HAM-CR 457-01.52
HAM County · est $0.4M
Bid dateThursday, September 29—
HAM County · est $0.4M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 57 more items below.
| Item | Quantity | R1Bansal Construction INC | R2Complete General Construction Company | R3Prus Construction Company | R4Capital Electric Line Builders INC | % of bid |
|---|---|---|---|---|---|---|
| 609E26000 CURB, TYPE 6 | 577 FT | $55.00 | $37.00 | $55.00 | $29.25 | 9% |
| 625E25908 CONDUIT, JACKED OR DRILLED, 725.052 , 4" | 312 FT | $100 | $62.00 | $72.00 | $46.62 | 9% |
| 632E72110 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 4 | 2 EACH | $15,550 | $14,900 | $14,730 | $17,827 | 9% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,000 | $40,000 | $50,000 | $25,120 | 8% |
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 4 EACH | $7,265 | $7,000 | $7,915 | $8,436 | 8% |
| 632E72140 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 13 | 1 EACH | $21,480 | $21,000 | $20,790 |
| Item | Quantity | R1Bansal Construction INC | R2Complete General Construction Company | R3Prus Construction Company | R4Capital Electric Line Builders INC |
|---|---|---|---|---|---|
| 202E30000 WALK REMOVED | 140 SF | $10.00 | $13.00 | $35.00 | $35.10 |
| 202E32000 CURB REMOVED | 59 FT | $25.00 | $22.00 | $70.00 | $35.10 |
| 203E10000 EXCAVATION | 4 CY | $150 | $575 | $450 | $351 |
| 203E35120 GRANULAR MATERIAL, TYPE C | 62 CY | $90.00 | $99.00 | $300 | $287 |
| 204E10000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $24,108 |
| 6% |
| 632E64010 SIGNAL SUPPORT FOUNDATION | 4 EACH | $5,000 | $6,500 | $6,700 | $6,599 | 6% |
| 632E72130 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 12 | 1 EACH | $17,475 | $16,850 | $16,870 | $19,865 | 5% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449), (449) | 25 CY | $680 | $680 | $750 | $831 | 5% |
| 633E65511 CABINET, TYPE TS-2, AS PER PLAN | 1 EACH | $16,125 | $15,555 | $15,000 | $17,667 | 4% |
| 202E23000 PAVEMENT REMOVED | 352 SY | $45.00 | $29.50 | $85.00 | $70.20 | 4% |
| 611E04400 12" CONDUIT, TYPE B | 47 FT | $300 | $400 | $225 | $638 | 4% |
| 609E72000 CONCRETE MEDIAN | 187 SY | $75.00 | $68.50 | $115 | $72.54 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $13,000 | $40,000 | $10,000 | $18,018 | 4% |
| 632E05006 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, | 11 EACH | $1,090 | $920 | $1,150 | $1,042 | 3% |
| 608E52000 CURB RAMP | 263 SF | $45.00 | $26.00 | $45.00 | $28.08 | 3% |
| 304E20000 AGGREGATE BASE | 56 CY | $175 | $140 | $200 | $304 | 3% |
| 441E50200 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 1 | 448 (8 CY | $1,055 | $1,055 | $900 | $1,053 | 2% |
| 832E30000 EROSION CONTROL, INLET PROTECTION | 8,300 EACH | $1.00 | $1.00 | $1.00 | $1.00 | 2% |
| 441E50000 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (448), PG | 7 CY | $1,170 | $1,170 | $1,000 | $1,667 | 2% |
| 352 SY |
| $7.00 |
| $7.00 |
| $3.00 |
| $23.40 |
| 878E25000 INSPECTION AND COMPACTION TESTING OF UNBOUND MATER | 1 LS | $3,250 | $3,600 | $4,000 | $3,510 |
| 659E00300 TOPSOIL | 0.5 CY | $500 | $865 | $625 | $6,201 |
| 659E10000 SEEDING AND MULCHING | 5 SY | $40.00 | $98.00 | $105 | $380 |
| 605E14000 6" BASE PIPE UNDERDRAINS | 281 FT | $25.00 | $22.00 | $40.00 | $58.50 |
| 611E00510 6" CONDUIT, TYPE F FOR UNDERDRAIN OUTLETS | 10 FT | $45.00 | $84.00 | $110 | $76.05 |
| 611E98180 CATCH BASIN, NO. 3A | 1 EACH | $4,500 | $5,300 | $6,500 | $7,254 |
| 407E20000 NON-TRACKING TACK COAT | 15 GAL | $216 | $216 | $9.00 | $7.02 |
| 620E00500 DELINEATOR, POST GROUND MOUNTED | 24 EACH | $105 | $105 | $105 | $123 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 166 FT | $18.00 | $18.00 | $18.00 | $21.06 |
| 630E80100 SIGN, FLAT SHEET | 45 SF | $32.00 | $32.00 | $32.00 | $37.44 |
| 642E30000 REMOVAL OF PAVEMENT MARKING | 550 FT | $8.70 | $8.70 | $8.70 | $10.18 |
| 644E00100 EDGE LINE, 4" | 0.35 MILE | $4,070 | $4,070 | $4,070 | $4,762 |
| 644E00300 CENTER LINE | 0.15 MILE | $7,965 | $7,965 | $7,965 | $9,319 |
| 644E00400 CHANNELIZING LINE, 8" | 1,116 FT | $1.25 | $1.25 | $1.25 | $1.46 |
| 644E00500 STOP LINE | 118 FT | $8.00 | $8.00 | $8.00 | $9.36 |
| 644E00630 CROSSWALK LINE, 24" | 230 FT | $6.00 | $6.00 | $6.00 | $7.02 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 160 FT | $7.00 | $7.00 | $7.00 | $8.19 |
| 644E00720 CHEVRON MARKING | 410 FT | $7.00 | $7.00 | $7.00 | $8.19 |
| 644E00900 ISLAND MARKING | 107 SF | $6.00 | $6.00 | $6.00 | $7.02 |
| 644E01300 LANE ARROW | 9 EACH | $100 | $100 | $100 | $117 |
| 644E01400 WORD ON PAVEMENT, 72" | 2 EACH | $120 | $120 | $120 | $140 |
| 644E01514 DOTTED LINE, 8" | 218 FT | $1.75 | $1.75 | $1.75 | $2.05 |
| 625E25408 CONDUIT, 2", 725.051 | 87 FT | $5.50 | $16.00 | $7.50 | $12.98 |
| 625E25604 CONDUIT, 4", 725.051 | 57 FT | $11.85 | $28.00 | $17.50 | $28.27 |
| 625E29000 TRENCH | 134 FT | $10.50 | $10.00 | $14.00 | $29.98 |
| 625E30706 PULL BOX, 725.08, 24" | 5 EACH | $1,050 | $1,550 | $1,540 | $1,574 |
| 625E32000 GROUND ROD | 7 EACH | $330 | $275 | $340 | $292 |
| 630E79100 SIGN HANGER ASSEMBLY, MAST ARM | 8 EACH | $405 | $405 | $380 | $474 |
| 630E79200 SIGN ATTACHMENT ASSEMBLY, MAST ARM | 4 EACH | $450 | $450 | $50.00 | $527 |
| 630E80100 SIGN, FLAT SHEET | 92 SF | $32.00 | $32.00 | $30.00 | $37.44 |
| 632E05086 VEHICULAR SIGNAL HEAD, (LED), 5-SECTION, 12" LENS, | 2 EACH | $1,675 | $1,400 | $1,630 | $1,670 |
| 632E20731 PEDESTRIAN SIGNAL HEAD (LED), TYPE D2, COUNTDOWN, | 4 EACH | $580 | $625 | $710 | $622 |
| 632E25000 COVERING OF VEHICULAR SIGNAL HEAD | 13 EACH | $75.00 | $40.00 | $5.00 | $30.17 |
| 632E25010 COVERING OF PEDESTRIAN SIGNAL HEAD | 4 EACH | $75.00 | $35.00 | $5.00 | $30.17 |
| 632E26000 PEDESTRIAN PUSHBUTTON | 2 EACH | $230 | $275 | $190 | $246 |
| 632E40300 SIGNAL CABLE, 3 CONDUCTOR, NO. 14 AWG | 327 FT | $1.85 | $3.10 | $2.85 | $3.33 |
| 632E40500 SIGNAL CABLE, 5 CONDUCTOR, NO. 14 AWG | 504 FT | $2.10 | $3.85 | $3.15 | $3.74 |
| 632E40700 SIGNAL CABLE, 7 CONDUCTOR, NO. 14 AWG | 1,987 FT | $2.35 | $4.60 | $3.55 | $3.98 |
| 632E64020 PEDESTAL FOUNDATION | 2 EACH | $1,280 | $1,400 | $1,000 | $1,638 |
| 632E68200 POWER CABLE, 2 CONDUCTOR, NO. 6 AWG | 102 FT | $4.30 | $7.00 | $4.15 | $102 |
| 632E70001 POWER SERVICE, AS PER PLAN | 1 EACH | $5,000 | $3,600 | $3,500 | $2,457 |
| 632E89901 PEDESTAL, 8', TRANSFORMER BASE, AS PER PLAN | 2 EACH | $1,060 | $1,900 | $550 | $2,327 |
| 632E90101 REMOVAL OF TRAFFIC SIGNAL INSTALLATION, AS PER PLA | 1 EACH | $4,500 | $3,500 | $4,870 | $8,471 |
| 632E90400 SIGNALIZATION, MISC.:MODIFY SIGNAL PHASING | 1 EACH | $1,725 | $1,500 | $800 | $293 |
| 633E67100 CABINET FOUNDATION | 1 EACH | $1,565 | $3,600 | $2,500 | $2,984 |
| 633E67200 CONTROLLER WORK PAD | 1 EACH | $875 | $1,800 | $1,400 | $1,720 |
| 633E75001 UNINTERRUPTIBLE POWER SUPPLY (UPS), 1000 WATT, AS | 1 EACH | $7,600 | $6,000 | $7,225 | $8,085 |
| 633E99000 CONTROLLER ITEM, MISC.:INSTALL COORDINATED TIMING | 3 EACH | $1,150 | $850 | $400 | $585 |
| 805E00101 GLOBAL POSITIONING SYSTEM CLOCK ASSEMBLY, AS PER P | 4 EACH | $1,065 | $1,500 | $1,100 | $1,520 |
| 809E69123 ATC CONTROLLER, AS PER PLAN | 1 EACH | $5,160 | $5,000 | $5,100 | $5,725 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $3,746 | $5,000 | $7,500 | $6,505 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $6,000 | $3,000 | $7,500 | $7,371 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 609E26000 CURB, TYPE 6 | 577 FT | $55 | $32k | 6% |
| 625E25908 CONDUIT, JACKED OR DRILLED, 725.052 , 4" | 312 FT | $100 | $31k | 6% |
| 632E72110 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 4 | 2 EACH | $15,550 | $31k | 6% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $30,000 | $30k | 6% |
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 4 EACH | $7,265 | $29k | 6% |
| 632E72140 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 13 | 1 EACH | $21,480 | $21k | 4% |
| 632E64010 SIGNAL SUPPORT FOUNDATION | 4 EACH | $5,000 | $20k | 4% |
| 632E72130 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 12 | 1 EACH | $17,475 | $17k | 4% |
| 301E56000 ASPHALT CONCRETE BASE, PG64-22, (449), (449) | 25 CY | $680 | $17k | 3% |
| 633E65511 CABINET, TYPE TS-2, AS PER PLAN | 1 EACH | $16,125 | $16k | 3% |