Miscellaneous Bridge Repair (BPM 2027)
Comanche County · est $981k
Comanche County · est $981k
11 published bidders
| Rank | Contractor | Published bid | Gap to low bid |
|---|---|---|---|
| 1Low bid | TAYLOR BRIDGE LLC | $727,661.05 | — |
| 2 | STRUCTURAL INTEGRITY GROUP LLC | $854,441.65 | $126,780.60 |
| 3 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC | $961,691.00 | $234,029.95 |
| 4 | THE TRUESDELL CORPORATION | $1,041,041.00 | $313,379.95 |
| 5 | BLACKSMITH VENTURES LLC | $1,183,371.35 | $455,710.30 |
| 6 | ICOS MANAGEMENT, LLC | $1,217,844.96 | $490,183.91 |
| 7 | SCR CIVIL CONSTRUCTION, LLC | $1,251,601.05 | $523,940.00 |
| 8 | COPPELL CONSTRUCTION CO., INC. | $1,306,823.50 | $579,162.45 |
| 9 | REAR CONTRACTORS LLC | $1,382,356.50 | $654,695.45 |
| 10 | THK CONSTRUCTION LLC | $1,424,773.72 | $697,112.67 |
| 11 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | $1,925,646.65 | $1,197,985.60 |
Source: TxDOT published bid tab. Low bid is the source-published position; it does not establish an agency award.
Review bid results in Workspace →Workspace access is required. The $199 project briefing is a separate purchase.
TxDOT source checked
No addenda matched in the stored source. Check TxDOT for current revisions before bidding.
Stored revisions can change. Confirm the current proposal and all applicable addenda with TxDOT.
How to read this. Bid amounts and plan requests are published TxDOT facts. Low bid describes a published position; it does not establish an agency award. Contractor links require an exact, unique match to the official vendor directory. Confirm current proposal revisions with TxDOT before bidding. More on what Cassandri does →
Bid tab · TxDOT
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 432-7044 RIPRAP (STONE PROTECTION)(21 IN) | 270 CY | $325 | $88k | 12% |
| 420-7059 CL C CONC(PILE ENCASEMENT) | 216 LF | $350 | $76k | 10% |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 96 SF | $750 | $72k | 10% |
| 787-7001 REPLACING ELASTOMERIC BEARING PADS | 10 EA | $5,500 | $55k | 8% |
| 401-7001 FLOWABLE BACKFILL | 167 CY | $320 | $53k | 7% |
| 735-7060 DRIFTWOOD REMOVAL | 289 CY | $150 | $43k | 6% |
| 4010-7001 STEEL BRIDGE ZONE PAINTING REF STR #1 | 1 EA | $30,000 | $30k | 4% |
| 4010-7003 STEEL BRIDGE ZONE PAINTING REF STR #2 | 1 EA | $30,000 | $30k | 4% |
| 4010-7004 STEEL BRIDGE ZONE PAINTING REF STR #3 | 1 EA | $30,000 | $30k | 4% |
| 788-7003 CONCRETE BEAM REP(STRAND SPLICE & CFRP) |
| 2 EA |
| $12,500 |
| $25k |
| 3% |