1% |
| 162-7002 BLOCK SODDING | 20 SY | $50 | $1k | 0% |
| 104-7006 REMOV CONC (RIPRAP) | 12 SY | $75 | $900 | 0% |
| 132-7015 EMBANK (VEH)(OC)(TY B) | 292 CY | $1 | $292 | 0% |