HAM-IR 75-08.91 Pump Station & CSO
HAM County · est $15M
Bid dateThursday, April 4—
HAM County · est $15M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 140 more items below.
| Item | Quantity | R1John R Jurgensen Company | R2Sunesis Construction CO | % of bid |
|---|---|---|---|---|
| 690E98400 SPECIAL - STORMWATER DETENTION SYSTEM 6 | 1 LS | $3,739,849 | $3,630,705 | 21% |
| 690E98400 SPECIAL - STORMWATER PUMP STATION STRUCTURE | 1 LS | $3,385,300 | $4,086,025 | 19% |
| 690E98400 SPECIAL - PUMP STATION BUILDING AND CONTROLS | 1 LS | $1,650,000 | $295,741 | 9% |
| 638E98600 WATER WORK, MISC.: 36" WATER MAIN DUCTILE IRON PIP | 1,368 FT | $872 | $735 | 7% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $1,038,069 | $367,378 | 6% |
| 638E07330 54" STEEL PIPE ENCASEMENT, BORED OR JACKED | 528 FT | $1,950 | $2,513 | 6% |
| 611E21100 48" CONDUIT, TYPE C | 1,482 FT | $638 | $315 | 5% |
| 611E26400 72" CONDUIT, TYPE C | 657 FT | $1,262 | $713 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $800,000 | $600,057 | 5% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN STO | 1 LS | $450,132 | $2,642,809 | 3% |
| 611E96600 CONDUIT, BORED OR JACKED, 15" TYPE B, 748.01 WITH | 368 FT | $1,114 | $1,278 | 2% |
| 503E11100 COFFERDAMS AND EXCAVATION BRACING | 1 LS | $380,561 | $93,062 | 2% |
| 611E99920 DRAINAGE STRUCTURE, MISC.: CSO VAULT 25' L X 13' W | 1 LS | $337,873 | $488,437 | 2% |
| 611E96600 CONDUIT, BORED OR JACKED, 48" TYPE C | 197 FT | $1,238 | $1,418 | 1% |
| 611E99690 MANHOLE, MISC.: SANITARY MANHOLE PER MSD STD ACC. | 4 EACH | $46,927 | $14,263 | 1% |
| 611E96600 CONDUIT, BORED OR JACKED, 42" TYPE B | 149 FT | $1,238 | $1,245 | 1% |
| 622E41100 PORTABLE BARRIER, UNANCHORED | 4,090 FT | $43.64 | $37.66 | 1% |
| 611E21100 48" CONDUIT, TYPE C, WITH CLASS II BEDDING | 171 FT | $928 | $836 | 1% |
| 203E10000 EXCAVATION | 5,442 CY | $28.23 | $39.07 | 1% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $136,067 | $129,001 | 1% |
| Item | Quantity | R1John R Jurgensen Company | R2Sunesis Construction CO |
|---|---|---|---|
| 202E98500 REMOVAL MISC.: PAVEMENT | 1,450 CY | $43.06 | $30.90 |
| 202E32000 CURB REMOVED | 48 FT | $12.48 | $13.08 |
| 202E32500 CURB AND GUTTER REMOVED | 71 FT | $12.49 | $8.57 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 37 FT | $199 | $19.41 |
| 202E35200 PIPE REMOVED, OVER 24" | 81 FT | $332 | $23.46 |
| 202E38000 GUARDRAIL REMOVED | 836 FT | $6.00 | $6.00 |
| 202E56101 BUILDING DEMOLISHED, AS PER PLAN - PARCEL# 056-006 | 1 EACH |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $18,100 |
| $22,000 |
| 202E58000 MANHOLE REMOVED | 3 EACH | $2,363 | $682 |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT, 12" DIA. | 122 FT | $54.34 | $10.97 |
| 202E70110 SPECIAL - PIPE CLEANOUT, 24" AND UNDER | 100 FT | $144 | $100 |
| 202E70120 SPECIAL - PIPE CLEANOUT, 27" TO 48" | 100 FT | $169 | $125 |
| 202E70130 SPECIAL - PIPE CLEANOUT OVER 48" | 100 FT | $194 | $150 |
| 202E75000 FENCE REMOVED | 3,053 FT | $5.00 | $5.00 |
| 202E98100 REMOVAL MISC.: BILLBOARD | 2 EACH | $11,000 | $16,500 |
| 202E98100 REMOVAL MISC.: LIGHT POLE | 1 EACH | $1,000 | $1,063 |
| 203E20000 EMBANKMENT | 570 CY | $40.17 | $13.18 |
| 204E10000 SUBGRADE COMPACTION | 842 SY | $4.41 | $4.58 |
| 606E15050 GUARDRAIL, TYPE MGS | 688 FT | $20.00 | $20.00 |
| 606E26100 ANCHOR ASSEMBLY, TYPE E (MASH 2016) | 2 EACH | $2,600 | $2,600 |
| 606E35002 MGS BRIDGE TERMINAL ASSEMBLY, TYPE 1 | 2 EACH | $2,450 | $2,450 |
| 607E23000 FENCE, TYPE CLT | 2,458 FT | $28.00 | $28.00 |
| 607E61200 GATE, TYPE CLT | 3 EACH | $5,350 | $5,350 |
| 608E10000 4" CONCRETE WALK | 15 SF | $117 | $17.95 |
| 622E25000 CONCRETE BARRIER END SECTION, TYPE D | 1 EACH | $8,732 | $2,312 |
| 690E50600 SPECIAL - BOLLARD | 32 EACH | $625 | $625 |
| 690E99550 SPECIAL - TEMPORARY 600 KW GENERATOR | 4 MNTH | $20,000 | $15,773 |
| 202E98510 REMOVAL MISC.: CONCRETE FOUNDATION REMOVED | 40 MNHR | $675 | $583 |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN, JA | 1 LS | $1,000 | $75,645 |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN, JA | 1 LS | $1,000 | $25,039 |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN, JA | 1 LS | $1,000 | $57,045 |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN, JA | 1 LS | $1,000 | $73,943 |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN, JA | 1 LS | $1,000 | $88,332 |
| 690E98400 SPECIAL - OPERATIONS AND MAINTENANCE MANUAL | 1 LS | $1,750 | $1,923 |
| 690E99300 SPECIAL - WATER FOR PUMP STATION TESTING | 80 MGAL | $100 | $531 |
| 690E99550 SPECIAL - OPERATIONS AND MAINTENANCE | 36 MNTH | $450 | $427 |
| 601E21050 TIED CONCRETE BLOCK MAT WITH TYPE 1 UNDERLAYMENT | 10 SY | $193 | $218 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $150 | $150 |
| 659E00300 TOPSOIL | 1,104 CY | $4.36 | $20.43 |
| 659E10000 SEEDING AND MULCHING | 9,939 SY | $0.81 | $2.63 |
| 659E14000 REPAIR SEEDING AND MULCHING | 497 SY | $1.00 | $1.00 |
| 659E15000 INTER-SEEDING | 497 SY | $1.00 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 1.39 TON | $1,000 | $1,000 |
| 659E31000 LIME | 2.06 ACRE | $250 | $250 |
| 659E35000 WATER | 57 MGAL | $20.00 | $20.00 |
| 659E40000 MOWING | 23 MSF | $2.10 | $50.00 |
| 670E00700 DITCH EROSION PROTECTION | 940 SY | $2.00 | $2.00 |
| 832E15000 STORM WATER POLLUTION PREVENTION PLAN | 1 LS | $1,945 | $1,945 |
| 832E15002 STORM WATER POLLUTION PREVENTION INSPECTIONS | 1 LS | $11,060 | $21,600 |
| 832E15010 STORM WATER POLLUTION PREVENTION INSPECTION SOFTWA | 1 LS | $13,124 | $13,124 |
| 832E30000 EROSION CONTROL | 50,000 EACH | $1.00 | $1.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 200 FT | $48.21 | $26.17 |
| 611E00900 6" CONDUIT, TYPE B | 100 FT | $38.54 | $35.51 |
| 611E01100 6" CONDUIT, TYPE C | 100 FT | $38.54 | $38.97 |
| 611E01400 6" CONDUIT, TYPE E | 100 FT | $38.54 | $19.97 |
| 611E01500 6" CONDUIT, TYPE F | 100 FT | $38.54 | $19.97 |
| 611E01800 8" CONDUIT, TYPE B | 100 FT | $81.41 | $38.09 |
| 611E02000 8" CONDUIT, TYPE C | 100 FT | $81.41 | $34.05 |
| 611E07400 18" CONDUIT, TYPE B | 113 FT | $415 | $475 |
| 611E19600 42" CONDUIT, TYPE C | 16 FT | $560 | $494 |
| 611E20900 48" CONDUIT, TYPE B | 20 FT | $682 | $803 |
| 611E96600 CONDUIT, BORED OR JACKED, 36" TYPE B | 167 FT | $813 | $162 |
| 611E98300 CATCH BASIN, NO. 5 | 1 EACH | $7,188 | $10,136 |
| 611E98341 CATCH BASIN, NO. 5A | 5 EACH | $14,361 | $17,345 |
| 611E98434 CATCH BASIN, NO. 8A | 1 EACH | $17,764 | $16,786 |
| 611E99115 INLET, NO. 3 FOR SINGLE SLOPE BARRIER, TYPE D, AS | 3 EACH | $17,349 | $16,518 |
| 611E99115 INLET, NO. 3 FOR SINGLE SLOPE BARRIER, TYPE D, AS | 1 EACH | $17,349 | $14,129 |
| 611E99574 MANHOLE, NO. 3 | 4 EACH | $15,640 | $14,696 |
| 611E99690 MANHOLE, MISC.: TRASH RACK STRUCTURE | 1 EACH | $82,000 | $81,897 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 5 EACH | $688 | $250 |
| 690E98400 SPECIAL - PRESSURE RELEASE VALVE AND STRUCTURE | 1 LS | $70,050 | $35,672 |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449) | 70 CY | $400 | $400 |
| 304E20000 AGGREGATE BASE | 140 CY | $92.78 | $88.33 |
| 407E20000 NON-TRACKING TACK COAT | 84 GAL | $10.00 | $10.00 |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 35 CY | $650 | $650 |
| 609E26000 CURB, TYPE 6 | 756 FT | $31.62 | $27.04 |
| 253E02001 PAVEMENT REPAIR, AS PER PLAN | 66 CY | $528 | $300 |
| 611E06100 15" CONDUIT, TYPE C | 466 FT | $188 | $207 |
| 611E20900 48" CONDUIT, TYPE B, WITH CLASS II BEDDING | 51 FT | $924 | $884 |
| 611E97910 SPECIAL - SANITARY SEWER MSD SANITARY SEWER PROTEC | 1 LS | $88,020 | $57,270 |
| 611E99690 MANHOLE, MISC.: SANITARY MANHOLE PER MSD STD ACC. | 4 EACH | $32,990 | $32,738 |
| 611E99690 MANHOLE, MISC.: SANITARY MANHOLE PER MSD STD ACC. | 1 EACH | $1,812 | $1,094 |
| 625E00450 CONNECTION, FUSED PULL APART | 8 EACH | $177 | $177 |
| 625E00460 CONNECTION, UNFUSED PULL APART | 4 EACH | $177 | $177 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 12 EACH | $133 | $133 |
| 625E10503 LIGHT POLE (INSTALLATION ONLY), AS PER PLAN | 4 EACH | $1,157 | $1,157 |
| 625E14001 LIGHT POLE FOUNDATION, 24" X 6' DEEP, AS PER PLAN | 4 EACH | $2,288 | $2,288 |
| 625E15201 LIGHT TOWER FOUNDATION, 36" X 25' DEEP, AS PER PLA | 1 EACH | $11,829 | $11,829 |
| 625E23300 NO. 2 AWG 2400 VOLT DISTRIBUTION CABLE | 3,033 FT | $5.35 | $5.35 |
| 625E25500 CONDUIT, 3", 725.04 | 941 FT | $34.30 | $34.30 |
| 625E29000 TRENCH | 941 FT | $12.25 | $12.25 |
| 625E30700 PULL BOX, 725.08, 18" | 2 EACH | $913 | $913 |
| 625E30710 PULL BOX, 725.08, 32" | 1 EACH | $4,682 | $4,682 |
| 625E32000 GROUND ROD | 3 EACH | $296 | $296 |
| 625E36010 UNDERGROUND WARNING/MARKING TAPE | 941 FT | $1.95 | $1.95 |
| 625E40000 SPECIAL - MAINTAIN EXISTING LIGHTING | 1 LS | $19,985 | $19,985 |
| 625E60010 LIGHT POLE REMOVED FOR REERECTION | 4 EACH | $315 | $315 |
| 625E75360 LIGHT TOWER REMOVED FOR STORAGE | 1 EACH | $1,260 | $1,260 |
| 625E75500 LIGHT POLE FOUNDATION REMOVED | 4 EACH | $478 | $478 |
| 625E75540 LIGHT TOWER FOUNDATION REMOVED | 1 EACH | $898 | $898 |
| 625E75800 DISCONNECT CIRCUIT | 3 EACH | $449 | $449 |
| 625E98000 LIGHTING, MISC.: LIGHT TOWER INSTALLATION ONLY | 1 EACH | $2,410 | $2,410 |
| 625E25600 CONDUIT, 4", 725.04 | 620 FT | $30.00 | $64.30 |
| 625E25902 CONDUIT, JACKED OR DRILLED, 725.04, 4" | 240 FT | $62.00 | $91.00 |
| 625E25930 CONDUIT, MISC.: CONDUIT RISER, 4" DIAMETER | 2 EACH | $600 | $1,450 |
| 625E34301 TRANSFORMER PAD, CONCRETE, AS PER PLAN | 1 EACH | $6,500 | $3,987 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 98 FT | $19.00 | $19.00 |
| 630E08600 SIGN POST REFLECTOR | 2 EACH | $50.00 | $50.00 |
| 630E09000 BREAKAWAY STRUCTURAL BEAM CONNECTION | 2 EACH | $555 | $555 |
| 630E84510 RIGID OVERHEAD SIGN SUPPORT FOUNDATION | 2 EACH | $1,250 | $1,250 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 10 EACH | $50.00 | $50.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 6 EACH | $60.00 | $60.00 |
| 630E86250 REMOVAL OF GROUND MOUNTED STRUCTURAL BEAM SUPPORT | 3 EACH | $400 | $400 |
| 644E01510 DOTTED LINE, 6" | 370 FT | $13.30 | $13.30 |
| 606E60022 IMPACT ATTENUATOR, TYPE 2 (UNIDIRECTIONAL), 60 MPH | 1 EACH | $36,838 | $33,100 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 50 HOUR | $95.05 | $140 |
| 614E12380 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS | — | $3,456 | $2,032 |
| 614E13310 BARRIER REFLECTOR, TYPE 1, ONE WAY | 89 EACH | $21.78 | $7.50 |
| 614E13312 BARRIER REFLECTOR, TYPE 2, ONE WAY | 3 EACH | $21.78 | $14.39 |
| 614E13350 OBJECT MARKER, ONE WAY | 92 EACH | $21.78 | $15.00 |
| 614E23010 WORK ZONE CHANNELIZING LINE, CLASS I, 12" | 370 FT | $7.35 | $7.35 |
| 615E10000 ROADS FOR MAINTAINING TRAFFIC | 1 LS | $32,495 | $5,194 |
| 615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A | 558 SY | $95.00 | $121 |
| 616E10000 WATER | 18 MGAL | $151 | $4.22 |
| 622E41060 DUAL PORTABLE BARRIER TRANSITION/TERMINATION | 1 EACH | $3,078 | $12,231 |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN, WA | 1 LS | $1,513 | $111,856 |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN, WA | 1 LS | $2,011 | $355,955 |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN, WA | 1 LS | $1,435 | $56,427 |
| 503E21300 UNCLASSIFIED EXCAVATION | 1 LS | $30,235 | $18,111 |
| 509E10000 EPOXY COATED STEEL REINFORCEMENT | 8,329 LB | $1.41 | $1.49 |
| 511E46010 CLASS QC1 CONCRETE, RETAINING/WINGWALL NOT INCLUDI | 27 CY | $1,734 | $1,475 |
| 511E46510 CLASS QC1 CONCRETE, FOOTING | 47 CY | $977 | $494 |
| 512E10100 SEALING OF CONCRETE SURFACES (EPOXY-URETHANE) | 63 SY | $58.50 | $58.50 |
| 517E73501 RAILING, PIPE, AS PER PLAN | 44 FT | $395 | $395 |
| 518E21201 POROUS BACKFILL WITH GEOTEXTILE FABRIC, AS PER PLA | 28 CY | $150 | $105 |
| 601E32004 ROCK CHANNEL PROTECTION, TYPE A WITH GEOTEXTILE FA | 90 CY | $194 | $168 |
| 611E99900 DRAINAGE STRUCTURE, MISC.: FLAP GATE | 1 EACH | $43,868 | $85,681 |
| 100E51200 DEPARTMENT'S SHARE OF THE DISPUTE RESOLUTION ADVIS | 16,000 EACH | $1.00 | $1.00 |
| 108E10000 CPM PROGRESS SCHEDULE | 1 LS | $11,678 | $14,860 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $25,097 | $106,400 |
| 619E16021 FIELD OFFICE, TYPE C, AS PER PLAN | 14 MNTH | $4,761 | $3,764 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 690E98400 SPECIAL - STORMWATER DETENTION SYSTEM 6 | 1 LS | $3,739,849 | $3.74M | 19% |
| 690E98400 SPECIAL - STORMWATER PUMP STATION STRUCTURE | 1 LS | $3,385,300 | $3.39M | 17% |
| 690E98400 SPECIAL - PUMP STATION BUILDING AND CONTROLS | 1 LS | $1,650,000 | $1.65M | 8% |
| 638E98600 WATER WORK, MISC.: 36" WATER MAIN DUCTILE IRON PIP | 1,368 FT | $871.85 | $1.19M | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $1,038,069 | $1.04M | 5% |
| 638E07330 54" STEEL PIPE ENCASEMENT, BORED OR JACKED | 528 FT | $1,950 | $1.03M | 5% |
| 611E21100 48" CONDUIT, TYPE C | 1,482 FT | $637.63 | $945k | 5% |
| 611E26400 72" CONDUIT, TYPE C | 657 FT | $1,262 | $829k | 4% |
| 624E10000 MOBILIZATION | 1 LS | $800,000 | $800k | 4% |
| 503E11101 COFFERDAMS AND EXCAVATION BRACING, AS PER PLAN STO | 1 LS | $450,132 | $450k | 2% |