HAM-US 50-31.25/32.23
HAM County · est $0.8M
Bid dateThursday, March 22—
HAM County · est $0.8M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 53 more items below.
| Item | Quantity | R1Tri-state Concrete Construction INC | R2Eclipse CO LLC | R3Belgray, INC | % of bid |
|---|---|---|---|---|---|
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 364 CY | $200 | $191 | $187 | 12% |
| 611E01500 6" CONDUIT, TYPE F | 4,035 FT | $17.00 | $3.50 | $8.50 | 12% |
| 608E10000 4" CONCRETE WALK | 9,020 SF | $4.95 | $5.00 | $5.00 | 8% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 184 CY | $240 | $200 | $195 | 8% |
| 202E23000 PAVEMENT REMOVED | 1,529 SY | $28.00 | $12.00 | $20.00 | 7% |
| 611E98150 CATCH BASIN, NO. 3 | 10 EACH | $3,200 | $2,766 | $3,900 | 5% |
| 609E12000 COMBINATION CURB AND GUTTER, TYPE 2 | 1,755 FT | $17.25 | $26.50 |
| Item | Quantity | R1Tri-state Concrete Construction INC | R2Eclipse CO LLC | R3Belgray, INC |
|---|---|---|---|---|
| 201E11001 CLEARING AND GRUBBING, AS PER PLAN | 1 LS | $5,000 | $11,000 | $10,000 |
| 202E23010 PAVEMENT REMOVED, ASPHALT | 316 SY | $8.00 | $8.00 | $8.00 |
| 202E30000 WALK REMOVED | 5,800 SF | $1.50 | $1.50 | $1.50 |
| 202E30204 STEPS REMOVED | 1 LS | $750 | $930 | $700 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 1,347 FT | $7.60 | $11.00 | $7.00 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $25.00 |
| 5% |
| 203E35120 GRANULAR MATERIAL, TYPE C | 353 CY | $69.85 | $77.00 | $70.00 | 4% |
| 204E13000 EXCAVATION OF SUBGRADE | 529 CY | $45.00 | $33.00 | $28.00 | 4% |
| 611E10600 24" CONDUIT, TYPE C | 390 FT | $60.00 | $68.50 | $72.00 | 4% |
| 611E04600 12" CONDUIT, TYPE C | 385 FT | $58.00 | $51.00 | $56.00 | 4% |
| 611E99574 MANHOLE, NO. 3 | 6 EACH | $3,400 | $2,833 | $1,900 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20,000 | $20,000 | 3% |
| 611E16400 36" CONDUIT, TYPE B | 175 FT | $107 | $127 | $175 | 3% |
| 304E20000 AGGREGATE BASE | 255 CY | $72.00 | $62.50 | $90.00 | 3% |
| 611E10400 24" CONDUIT, TYPE B | 265 FT | $68.00 | $82.00 | $92.00 | 3% |
| 611E16600 36" CONDUIT, TYPE C | 212 FT | $82.00 | $88.50 | $105 | 3% |
| 609E26000 CURB, TYPE 6 | 1,270 FT | $12.00 | $19.50 | $18.00 | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $15,000 | $47,577 | $15,000 | 3% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $13,500 | $22,000 | $7,177 | 2% |
| 378 FT |
| $8.10 |
| $11.50 |
| $8.00 |
| 202E53100 MAILBOX REMOVED | 4 EACH | $85.00 | $57.00 | $60.00 |
| 202E58000 MANHOLE REMOVED | 2 EACH | $875 | $366 | $750 |
| 202E58100 CATCH BASIN REMOVED | 2 EACH | $325 | $366 | $400 |
| 202E58101 CATCH BASIN REMOVED, AS PER PLAN | 7 EACH | $525 | $366 | $750 |
| 202E58400 INLET ABANDONED | 3 EACH | $500 | $366 | $650 |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT, 24" CMP | 336 FT | $19.50 | $15.00 | $32.00 |
| 202E70000 SPECIAL - FILL AND PLUG EXISTING CONDUIT, 36" CMP | 235 FT | $39.50 | $24.50 | $50.00 |
| 202E70110 SPECIAL - PIPE CLEANOUT, 24" AND UNDER | 12 FT | $35.00 | $102 | $45.00 |
| 203E10000 EXCAVATION | 5 CY | $85.00 | $158 | $80.00 |
| 203E20000 EMBANKMENT | 10 CY | $48.00 | $98.00 | $20.00 |
| 204E10000 SUBGRADE COMPACTION | 1,117 SY | $2.00 | $7.00 | $4.00 |
| 204E50000 GEOTEXTILE FABRIC | 1,058 SY | $2.35 | $3.50 | $1.00 |
| 608E52000 CURB RAMP | 435 SF | $9.00 | $11.50 | $12.00 |
| 609E28000 CURB, TYPE 7 | 960 FT | $13.00 | $26.00 | $30.00 |
| 690E50000 SPECIAL - MAILBOX SUPPORT | 4 EACH | $230 | $138 | $175 |
| 659E10000 SEEDING AND MULCHING | 1,350 SY | $2.00 | $2.00 | $4.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.2 TON | $375 | $657 | $550 |
| 659E31000 LIME | 0.3 ACRE | $285 | $84.00 | $400 |
| 659E35000 WATER | 6 MGAL | $20.00 | $1.00 | $80.00 |
| 832E30000 EROSION CONTROL | 10,000 EACH | $1.00 | $1.00 | $1.00 |
| 601E21050 TIED CONCRETE BLOCK MAT, TYPE 1 | 4 SY | $345 | $136 | $150 |
| 611E02000 8" CONDUIT, TYPE C | 5 FT | $48.00 | $43.00 | $50.00 |
| 611E06100 15" CONDUIT, TYPE C | 141 FT | $38.50 | $52.00 | $57.00 |
| 611E07600 18" CONDUIT, TYPE C | 184 FT | $58.75 | $55.00 | $73.00 |
| 611E99710 PRECAST REINFORCED CONCRETE OUTLET | 2 EACH | $200 | $193 | $175 |
| 407E10000 TACK COAT | 87 GAL | $2.50 | $2.50 | $2.50 |
| 408E10000 PRIME COAT | 30 GAL | $2.50 | $5.50 | $5.00 |
| 509E25000 REINFORCING STEEL | 790 LB | $1.00 | $2.50 | $1.50 |
| 511E53010 CLASS QC1 CONCRETE, MISC.: WATER WORK | 5 CY | $125 | $222 | $160 |
| 638E20064 SPECIAL - 6" WATER MAIN DIP CLASS 55 MECHANICAL JO | 25 FT | $225 | $177 | $275 |
| 638E20502 SPECIAL - VALVE BOX REBUILT TO GRADE (CINCINNATI) | 2 EACH | $400 | $491 | $900 |
| 638E20754 SPECIAL - FIRE HYDRANT RELOCATED (CINCINNATI) | 2 EACH | $730 | $2,707 | $2,500 |
| 630E85100 REMOVAL OF GROUND MOUNTED SIGN AND REERECTION | 7 EACH | $150 | $67.00 | $150 |
| 642E00094 EDGE LINE, 6" | 1.09 MILE | $1,135 | $1,193 | $1,135 |
| 642E00290 CENTER LINE | 0.94 MILE | $1,280 | $1,345 | $1,280 |
| 642E00590 CROSSWALK LINE | 106 FT | $2.15 | $2.50 | $2.15 |
| 642E00690 TRANSVERSE/DIAGONAL LINE | 100 FT | $2.40 | $2.50 | $2.40 |
| 642E01290 LANE ARROW | 6 EACH | $100 | $105 | $100 |
| 644E30000 REMOVAL OF PAVEMENT MARKING | 182 FT | $1.80 | $2.00 | $1.80 |
| 644E30020 REMOVAL OF PAVEMENT MARKING | 6 EACH | $105 | $111 | $105 |
| 644E30030 REMOVAL OF PAVEMENT MARKING | 1.88 MILE | $1,584 | $1,664 | $1,584 |
| 809E69101 STOP-BAR RADAR DETECTION, AS PER PLAN | 1 EACH | $11,650 | $14,709 | $7,925 |
| 614E21200 WORK ZONE CENTER LINE, CLASS I, 740.06, TYPE I | 0.57 MILE | $11,000 | $11,557 | $11,000 |
| 614E22000 WORK ZONE EDGE LINE, CLASS I, 4" | 0.92 MILE | $1,830 | $1,923 | $1,830 |
| 614E24400 WORK ZONE DOTTED LINE, CLASS I, 740.06, TYPE I | 1,000 FT | $1.75 | $2.00 | $1.75 |
| 616E10000 WATER | 1 MGAL | $125 | $68.50 | $80.00 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,500 | $7,500 | $11,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 364 CY | $200 | $73k | 10% |
| 611E01500 6" CONDUIT, TYPE F | 4,035 FT | $17 | $69k | 9% |
| 608E10000 4" CONCRETE WALK | 9,020 SF | $4.95 | $45k | 6% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 184 CY | $240 | $44k | 6% |
| 202E23000 PAVEMENT REMOVED | 1,529 SY | $28 | $43k | 6% |
| 611E98150 CATCH BASIN, NO. 3 | 10 EACH | $3,200 | $32k | 4% |
| 609E12000 COMBINATION CURB AND GUTTER, TYPE 2 | 1,755 FT | $17.25 | $30k | 4% |
| 203E35120 GRANULAR MATERIAL, TYPE C | 353 CY | $69.85 | $25k | 3% |
| 204E13000 EXCAVATION OF SUBGRADE | 529 CY | $45 | $24k | 3% |
| 611E10600 24" CONDUIT, TYPE C | 390 FT | $60 | $23k | 3% |