CUY-US 42-16.62 Utility Part 2
CUY County · est $1.4M
Bid dateThursday, May 17—
CUY County · est $1.4M
Published by ODOTon this contract’s Proposal PDF · DBE Goal: 6.0%
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 24 more items below.
| Item | Quantity | R1Eclipse CO LLC | R2S E T INC | R3Terrace Construction CO INC | R4Perk Company INC | % of bid |
|---|---|---|---|---|---|---|
| 625E23308 DISTRIBUTION CABLE, MISC.: CPP STANDARD CABLE | 33,180 FT | $11.00 | $13.50 | $11.50 | $16.90 | 26% |
| 625E25803 CONDUIT, CONCRETE ENCASED, AS PER PLAN, 5" | 2,370 FT | $110 | $118 | $87.00 | $175 | 18% |
| 625E29000 TRENCH | 2,370 FT | $89.00 | $95.00 | $108 | $160 | 15% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 603 CY | $135 | $155 | $185 | $135 | 6% |
| Item | Quantity | R1Eclipse CO LLC | R2S E T INC | R3Terrace Construction CO INC | R4Perk Company INC |
|---|---|---|---|---|---|
| 202E30000 WALK REMOVED | 500 SF | $2.00 | $2.00 | $1.30 | $5.00 |
| 202E32000 CURB REMOVED | 1,772 FT | $3.50 | $6.00 | $3.10 | $4.95 |
| 202E35100 PIPE REMOVED, 24" AND UNDER | 50 FT | $10.50 | $20.00 | $16.50 | $10.00 |
| 202E75000 FENCE REMOVED | 259 FT | $3.50 | $6.00 | $2.70 | $6.50 |
| 608E10000 4" CONCRETE WALK | 500 SF |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 611E99690 MANHOLE, MISC.: CPP STANDARD MANHOLE |
| 5 EACH |
| $15,356 |
| $22,520 |
| $29,500 |
| $35,700 |
| 5% |
| 611E13400 30" CONDUIT, TYPE B, 748.01 | 80 FT | $936 | $458 | $684 | $650 | 5% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $48,558 | $16,000 | $9,990 | $30,000 | 3% |
| 609E98000 CURB, MISC.: CITY OF CLEVELAND CURB | 1,772 FT | $23.50 | $30.00 | $18.00 | $32.00 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40,000 | $100,000 | $88,000 | 3% |
| 304E20000 AGGREGATE BASE | 603 CY | $62.50 | $56.00 | $52.00 | $64.00 | 3% |
| 202E23000 PAVEMENT REMOVED | 3,674 SY | $9.50 | $7.00 | $19.50 | $17.00 | 2% |
| 441E50300 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 448 (176 CY | $140 | $161 | $164 | $140 | 2% |
| 611E97600 CONDUIT, MISC.: BRICK SEWER CONCRETE REINFORCEMENT | 120 CY | $205 | $512 | $400 | $500 | 2% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 126 CY | $175 | $196 | $199 | $170 | 2% |
| 611E99690 MANHOLE, MISC.: WPC STANDARD MANHOLE | 1 EACH | $22,000 | $5,180 | $21,000 | $26,400 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $20,513 | $55,000 | $43,300 | $94,300 | 1% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $11,500 | $15,000 | $25,000 | $5,600 | 1% |
| 607E23000 FENCE, TYPE CLT | 259 FT | $34.50 | $23.00 | $23.00 | $19.75 | 1% |
| 659E00300 TOPSOIL | 178 CY | $50.00 | $44.00 | $47.00 | $50.00 | 1% |
| 201E11000 CLEARING AND GRUBBING | 1 LS | $8,500 | $19,500 | $1,500 | $10,165 | 1% |
| $7.50 |
| $7.00 |
| $6.00 |
| $10.40 |
| 659E00100 SOIL ANALYSIS TEST | 2 EACH | $158 | $115 | $59.00 | $500 |
| 659E00510 SEEDING AND MULCHING, CLASS 2 | 1,600 SY | $2.75 | $2.00 | $1.00 | $2.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 80 SY | $0.50 | $1.00 | $2.40 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.22 TON | $315 | $719 | $821 | $1,000 |
| 659E31000 LIME | 0.33 ACRE | $105 | $127 | $11.52 | $1,000 |
| 659E35000 WATER | 9 MGAL | $1.00 | $115 | $11.50 | $50.00 |
| 832E30000 EROSION CONTROL | 7,600 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 611E04400 12" CONDUIT, TYPE B, 706.08 | 93 FT | $83.50 | $114 | $136 | $260 |
| 611E98690 CATCH BASIN, MISC.: CITY OF CLEVELAND CB-1 CATCH | 1 EACH | $2,221 | $3,000 | $3,443 | $3,950 |
| 407E10000 TACK COAT | 434 GAL | $2.00 | $2.00 | $2.40 | $2.00 |
| 452E10050 6" NON-REINFORCED CONCRETE PAVEMENT, CLASS QC MS | 57 SY | $79.50 | $75.00 | $58.00 | $83.35 |
| 611E00900 6" CONDUIT, TYPE B, 706.08 | 50 FT | $57.00 | $28.00 | $107 | $350 |
| 611E97200 CONDUIT, MISC.:CONDUIT CORING | 2 EACH | $3,706 | $250 | $240 | $500 |
| 625E36000 PLASTIC CAUTION TAPE | 4,740 FT | $0.50 | $1.00 | $0.25 | $1.00 |
| 690E98400 SPECIAL - CPP COORDINATION | 1 LS | $2,279 | $5,000 | $1,121 | $5,000 |
| 614E12420 DETOUR SIGNING | 1 LS | $7,872 | $10,000 | $7,544 | $7,500 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 0.4 SNMT | $1,400 | $1,208 | $1,821 | $3,200 |
| 108E30000 CPM PROGRESS SCHEDULE SHORT DURATION PROJECTS | 1 LS | $4,000 | $5,000 | $2,522 | $3,000 |
| 619E16011 FIELD OFFICE, TYPE B, AS PER PLAN | 4 MNTH | $500 | $650 | $3,000 | $2,120 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 625E23308 DISTRIBUTION CABLE, MISC.: CPP STANDARD CABLE | 33,180 FT | $11 | $365k | 24% |
| 625E25803 CONDUIT, CONCRETE ENCASED, AS PER PLAN, 5" | 2,370 FT | $110 | $261k | 17% |
| 625E29000 TRENCH | 2,370 FT | $89 | $211k | 14% |
| 301E46000 ASPHALT CONCRETE BASE, PG64-22 | 603 CY | $135 | $81k | 5% |
| 611E99690 MANHOLE, MISC.: CPP STANDARD MANHOLE | 5 EACH | $15,356 | $77k | 5% |
| 611E13400 30" CONDUIT, TYPE B, 748.01 | 80 FT | $936 | $75k | 5% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $48,558 | $49k | 3% |
| 609E98000 CURB, MISC.: CITY OF CLEVELAND CURB | 1,772 FT | $23.5 | $42k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 3% |
| 304E20000 AGGREGATE BASE | 603 CY | $62.5 | $38k | 3% |