US 59 Hillje Truck Stop Accel/Decel Lane
Wharton County · est $839k
Wharton County · est $839k
2 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | HUNTER INDUSTRIES, LTD. | $933,297.28 | — |
| 2 | TEXAS MATERIALS GROUP, INC. | $1,028,683.25 | $95,385.97 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
Bid tab · TxDOT
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 341-7001 D-GR HMA TY-B PG64-22 | 3,542 TON | $113.3 | $401k | 43% |
| 341-7050 D-GR HMA TY-D SAC-B PG70-22 | 648 TON | $150.7 | $98k | 10% |
| 500-7001 MOBILIZATION | 1 LS | $92,622 | $93k | 10% |
| 342-7001 PFC-C PG76-22 SAC-A | 376 TON | $209 | $79k | 8% |
| 112-7001 SUBGR WIDEN (OC) | 33.2 STA | $1,709 | $57k | 6% |
| 545-7006 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3) | 1 EA | $32,000 | $32k | 3% |
| 432-7003 RIPRAP (CONC)(6 IN) | 30 CY | $900 | $27k | 3% |
| 514-7001 PERM CTB (SGL SLOPE) (TY 1) (42 ) | 90 LF | $290 | $26k | 3% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $10,000 | $20k | 2% |
| 530-7006 DRIVEWAYS (CONC) | 74 SY | $180 | $13k | 1% |