Texas DOT vendor directory and published bid history
Vendor source checked · TxDOT vendor source ↗
417 matched projects
| Position | Project | County | Bid date | Published bid | Low bid |
|---|---|---|---|---|---|
| Rank 3of 7 | INSTALLATION OF CONCRETE TRAFFIC BARRIER | EL PASO | 2020-08-05 | $2,682,661.55 | $2,235,501.70 |
| Rank 6of 7 | INSTALLATION OF BOX CULVERT AND ROADWAY APPROACHES | HUDSPETH | 2020-08-05 | $587,166.20 | $423,112.00 |
| Rank 2of 5 | RECONSTRUCT EXST 2-LN RDWY TO A 4-LN RDWY W/CLTL | TRAVIS | 2020-07-08 | $10,839,240.31 | $10,089,973.35 |
| Rank 2of 11 | INSTALL MEDIAN CABLE BARRIER | EL PASO | 2020-07-08 | $4,244,799.00 | $4,020,479.50 |
| Low bidof 4 | CONSTRUCT ASPHALT CONCRETE PVMNT MILL AND INLAY | EL PASO | 2020-06-05 | $9,796,784.10 | $9,796,784.10 |
| Rank 6of 7 | HAZARD ELIMINATION & SAFETY | BASTROP | 2020-06-05 | $2,162,034.80 | $1,850,411.75 |
| Rank 3of 11 | ROADWAY REHABILITATION | REEVES | 2020-06-05 | $5,403,836.80 | $5,198,387.00 |
| Low bidof 5 | HIGHWAY IMPROVEMENT | WILLIAMSON | 2020-06-04 | $1,496,432.62 | $1,496,432.62 |
| Low bidof 8 | MILL & OVERLAY CLEANING/RESEAL BRIDGE JOINTS | EL PASO | 2020-06-04 | $777,686.30 | $777,686.30 |
| Rank 2of 5 | BRIDGE REPAIR | REEVES | 2020-06-04 | $842,510.00 | $831,572.20 |
| Rank 6of 10 | INTERSECT OPER IMPROV & INCL WIDEN CIBOLO CRK BRDG | BEXAR | 2020-05-08 | $7,995,410.49 | $6,580,022.65 |
| Rank 7of 7 | ROADWAY REHABILITATION | REEVES | 2020-05-08 | $70,951,914.69 | $62,350,992.18 |
| Rank 5of 7 | REPLACE SUBSTANDARD METAL BEAM GUARD FENCE | HUDSPETH | 2020-05-08 | $2,118,291.40 | $1,883,865.28 |
| Rank 2of 7 | REHABILITATION OF ROADWAY | EL PASO | 2020-05-08 | $2,294,310.10 | $2,225,974.74 |
| Rank 5of 9 | BPM | EL PASO | 2020-05-08 | $545,446.00 | $485,854.80 |
| Rank 9of 10 | CONSTRUCT SUPER 2 PASSING LANES | LLANO | 2020-05-07 | $6,237,818.99 | $4,653,514.57 |
| Rank 3of 10 | FY 2020 BRIDGE MAINTENANCE (EL PASO COUNTY) | EL PASO | 2020-05-07 | $2,850,727.50 | $2,570,503.40 |
| Rank 3of 3 | FLEXIBLE PAVEMENT REPAIR | CULBERSON | 2020-05-07 | $529,600.00 | $431,376.00 |
| Low bidof 5 | CONSTRUCTION OF SHARED USE PATH AND SIDEWALKS | PRESIDIO | 2020-04-09 | $531,477.00 | $531,477.00 |
| Rank 5of 6 | MILL AND INLAY (FRONTAGE ROAD) | EL PASO | 2020-04-09 | $1,016,093.40 | $719,532.16 |
| Rank 5of 6 | BRIDGE REPAIR (CALLOUT) | PECOS | 2020-04-09 | $928,750.00 | $429,900.00 |
| Rank 3of 7 | ROADWAY REHABILITATION | REEVES | 2020-04-08 | $22,479,609.81 | $20,145,622.79 |
| Rank 2of 4 | UPGRADE BRIDGE AND APPROACH RAILING, REHABILITATE | WILLIAMSON | 2020-04-08 | $994,024.00 | $939,068.96 |
| Low bidof 2 | RETAINING WALL RAIL RETROFIT | BEXAR | 2020-03-17 | $370,996.50 | $370,996.50 |
| Low bidof 6 | INSTALL MEDIAN BARRIER | TRAVIS | 2020-03-04 | $1,310,000.00 | $1,310,000.00 |
Source: published TxDOT bid tabs. History matches the exact official vendor name and case variants; punctuation and similarly named firms remain separate. Different spellings or name changes may leave relevant bids unmatched. Low bid is a published position, not a separately verified agency award.