| Result | Project | County | Let | Their bid | Winning bid |
|---|---|---|---|---|---|
| Rank 4of 4 | TUS-IR 77-01.21Drainage | TUS | Jul 2025 | $691k | $298k |
| Rank 2of 2 | COL-SR 45-23.72Drainage | COL | Feb 2024 | $393k | $269k |
| Wonof 2 | D01-BM FY23Drainage | D01 | Feb 2023 | $741k | $741k |
| Rank 5of 5 | D01-CR FY22Drainage | D01 | Jan 2022 | $464k | $230k |
| Rank 6of 6 | CLI-Culverts FY22Drainage | CLI | Dec 2021 | $367k | $177k |
| Rank 2of 4 | MED-IR 76-01.80Maintenance | MED | Apr 2021 | $273k | $195k |
| Rank 5of 8 | D09-CR-FY2021Drainage | D09 | Jan 2021 | $988k | $575k |
| Rank 2of 2 | D01-CR FY20Maintenance | D01 | May 2020 | $429k | $298k |
| Rank 3of 8 | D10-Culverts FY2020ADrainage | D10 | Mar 2020 | $192k | $145k |
| Rank 8of 9 | BRO-/ROS-SR 32/US 35-07.43/09.28Drainage | BRO | Mar 2020 | $424k | $250k |
| Rank 6of 6 | CLE-/WAR Culverts FY20 (B)Drainage | CLE | Feb 2020 | $289k | $194k |
| Rank 2of 7 | HAM-Culverts FY19Drainage | HAM | Oct 2018 | $963k | $568k |
| Rank 3of 3 | DAR-BH FY18 (C)Maintenance | DAR | Feb 2018 | $185k | $121k |
| Rank 4of 4 | MED-US 42-06.75Drainage | MED | Jan 2018 | $478k | $309k |