Figure 0.1 · BRIEFING
BID #264000 · ODOTRESULT · awarded Jan 15

COL-SR 644-07.96

COL County · est $0.6M

Bid dateThursday, January 15
Awarded toRUDZIK EXCAVATING INC$660,049
read → connected → answeredcassandri

Project scope

Bid form · ODOT

55ITEMS
  • Maintaining Traffic20%
  • Earthwork15%
  • Guardrail & Barrier13%
  • Erosion & Landscaping13%
  • Drainage5%
  • Aggregate & Base5%
  • Other29%

Top items by winning bid

ItemQtyUnit priceExtended%
611E96600 CONDUIT, BORED OR JACKED, 30" TYPE A, 748.06 Section 3 - DRAINAGE - Totals Awd $120,590.20 2 $117,962.20 3 $191,700.00 4 $511,850.00124 FT$895$111k17%
203E20000 EMBANKMENT2,141 CY$49.13$105k16%
301E56000 ASPHALT CONCRETE BASE, PG64-22, (449)172 CY$297$51k8%
622E41100 PORTABLE BARRIER, UNANCHORED Section 6 - MAINTENANCE OF TRAFFIC - Totals Awd $100,050.35 2 $105,969.55 3 $137,532.00 4 $95,462.001,430 FT$31$44k7%
441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 Section 4 - PAVEMENT - Totals Awd $127,844.41 2 $129,413.60 3 $106,226.50 4 $166,845.00449 (48 CY$690$33k5%
614E11000 MAINTAINING TRAFFIC1 LS$28,540$29k4%
624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $129,303.69 2 $74,589.42 3 $233,000.00 4 $117,000.001 LS$26,499$26k4%
441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG34 CY$771$26k4%
203E10000 EXCAVATION845 CY$30$25k4%
615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A233 SY$98$23k3%

Per-bidder unit pricing

ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 35 more items below.

Rank 1Rudzik Excavating INC$660kRank 2S.t.a.r.t., LLC$665kRank 3Shook Company LLC$897kRank 4Bog Construction INC$1.09M
ItemQuantityR1Rudzik Excavating INCR2S.t.a.r.t., LLCR3Shook Company LLCR4Bog Construction INC
611E96600 CONDUIT, BORED OR JACKED, 30" TYPE A, 748.06 Section 3 - DRAINAGE - Totals Awd $120,590.20 2 $117,962.20 3 $191,700.00 4 $511,850.00124 FT$895$919$1,500$4,100
203E20000 EMBANKMENT2,141 CY$49.13$31.24$40.00$40.00
301E56000 ASPHALT CONCRETE BASE, PG64-22, (449)172 CY$297$366$300$510
622E41100 PORTABLE BARRIER, UNANCHORED Section 6 - MAINTENANCE OF TRAFFIC - Totals Awd $100,050.35 2 $105,969.55 3 $137,532.00 4 $95,462.001,430 FT$31.00$32.03$35.00$25.00
441E70300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 Section 4 - PAVEMENT - Totals Awd $127,844.41 2 $129,413.60 3 $106,226.50 4 $166,845.00449 (48 CY$690$508$350$660
614E11000 MAINTAINING TRAFFIC1 LS$28,540$40,422$96,000$50,000
624E10000 MOBILIZATION Section 7 - INCIDENTALS - Totals Awd $129,303.69 2 $74,589.42 3 $233,000.00 4 $117,000.001 LS$26,499$55,150$65,000$29,000
441E70100 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449), PG34 CY$771$584$580$720
203E10000 EXCAVATION845 CY$30.00$27.17$35.00$30.00
615E20000 PAVEMENT FOR MAINTAINING TRAFFIC, CLASS A233 SY$98.00$81.00$100$115
304E20000 AGGREGATE BASE179 CY$105$114$100$125
614E12384 WORK ZONE IMPACT ATTENUATOR, 24" WIDE HAZARDS$2,930$2,156$3,000$2,500
201E11000 CLEARING AND GRUBBING1 LS$17,500$12,290$25,000$5,000
832E30000 EROSION CONTROL Section 2 - EROSION CONTROL - Totals Awd $29,301.19 2 $26,353.90 3 $23,525.00 4 $27,557.0017,041 EACH$1.00$1.00$1.00$1.00
606E26150 ANCHOR ASSEMBLY, MGS TYPE E (MASH 2016) Section 1 - ROADWAY - Totals Awd $148,003.27 2 $192,286.83 3 $196,184.00 4 $166,372.004 EACH$2,882$2,620$3,000$2,850
606E15050 GUARDRAIL, TYPE MGS475 FT$23.00$21.00$30.00$24.00
202E23000 PAVEMENT REMOVED859 SY$12.50$12.66$15.00$18.00
615E10000 ROADS FOR MAINTAINING TRAFFIC1 LS$10,000$10,053$25,000$7,500
619E16010 FIELD OFFICE, TYPE B6 MNTH$1,400$3,200$2,000$500
103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM1 LS$6,650$32.03$40,000$25,000
Show all 55 line items
ItemQuantityR1Rudzik Excavating INCR2S.t.a.r.t., LLCR3Shook Company LLCR4Bog Construction INC
202E38000 GUARDRAIL REMOVED680 FT$3.60$2.00$3.00$3.00
202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT, 24" DIAM84 FT$61.25$98.89$150$55.00
204E10000 SUBGRADE COMPACTION1,072 SY$3.00$4.14$2.00$5.00
204E45000 PROOF ROLLING1 HOUR$250$435$50.00$100
601E32204 ROCK CHANNEL PROTECTION, TYPE C WITH GEOTEXTILE FA3 CY$770$1,101$250$150
659E00100 SOIL ANALYSIS TEST1 EACH$50.00$168$50.00$100
659E00300 TOPSOIL90 CY$40.00$54.11$35.00$35.00
659E10000 SEEDING AND MULCHING807 SY$4.00$3.64$3.00$8.00
659E14000 REPAIR SEEDING AND MULCHING40 SY$1.00$6.38$1.00$3.00
659E15000 INTER-SEEDING40 SY$1.00$6.38$1.00$1.00
659E20000 COMMERCIAL FERTILIZER0.11 TON$400$2,544$100$1,000
659E31000 LIME0.17 ACRE$5.00$1,067$100$500
659E35000 WATER5 MGAL$0.01$2.00$1.00$1.00
602E20000 CONCRETE MASONRY0.9 CY$5,268$4,799$5,000$2,500
605E31100 AGGREGATE DRAINS60 FT$37.35$38.64$20.00$20.00
407E10000 TACK COAT59 GAL$3.40$3.60$3.50$10.00
621E00100 RPM17 EACH$165$150$175$20.00
621E54000 RAISED PAVEMENT MARKER REMOVED17 EACH$35.00$22.06$25.00$50.00
626E00110 BARRIER REFLECTOR, TYPE 2, BIDIRECTIONAL8 EACH$16.50$15.00$13.00$20.00
630E02100 GROUND MOUNTED SUPPORT, NO. 2 POST9.5 FT$83.00$35.00$154$200
630E80100 SIGN, FLAT SHEET1 SF$688$100$50.00$200
630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL1 EACH$50.00$10.00$100$200
630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA1 EACH$50.00$10.00$100$200
646E10010 EDGE LINE, 6"0.26 MILE$16,500$13,500$8,500$10,000
646E10200 CENTER LINE Section 5 - TRAFFIC CONTROL - Totals Awd $10,257.52 2 $13,473.50 3 $8,532.00 4 $7,750.000.13 MILE$31,350$25,000$8,500$10,000
410E13000 TRAFFIC COMPACTED SURFACE, TYPE C35 CY$82.00$165$350$40.00
614E11630 INCREASED BARRIER DELINEATION740 FT$1.55$1.00$2.00$3.00
614E13310 BARRIER REFLECTOR, TYPE 1, BIDIRECTIONAL14 EACH$40.00$12.56$15.00$15.00
614E13360 OBJECT MARKER, TWO WAY29 EACH$32.00$25.00$26.00$15.00
614E21100 WORK ZONE CENTER LINE, CLASS I, 642 PAINT0.13 MILE$5,225$4,750$6,100$8,000
614E22110 WORK ZONE EDGE LINE, CLASS I, 6", 642 PAINT0.26 MILE$2,915$2,650$6,100$8,000
614E22210 WORK ZONE EDGE LINE, CLASS I, 6", 740.06, TYPE I0.33 MILE$12,000$10,053$10,300$7,500
614E26400 WORK ZONE STOP LINE, CLASS I, 740.06, TYPE I20 FT$13.20$12.00$7.00$25.00
616E10000 WATER57 MGAL$1.00$2.00$10.00$1.00
623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING1 LS$4,500$14,500$20,000$10,000

Project details

Description
COL-SR 644-07.96
Type of work
Maintenance

How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →