CUY-Detroit Ave Streetscape II
CUY County · est $1.4M
Bid dateThursday, January 25—
CUY County · est $1.4M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 10.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 49 more items below.
| Item | Quantity | R1S E T INC | R2Perk Company INC | R3Terrace Construction CO INC | R4Liberta Construction Company INC | R5Tri-mor CORP | R6Great Lakes Construction CO | R7Vandra Brothers Construction INC | R8Fabrizi Trucking & Paving CO INC | % of bid |
|---|---|---|---|---|---|---|---|---|---|---|
| 202E30001 WALK REMOVED, AS PER PLAN | 38,515 SF | $3.00 | $1.50 | $0.95 | $1.50 | $2.00 | $1.50 | $2.00 | $1.65 | 10% |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN | 5,286 FT | $21.00 | $29.95 | $32.00 | $48.00 | $35.00 |
| Item | Quantity | R1S E T INC | R2Perk Company INC | R3Terrace Construction CO INC | R4Liberta Construction Company INC | R5Tri-mor CORP | R6Great Lakes Construction CO | R7Vandra Brothers Construction INC | R8Fabrizi Trucking & Paving CO INC |
|---|---|---|---|---|---|---|---|---|---|
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $10,500 | $7,800 | $2,173 | $15,000 | $13,000 | $16,000 | $15,000 | $15,000 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 6 FT | $50.00 | $50.00 | $148 | $5.00 | $100 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $56.00 |
| $38.00 |
| $56.00 |
| 10% |
| 452E19250 NON-REINFORCED CONCRETE PAVEMENT, MISC.: COLORED A | 4,738 SF | $20.00 | $25.25 | $32.00 | $29.00 | $30.00 | $28.00 | $28.00 | $35.00 | 9% |
| 624E10000 MOBILIZATION | 1 LS | $81,850 | $10,550 | $97,666 | $40,000 | $30,000 | $40,000 | $125,000 | $75,026 | 7% |
| 608E13001 6" CONCRETE WALK, AS PER PLAN | 30,494 SF | $2.50 | $6.80 | $8.75 | $9.00 | $10.00 | $9.00 | $8.00 | $8.60 | 7% |
| 608E98000 WALKWAY, MISC.:INTEGRALLY COLORED CONCRETE, TYPE A | 3,994 SF | $17.00 | $8.50 | $15.00 | $15.00 | $15.00 | $16.00 | $23.00 | $22.00 | 6% |
| 452E19200 NON-REINFORCED CONCRETE PAVEMENT, MISC.: 8" NON-RE | 880 SY | $72.00 | $68.00 | $84.60 | $81.00 | $75.00 | $62.00 | $90.00 | $74.00 | 6% |
| 608E98000 WALKWAY, MISC.:UNIT PAVER 1 | 1,781 SF | $34.00 | $39.00 | $36.55 | $40.00 | $45.00 | $58.00 | $35.00 | $45.00 | 5% |
| 202E98100 REMOVAL MISC.:POLE REMOVAL-WOOD, METAL OR CONCRETE | 60 EACH | $985 | $515 | $515 | $150 | $125 | $200 | $500 | $750 | 5% |
| 608E98000 WALKWAY, MISC.:CURB EDGE RESTRAINT | 2,201 SF | $26.00 | $27.40 | $28.00 | $20.00 | $18.00 | $35.00 | $35.00 | $38.00 | 5% |
| 605E14021 6" BASE PIPE UNDERDRAINS WITH GEOTEXTILE FABRIC, A | 5,025 FT | $11.00 | $14.00 | $13.50 | $16.00 | $12.50 | $15.00 | $13.00 | $9.50 | 5% |
| 608E52001 CURB RAMP, AS PER PLAN | 2,867 SF | $18.00 | $31.00 | $31.60 | $9.00 | $18.00 | $20.00 | $20.00 | $22.00 | 5% |
| 614E11001 MAINTAINING TRAFFIC, AS PER PLAN | 1 LS | $46,695 | $41,950 | $32,952 | $60,000 | $78,000 | $52,000 | $150,000 | $65,300 | 4% |
| 202E23001 PAVEMENT REMOVED, AS PER PLAN | 1,009 SY | $35.00 | $10.75 | $34.00 | $34.00 | $30.00 | $85.00 | $43.00 | $28.00 | 3% |
| AB1 690E99800 SPECIAL - FABRICATION AND INSTALLATION OF PUBLIC A | 26,000 DLR | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 661E99900 PLANTING, MISC.:PLANTER TYPE A | 19 EACH | $1,250 | $1,300 | $979 | $1,155 | $1,500 | $1,200 | $1,200 | $1,500 | 2% |
| 611E99655 MANHOLE ADJUSTED TO GRADE, AS PER PLAN | 19 EACH | $1,115 | $750 | $474 | $750 | $500 | $1,000 | $800 | $850 | 2% |
| 202E32001 CURB REMOVED, AS PER PLAN | 5,286 FT | $4.00 | $7.30 | $3.50 | $5.00 | $12.00 | $1.25 | $4.00 | $12.00 | 2% |
| 690E98000 SPECIAL - BIKE RACK | 32 EACH | $625 | $675 | $697 | $633 | $800 | $800 | $750 | $850 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $18,500 | $20,460 | $9,517 | $25,000 | $22,000 | $15,000 | $15,000 | $35,000 | 2% |
| $250 |
| $25.00 |
| $150 |
| 202E58100 CATCH BASIN REMOVED | 1 EACH | $1,000 | $750 | $829 | $100 | $500 | $1,000 | $1,000 | $750 |
| 202E98300 REMOVAL MISC.:PAVEMENT REMOVED FOR DRIVEWAYS | 1,053 SY | $10.00 | $16.75 | $19.00 | $13.50 | $22.00 | $15.00 | $30.00 | $13.00 |
| 202E98300 REMOVAL MISC.:TRACK REMOVED | 150 SY | $30.00 | $35.00 | $26.00 | $20.00 | $30.00 | $50.00 | $35.00 | $31.00 |
| 203E20001 EMBANKMENT, AS PER PLAN | 58 CY | $45.00 | $35.00 | $21.00 | $15.00 | $60.00 | $40.00 | $45.00 | $35.00 |
| 204E10000 SUBGRADE COMPACTION | 2,082 SY | $5.00 | $2.00 | $1.25 | $1.00 | $3.00 | $12.00 | $1.00 | $1.50 |
| 304E20000 AGGREGATE BASE | 134 CY | $95.00 | $75.00 | $111 | $50.00 | $105 | $135 | $50.00 | $60.00 |
| 613E41201 LOW STRENGTH MORTAR BACKFILL, AS PER PLAN | 50 CY | $65.00 | $60.00 | $77.00 | $70.00 | $125 | $65.00 | $75.00 | $80.00 |
| 690E98200 SPECIAL - CONCRETE WALK, POLE BOX OUT | 1,000 SF | $8.00 | $12.50 | $14.00 | $6.00 | $15.00 | $16.00 | $20.00 | $10.00 |
| 832E30001 EROSION CONTROL, AS PER PLAN | 5,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 260 FT | $20.00 | $19.00 | $16.00 | $16.00 | $16.00 | $35.00 | $25.00 | $14.00 |
| 611E99661 MANHOLE RECONSTRUCTED TO GRADE, AS PER PLAN | 1 EACH | $1,950 | $1,200 | $2,561 | $1,500 | $1,700 | $3,000 | $1,300 | $1,350 |
| 611E99820 SPECIAL - MISCELLANEOUS METAL | 5,000 LB | $1.00 | $1.25 | $1.25 | $2.00 | $1.50 | $1.10 | $2.00 | $2.50 |
| 611E99900 DRAINAGE STRUCTURE, MISC.:TEST TEE ADJUSTED TO GRA | 2 EACH | $200 | $450 | $535 | $50.00 | $200 | $150 | $1,000 | $350 |
| 690E98700 SPECIAL - SURCHARGE FOR CLASS MS CONCRETE | 250 CY | $25.00 | $10.00 | $10.00 | $16.00 | $20.00 | $15.00 | $15.00 | $25.00 |
| 638E10801 VALVE BOX ADJUSTED TO GRADE, AS PER PLAN | 5 EACH | $250 | $750 | $500 | $125 | $250 | $200 | $450 | $500 |
| 638E10900 SERVICE BOX ADJUSTED TO GRADE | 23 EACH | $150 | $125 | $164 | $50.00 | $100 | $100 | $150 | $150 |
| 625E14501 LIGHT POLE FOUNDATION, AS PER PLAN | 1 EACH | $1,500 | $1,800 | $1,653 | $1,980 | $2,500 | $1,800 | $1,800 | $2,250 |
| 625E25105 CONDUIT, 1", 725.051, AS PER PLAN | 52 FT | $3.00 | $18.00 | $19.00 | $19.80 | $22.00 | $18.00 | $18.00 | $22.00 |
| 625E29000 TRENCH | 52 FT | $22.00 | $10.00 | $7.00 | $11.00 | $12.00 | $10.00 | $10.00 | $15.00 |
| 625E32001 GROUND ROD, AS PER PLAN | 3 EACH | $150 | $155 | $129 | $171 | $200 | $155 | $155 | $185 |
| 625E36001 PLASTIC CAUTION TAPE, AS PER PLAN | 52 FT | $0.50 | $1.00 | $0.50 | $1.10 | $1.25 | $1.00 | $1.00 | $5.00 |
| 625E32000 GROUND ROD | 2 EACH | $150 | $155 | $123 | $171 | $200 | $155 | $155 | $185 |
| 632E64020 PEDESTAL FOUNDATION | 2 EACH | $800 | $800 | $514 | $880 | $1,000 | $800 | $800 | $950 |
| 644E00300 CENTER LINE | 0.2 MILE | $5,800 | $6,500 | $7,848 | $8,125 | $5,500 | $5,000 | $6,500 | $7,150 |
| 644E00400 CHANNELIZING LINE, 8" | 153 FT | $2.00 | $1.50 | $1.75 | $1.90 | $2.00 | $1.50 | $1.50 | $1.75 |
| 644E00500 STOP LINE | 122 FT | $9.00 | $5.50 | $7.00 | $6.90 | $9.00 | $8.00 | $5.50 | $9.50 |
| 644E00600 CROSSWALK LINE | 2,032 FT | $4.00 | $2.75 | $3.25 | $3.45 | $4.00 | $3.50 | $2.75 | $4.00 |
| 644E01300 LANE ARROW | 1 EACH | $115 | $125 | $151 | $156 | $500 | $100 | $125 | $150 |
| 644E30000 REMOVAL OF PAVEMENT MARKING | 510 FT | $1.50 | $5.00 | $5.00 | $6.25 | $5.00 | $4.33 | $5.00 | $8.00 |
| 630E97700 SIGNING, MISC.:Solar Powered Flashing Beacon Syste | 2 EACH | $6,500 | $8,500 | $6,540 | $10,625 | $20,000 | $8,500 | $8,500 | $11,000 |
| 659E00300 TOPSOIL | 183 CY | $50.00 | $46.00 | $52.00 | $47.00 | $50.00 | $33.00 | $43.00 | $50.00 |
| 659E00500 SEEDING AND MULCHING, CLASS 1 | 542 SY | $2.00 | $2.75 | $1.75 | $1.60 | $3.00 | $1.00 | $1.50 | $2.00 |
| 661E40120 DECIDUOUS TREE, 3" CALIPER ZELKOVA SERRATA 'GREEN | 16 EACH | $550 | $575 | $622 | $567 | $650 | $700 | $550 | $850 |
| 661E99900 PLANTING, MISC.:PLANTER TYPE B | 7 EACH | $600 | $1,500 | $1,173 | $1,430 | $1,300 | $1,200 | $1,400 | $2,000 |
| 690E98000 SPECIAL - BENCH TYPE A | 6 EACH | $2,250 | $2,500 | $2,055 | $2,200 | $2,400 | $2,000 | $2,200 | $2,550 |
| 690E98000 SPECIAL - BENCH TYPE B | 12 EACH | $620 | $650 | $760 | $605 | $1,000 | $1,000 | $750 | $1,350 |
| 690E98000 SPECIAL - DESTINATION CLEVELAND FOUNDATION | 2 EACH | $1,600 | $900 | $1,411 | $990 | $4,500 | $2,000 | $2,000 | $2,500 |
| AB1 690E98000 SPECIAL - PUBLIC ART FOUNDATION | 1 EACH | $2,500 | $3,500 | $2,619 | $3,850 | $5,500 | $5,000 | $5,000 | $6,850 |
| 608E21201 TEMPORARY ASPHALT CONCRETE WALK, AS PER PLAN | 1,000 SF | $2.00 | $0.10 | $0.85 | $5.00 | $6.00 | $8.00 | $3.00 | $3.00 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 80 HOUR | $77.00 | $75.00 | $87.00 | $60.00 | $60.00 | $70.00 | $65.00 | $65.00 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 16 SNMT | $1,050 | $1,300 | $1,050 | $1,313 | $1,200 | $900 | $1,050 | $1,250 |
| 614E21200 WORK ZONE CENTER LINE, CLASS I, 740.06, TYPE I | 0.4 MILE | $10,500 | $12,500 | $11,149 | $15,625 | $10,000 | $9,000 | $12,500 | $14,500 |
| 614E26400 WORK ZONE STOP LINE, CLASS I, 740.06, TYPE I | 64 FT | $6.50 | $5.00 | $7.00 | $6.25 | $7.00 | $5.60 | $5.00 | $8.00 |
| 108E30000 CPM PROGRESS SCHEDULE SHORT DURATION PROJECTS | 1 LS | $5,000 | $2,750 | $3,260 | $4,015 | $3,000 | $300 | $10,000 | $4,000 |
| 619E16010 FIELD OFFICE, TYPE B | 8 MNTH | $1,500 | $2,900 | $3,622 | $2,000 | $1,500 | $2,500 | $2,500 | $2,500 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $18,500 | $11,250 | $14,653 | $22,705 | $13,000 | $10,000 | $25,000 | $35,000 |
| 690E98400 SPECIAL - PRE-CONSTRUCTION AUDIO/VIDEO | 1 LS | $4,500 | $2,100 | $872 | $1,320 | $2,000 | $1,000 | $2,000 | $15,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 202E30001 WALK REMOVED, AS PER PLAN | 38,515 SF | $3 | $116k | 9% |
| 609E12001 COMBINATION CURB AND GUTTER, TYPE 2, AS PER PLAN | 5,286 FT | $21 | $111k | 8% |
| 452E19250 NON-REINFORCED CONCRETE PAVEMENT, MISC.: COLORED A | 4,738 SF | $20 | $95k | 7% |
| 624E10000 MOBILIZATION | 1 LS | $81,850 | $82k | 6% |
| 608E13001 6" CONCRETE WALK, AS PER PLAN | 30,494 SF | $2.5 | $76k | 6% |
| 608E98000 WALKWAY, MISC.:INTEGRALLY COLORED CONCRETE, TYPE A | 3,994 SF | $17 | $68k | 5% |
| 452E19200 NON-REINFORCED CONCRETE PAVEMENT, MISC.: 8" NON-RE | 880 SY | $72 | $63k | 5% |
| 608E98000 WALKWAY, MISC.:UNIT PAVER 1 | 1,781 SF | $34 | $61k | 4% |
| 202E98100 REMOVAL MISC.:POLE REMOVAL-WOOD, METAL OR CONCRETE | 60 EACH | $985 | $59k | 4% |
| 608E98000 WALKWAY, MISC.:CURB EDGE RESTRAINT | 2,201 SF | $26 | $57k | 4% |