D01-TSG-FY2024
D01 County · est $0.7M
Bid dateThursday, July 13—
D01 County · est $0.7M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 49 more items below.
| Item | Quantity | R1Perram Electric INC | R2Miller Cable Company | R3Complete General Construction Company | % of bid |
|---|---|---|---|---|---|
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 11 EACH | $8,405 | $9,200 | $8,000 | 15% |
| 632E64010 SIGNAL SUPPORT FOUNDATION | 10 EACH | $7,025 | $10,000 | $9,000 | 11% |
| 809E69001 ADVANCE RADAR DETECTION, AS PER PLAN | 6 EACH | $8,405 | $9,600 | $9,000 | 8% |
| 632E72141 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 13, AS PER P | 2 EACH | $19,820 | $20,500 | $23,000 | 6% |
| 633E65521 CABINET, TYPE 332, AS PER PLAN | 3 EACH | $13,055 | $14,000 | $16,000 | 6% |
| 632E72131 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 12, AS PER P | 2 EACH | $17,020 | $17,100 | $19,000 | 5% |
| 632E71384 SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 10 POLE, WITH | 1 EACH |
| Item | Quantity | R1Perram Electric INC | R2Miller Cable Company | R3Complete General Construction Company |
|---|---|---|---|---|
| 202E32500 CURB AND GUTTER REMOVED | 13 FT | $20.00 | $25.00 | $26.00 |
| 608E52001 CURB RAMP, AS PER PLAN | 99 SF | $70.00 | $85.00 | $64.00 |
| 690E50600 SPECIAL - BOLLARD | 3 EACH | $2,480 | $4,000 | $3,680 |
| 659E00300 TOPSOIL | 30 CY | $30.00 | $100 | $70.00 |
| 659E10000 SEEDING AND MULCHING | 260 SY | $0.40 | $12.80 | $12.80 |
| 659E20000 COMMERCIAL FERTILIZER |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $29,185 |
| $33,500 |
| $37,000 |
| 5% |
| 625E25908 CONDUIT, JACKED OR DRILLED, 725.052, 3" | 603 FT | $48.15 | $37.00 | $27.00 | 5% |
| 633E74001 UNINTERRUPTIBLE POWER SUPPLY (UPS), AS PER PLAN | 3 EACH | $8,240 | $7,000 | $8,300 | 4% |
| 632E79151 COMBINATION SIGNAL SUPPORT, TYPE TC-81.22, DESIGN | 1 EACH | $22,895 | $24,250 | $25,000 | 4% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $22,510 | $24,714 | $28,000 | 4% |
| 632E72151 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 14, AS PER P | 1 EACH | $21,685 | $23,000 | $23,750 | 3% |
| 632E79141 COMBINATION SIGNAL SUPPORT, TYPE TC-81.22, DESIGN | 1 EACH | $21,200 | $22,100 | $24,000 | 3% |
| 632E71240 SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 6 POLE, WITH | 1 EACH | $20,235 | $23,000 | $23,000 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $20,000 | $20,000 | $20,000 | 3% |
| 809E69123 ATC CONTROLLER, AS PER PLAN | 3 EACH | $6,245 | $7,200 | $7,250 | 3% |
| 632E05006 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, | 18 EACH | $980 | $965 | $1,000 | 3% |
| 632E05086 VEHICULAR SIGNAL HEAD, (LED), 5-SECTION, 12" LENS, | 10 EACH | $1,700 | $1,645 | $1,800 | 3% |
| 632E72130 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 12 | 1 EACH | $16,310 | $17,250 | $19,000 | 3% |
| 632E90101 REMOVAL OF TRAFFIC SIGNAL INSTALLATION, AS PER PLA | 4 EACH | $3,945 | $1,600 | $3,600 | 3% |
| 0.05 TON |
| $2,000 |
| $900 |
| $900 |
| 659E35000 WATER | 2 MGAL | $10.00 | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 |
| 630E79100 SIGN HANGER ASSEMBLY, MAST ARM | 14 EACH | $360 | $485 | $485 |
| 630E80100 SIGN, FLAT SHEET | 152 SF | $26.00 | $17.50 | $17.50 |
| 630E87520 REMOVAL OF POLE MOUNTED SIGN AND REERECTION | 1 EACH | $200 | $295 | $295 |
| 643E00500 STOP LINE | 37 FT | $58.00 | $58.10 | $10.00 |
| 643E00631 CROSSWALK LINE, 24", AS PER PLAN | 66 FT | $58.00 | $58.10 | $12.00 |
| 643E30010 REMOVAL OF PAVEMENT MARKING | 43 SF | $79.50 | $79.35 | $8.50 |
| 625E00450 CONNECTION, FUSED PULL APART | 2 EACH | $170 | $120 | $160 |
| 625E00460 CONNECTION, UNFUSED PULL APART | 2 EACH | $170 | $120 | $160 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 3 EACH | $165 | $120 | $125 |
| 625E18510 BRACKET ARM, 30' | 2 EACH | $1,845 | $1,900 | $2,750 |
| 625E23306 NO. 10 AWG 600 VOLT DISTRIBUTION CABLE | 815 FT | $1.47 | $2.00 | $1.50 |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE | 366 FT | $0.85 | $1.80 | $2.50 |
| 625E25400 CONDUIT, 2", 725.04 | 8 FT | $64.25 | $65.00 | $26.00 |
| 625E25500 CONDUIT, 3", 725.04 | 76 FT | $44.10 | $85.00 | $37.00 |
| 625E26252 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED), 8500 | 2 EACH | $455 | $400 | $425 |
| 625E29002 TRENCH, 24" DEEP | 84 FT | $18.55 | $24.00 | $10.00 |
| 625E30706 PULL BOX, 725.08, 24" | 8 EACH | $1,950 | $1,500 | $1,650 |
| 625E31510 PULL BOX REMOVED | 30 EACH | $290 | $45.00 | $175 |
| 625E32000 GROUND ROD | 14 EACH | $315 | $225 | $325 |
| 632E20731 PEDESTRIAN SIGNAL HEAD (LED), TYPE D2, COUNTDOWN, | 3 EACH | $510 | $590 | $700 |
| 632E25000 COVERING OF VEHICULAR SIGNAL HEAD | 28 EACH | $10.00 | $40.00 | $40.00 |
| 632E25010 COVERING OF PEDESTRIAN SIGNAL HEAD | 4 EACH | $5.00 | $30.00 | $35.00 |
| 632E26000 PEDESTRIAN PUSHBUTTON | 1 EACH | $285 | $220 | $300 |
| 632E26001 PEDESTRIAN PUSHBUTTON, AS PER PLAN | 2 EACH | $975 | $750 | $850 |
| 632E40500 SIGNAL CABLE, 5 CONDUCTOR, NO. 14 AWG | 444 FT | $2.45 | $2.60 | $2.50 |
| 632E40700 SIGNAL CABLE, 7 CONDUCTOR, NO. 14 AWG | 3,163 FT | $2.67 | $2.80 | $3.00 |
| 632E64020 PEDESTAL FOUNDATION | 3 EACH | $1,460 | $1,000 | $1,650 |
| 632E69300 POWER CABLE, 3 CONDUCTOR, NO. 4 AWG | 137 FT | $6.80 | $10.00 | $7.25 |
| 632E69900 SERVICE CABLE, 3 CONDUCTOR, NO. 4 AWG | 208 FT | $7.65 | $10.00 | $7.25 |
| 632E70001 POWER SERVICE, AS PER PLAN | 3 EACH | $2,220 | $2,100 | $2,600 |
| 632E89901 PEDESTAL, 8', TRANSFORMER BASE, AS PER PLAN | 2 EACH | $1,115 | $700 | $1,825 |
| 632E90010 PEDESTAL, MISC.:ReUse of Pedestrian Signal Head, P | 1 EACH | $1,330 | $600 | $1,200 |
| 632E90020 REMOVAL OF MISCELLANEOUS TRAFFIC SIGNAL ITEM:, Se | 1 EACH | $570 | $400 | $1,300 |
| 632E90500 SIGNALIZATION, MISC.:ADA Locator Tone Push Button | 434 FT | $2.25 | $2.60 | $2.50 |
| 633E67100 CABINET FOUNDATION | 3 EACH | $3,300 | $3,250 | $5,700 |
| 633E67200 CONTROLLER WORK PAD | 3 EACH | $860 | $750 | $1,850 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 160 HOUR | $70.00 | $77.00 | $95.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $9,487 | $7,185 | $6,500 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $3,500 | $6,800 | $5,000 |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $1,650 | $4,000 | $6,000 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $1,650 | $4,000 | $6,200 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 11 EACH | $8,405 | $92k | 12% |
| 632E64010 SIGNAL SUPPORT FOUNDATION | 10 EACH | $7,025 | $70k | 9% |
| 809E69001 ADVANCE RADAR DETECTION, AS PER PLAN | 6 EACH | $8,405 | $50k | 7% |
| 632E72141 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 13, AS PER P | 2 EACH | $19,820 | $40k | 5% |
| 633E65521 CABINET, TYPE 332, AS PER PLAN | 3 EACH | $13,055 | $39k | 5% |
| 632E72131 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 12, AS PER P | 2 EACH | $17,020 | $34k | 4% |
| 632E71384 SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 10 POLE, WITH | 1 EACH | $29,185 | $29k | 4% |
| 625E25908 CONDUIT, JACKED OR DRILLED, 725.052, 3" | 603 FT | $48.15 | $29k | 4% |
| 633E74001 UNINTERRUPTIBLE POWER SUPPLY (UPS), AS PER PLAN | 3 EACH | $8,240 | $25k | 3% |
| 632E79151 COMBINATION SIGNAL SUPPORT, TYPE TC-81.22, DESIGN | 1 EACH | $22,895 | $23k | 3% |