BPM - SH352 @ White Rock Creek 03 1025
Dallas County · est $536k
Dallas County · est $536k
6 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | GIBSON & ASSOCIATES, INC. | $299,758.38 | — |
| 2 | RAGLE CONSTRUCTION, INC. | $383,297.00 | $83,538.62 |
| 3 | PREMIER CONTRACTORS LLC | $405,433.00 | $105,674.62 |
| 4 | GARRET SHIELDS INFRASTRUCTURE | $418,835.00 | $119,076.62 |
| 5 | STRUCTURAL INTEGRITY GROUP LLC | $433,613.00 | $133,854.62 |
| 6 | PATHFIELD INVESTMENTS LLC | $509,170.00 | $209,411.62 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 350 SF | $218.9 | $77k | 26% |
| 347-7001 TOM-C PG76-22 SAC-A | 56 TON | $891 | $50k | 17% |
| 500-7001 MOBILIZATION | 1 LS | $36,700 | $37k | 12% |
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 150 SF | $202 | $30k | 10% |
| 780-7001 CNC CRACK REPAIR (DISCRETE)(GRAVITY) | 750 LF | $27 | $20k | 7% |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 190 SF | $105 | $20k | 7% |
| 354-7045 PLANE ASPH CONC PAV(0" TO 1" MICRO) | 928 SY | $15.51 | $14k | 5% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $6,200 | $12k | 4% |
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7) | 200 LF | $38.5 | $8k | 3% |
| 506-7020 CONSTRUCTION EXITS (INSTALL) (TY 1) |
| 350 SY |
| $22 |
| $8k |
| 3% |