Culvert Replacement 07 10.25
Collin County · est $452k
Collin County · est $452k
4 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | AAD CONTRACTING INC. | $461,459.00 | — |
| 2 | HIGHWAY 19 CONSTRUCTION LLC | $512,778.00 | $51,319.00 |
| 3 | ED BELL CONSTRUCTION COMPANY | $578,945.00 | $117,486.00 |
| 4 | GARRET SHIELDS INFRASTRUCTURE | $582,647.00 | $121,188.00 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 464-7011 RC PIPE (CL III)(48 IN) | 345 LF | $275 | $95k | 21% |
| 400-7010 CEM STABIL BKFL | 210 CY | $250 | $53k | 11% |
| 466-7056 HEADWALL (CH - FW - 45) (DIA= 48 IN) | 2 EA | $25,000 | $50k | 11% |
| 500-7001 MOBILIZATION | 1 LS | $50,000 | $50k | 11% |
| 403-7001 TEMPORARY SPL SHORING | 2,606 SF | $15 | $39k | 8% |
| 401-7001 FLOWABLE BACKFILL | 134 CY | $250 | $34k | 7% |
| 400-7006 CUT & RESTORING PAV | 176 SY | $150 | $26k | 6% |
| 496-7007 REMOV STR (PIPE) | 468 LF | $50 | $23k | 5% |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 240 CY | $70 | $17k | 4% |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 74 CY | $220 | $16k | 4% |