ASD-/LOR MICRO FY2018
ASD County · est $1.0M
Bid dateThursday, May 3—
ASD County · est $1.0M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 4%
Bid form · ODOT
| Item | Qty | Unit price |
|---|
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 13 more items below.
| Item | Quantity | R1American Pavements INC | R2Strawser Construction INC | R3Microsurfacing Contractors LLC | % of bid |
|---|---|---|---|---|---|
| 421E10011 MICROSURFACING, SURFACE COURSE, AS PER PLAN (24 LB | 211,184 SY | $2.70 | $2.65 | $3.32 | 57% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 725 CY | $270 | $275 | $367 | 20% |
| 624E10000 MOBILIZATION | 1 LS | $30,000 | $63,000 | $40,000 | 3% |
| 643E30030 REMOVAL OF PAVEMENT MARKING(EXISTING EDGE LINES) | 13.12 MILE | $1,980 | $2,000 | $1,980 | 3% |
| 644E30030 REMOVAL OF PAVEMENT MARKING (EXISTING EDGE LINES) | 10.94 MILE | $1,980 |
| Item | Quantity | R1American Pavements INC | R2Strawser Construction INC | R3Microsurfacing Contractors LLC |
|---|---|---|---|---|
| 642E00400 CHANNELIZING LINE, 8", TYPE 1 | 682 FT | $1.15 | $1.16 | $1.15 |
| 642E00500 STOP LINE, TYPE 1 | 421 FT | $3.10 | $3.33 | $3.10 |
| 642E00700 TRANSVERSE/DIAGONAL LINE, TYPE 1 | 348 FT | $2.85 | $3.00 | $2.85 |
| 642E01110 SCHOOL SYMBOL MARKING, 96", TYPE 1 | 1 EACH | $500 | $510 | $500 |
| 642E01300 LANE ARROW, TYPE 1 | 9 EACH | $55.00 | $56.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $2,000 |
| $1,980 |
| 2% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 24.06 MILE | $835 | $875 | $835 | 2% |
| 621E00100 RPM | 877 EACH | $19.75 | $20.00 | $19.75 | 2% |
| 643E30030 REMOVAL OF PAVEMENT MARKING(EXISTING CENTER LINES) | 6.56 MILE | $2,135 | $2,200 | $2,135 | 1% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 24.06 MILE | $565 | $575 | $565 | 1% |
| 253E02000 PAVEMENT REPAIR | 50 CY | $270 | $275 | $386 | 1% |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 877 EACH | $14.30 | $19.00 | $20.00 | 1% |
| 644E30030 REMOVAL OF PAVEMENT MARKING (EXISTING CENTER LINES | 5.47 MILE | $2,160 | $2,200 | $2,160 | 1% |
| 618E41000 EDGE LINE, RUMBLE STRIPE (ASPHALT CONCRETE) | 23.95 MILE | $385 | $1,500 | $1,250 | 1% |
| 897E01010 PAVEMENT PLANING, ASPHALT CONCRETE, CLASS A (BUTT | 676 SY | $13.00 | $13.50 | $20.50 | 1% |
| 614E12460 WORK ZONE MARKING SIGN | 106 EACH | $77.25 | $80.00 | $55.00 | 1% |
| 642E00300 CENTER LINE, TYPE 1 | 12.03 MILE | $600 | $625 | $600 | 1% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $5,500 | $59,999 | $45,000 | 1% |
| 103E06000 PREMIUM FOR CONTRACT PERFORMANCE BOND, PAYMENT BON | 1 LS | $5,000 | $5,500 | $7,900 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $2,711 | $900 | $5,000 | 0% |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 20 HOUR | $75.00 | $70.00 | $75.00 | 0% |
| $55.00 |
| 644E30000 REMOVAL OF PAVEMENT MARKING (EXISTING CHANNELIZING | 682 FT | $1.00 | $1.01 | $1.00 |
| 644E30000 REMOVAL OF PAVEMENT MARKING (EXISTING STOP LINES) | 84 FT | $3.00 | $3.10 | $3.00 |
| 644E30000 REMOVAL OF PAVEMENT MARKING (EXISTING TRANSVERSE L | 348 FT | $3.00 | $3.10 | $3.00 |
| 644E30020 REMOVAL OF PAVEMENT MARKING (EXISTING SCHOOL SYMBO | 1 EACH | $250 | $255 | $250 |
| 644E30020 REMOVAL OF PAVEMENT MARKING(EXISTING LANE ARROWS) | 9 EACH | $100 | $101 | $100 |
| 614E23680 WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA | 1,364 FT | $0.50 | $0.51 | $0.50 |
| 614E26610 WORK ZONE STOP LINE, CLASS III, 642 PAINT | 84 FT | $2.40 | $2.41 | $2.40 |
| 619E16010 FIELD OFFICE, TYPE B | 3 MNTH | $200 | $1,200 | $3,500 |
| Extended |
|---|
| % |
|---|
| 421E10011 MICROSURFACING, SURFACE COURSE, AS PER PLAN (24 LB | 211,184 SY | $2.7 | $570k | 57% |
| 251E01042 PARTIAL DEPTH PAVEMENT REPAIR (ASPHALT CONCRETE BA | 725 CY | $270 | $196k | 20% |
| 624E10000 MOBILIZATION | 1 LS | $30,000 | $30k | 3% |
| 643E30030 REMOVAL OF PAVEMENT MARKING(EXISTING EDGE LINES) | 13.12 MILE | $1,980 | $26k | 3% |
| 644E30030 REMOVAL OF PAVEMENT MARKING (EXISTING EDGE LINES) | 10.94 MILE | $1,980 | $22k | 2% |
| 614E21550 WORK ZONE CENTER LINE, CLASS III, 642 PAINT | 24.06 MILE | $835 | $20k | 2% |
| 621E00100 RPM | 877 EACH | $19.75 | $17k | 2% |
| 643E30030 REMOVAL OF PAVEMENT MARKING(EXISTING CENTER LINES) | 6.56 MILE | $2,135 | $14k | 1% |
| 642E00104 EDGE LINE, 6", TYPE 1 | 24.06 MILE | $565 | $14k | 1% |
| 253E02000 PAVEMENT REPAIR | 50 CY | $270 | $14k | 1% |