FY 26 Bridge Maintenance
Bexar County · est $1.6M
Bexar County · est $1.6M
5 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | ROY JORGENSEN ASSOCIATES, INC. | $1,143,629.00 | — |
| 2 | RELMCO, INC. | $1,540,980.00 | $397,351.00 |
| 3 | TAYLOR CONTRACTING LLC | $1,562,950.00 | $419,321.00 |
| 4 | GARRET SHIELDS INFRASTRUCTURE | $1,567,450.00 | $423,821.00 |
| 5 | BK FIELD OPERATIONS LLC | $1,609,055.00 | $465,426.00 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 1,375 LF | $120 | $165k | 14% |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 500 SF | $300 | $150k | 13% |
| 361-7047 FULL-DEPTH REP(BR APPR SLAB)(9"-13") | 100 CY | $1,200 | $120k | 10% |
| 721-7001 FIBER REINFORCED POLYMER PATCHING MATLS | 11,880 LB | $10 | $119k | 10% |
| 778-7001 CONCRETE RAIL REPAIR (IN-KIND) | 200 LF | $550 | $110k | 10% |
| 778-7004 CONCRETE RAIL REPLACEMENT (IN-KIND) | 200 LF | $400 | $80k | 7% |
| 361-7044 FULL-DEPTH REPAIR CRCP (VAR DEPTH) | 100 CY | $635 | $64k | 6% |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 500 SF | $90 | $45k | 4% |
| 480-7002 CLEAN EXIST CULVERTS | 500 CY | $90 | $45k | 4% |
| 785-7002 BRIDGE JOINT REPAIR (HEADER) |
| 300 LF |
| $145 |
| $44k |
| 4% |