HAN-US 224-17.67 Signal
HAN County · est $0.3M
Bid dateThursday, August 10—
HAN County · est $0.3M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 34 more items below.
| Item | Quantity | R1Miller Cable Company | R2Greenwich Electric INC | R3Perram Electric INC | R4Complete General Construction Company | % of bid |
|---|---|---|---|---|---|---|
| 632E64010 SIGNAL SUPPORT FOUNDATION | 3 EACH | $9,100 | $9,400 | $7,265 | $10,500 | 13% |
| 632E78361 COMBINATION SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 1 | 1 EACH | $23,500 | $22,000 | $21,145 | $19,000 | 11% |
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 3 EACH | $7,700 | $8,650 | $8,555 | $9,000 | 11% |
| 632E72151 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 14, AS PER P | 1 EACH | $22,500 | $22,500 | $21,780 | $27,000 | 11% |
| 632E72131 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 12, AS PER P | 1 EACH | $18,750 | $18,500 | $18,360 | $21,000 | 9% |
| 633E65511 CABINET, TYPE TS-2, AS PER PLAN | 1 EACH | $16,500 | $16,542 | $16,425 |
| Item | Quantity | R1Miller Cable Company | R2Greenwich Electric INC | R3Perram Electric INC | R4Complete General Construction Company |
|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $55.00 | $2,500 | $3,475 | $5,000 |
| 202E75000 FENCE REMOVED | 35 FT | $65.00 | $20.00 | $21.25 | $15.00 |
| 623E50000 PRECONSTRUCTION SURVEY MONUMENT VERIFICATION AND R | 1 LS | $1,750 | $1,000 | $1,250 | $2,000 |
| 623E51000 POST CONSTRUCTION SURVEY MONUMENT VERIFICATION AND | 1 LS | $1,750 | $1,000 | $1,250 | $2,000 |
| 653E10000 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $18,000 |
| 8% |
| 809E69001 ADVANCE RADAR DETECTION, AS PER PLAN | 2 EACH | $8,000 | $9,000 | $8,885 | $10,000 | 8% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $9,700 | $10,000 | $10,000 | 5% |
| 625E25908 CONDUIT, JACKED OR DRILLED, 725.052, 4" | 146 FT | $56.00 | $43.00 | $51.55 | $70.00 | 4% |
| 633E74001 UNINTERRUPTIBLE POWER SUPPLY (UPS), AS PER PLAN | 1 EACH | $6,000 | $6,575 | $7,020 | $8,500 | 3% |
| 632E05006 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, | 5 EACH | $1,000 | $967 | $1,030 | $1,200 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $4,890 | $5,000 | $12,025 | $5,000 | 2% |
| 809E69123 ATC CONTROLLER, AS PER PLAN | 1 EACH | $4,850 | $4,900 | $4,865 | $10,000 | 2% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $4,550 | $1,500 | $2,500 | $3,000 | 2% |
| 809E69231 PREEMPT PHASE SELECTOR, AS PER PLAN | 1 EACH | $4,300 | $4,300 | $4,200 | $4,600 | 2% |
| 625E30706 PULL BOX, 725.08, 24" | 3 EACH | $1,250 | $1,365 | $1,880 | $1,200 | 2% |
| 625E29002 TRENCH, 24" DEEP | 154 FT | $24.00 | $13.00 | $18.30 | $20.00 | 2% |
| 642E30000 REMOVAL OF PAVEMENT MARKING | 129 FT | $25.00 | $11.10 | $11.10 | $11.25 | 2% |
| 633E67100 CABINET FOUNDATION | 1 EACH | $3,100 | $3,000 | $3,260 | $4,500 | 1% |
| 625E25500 CONDUIT, 3", 725.04 | 154 FT | $20.00 | $34.35 | $42.35 | $27.00 | 1% |
| 8 CY |
| $200 |
| $185 |
| $35.00 |
| $190 |
| 654E11000 COMMERCIAL FERTILIZER | 0.01 TON | $500 | $1,200 | $2,000 | $45,000 |
| 659E10000 SEEDING AND MULCHING | 70 SY | $40.00 | $15.00 | $0.30 | $11.00 |
| 659E35000 WATER | 1 MGAL | $1.00 | $100 | $10.00 | $100 |
| 832E30000 EROSION CONTROL | 1,000 EACH | $1.00 | $1.00 | $1.00 | $1.00 |
| 621E54000 RAISED PAVEMENT MARKER REMOVED | 4 EACH | $140 | $30.00 | $95.00 | $100 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 144 FT | $12.00 | $15.00 | $19.50 | $22.00 |
| 630E08600 SIGN POST REFLECTOR | 9 EACH | $50.00 | $35.00 | $118 | $45.00 |
| 630E79500 SIGN SUPPORT ASSEMBLY, POLE MOUNTED | 4 EACH | $100 | $175 | $345 | $170 |
| 630E80100 SIGN, FLAT SHEET | 89.9 SF | $24.00 | $28.00 | $23.50 | $25.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 7 EACH | $15.00 | $25.00 | $26.55 | $60.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 7 EACH | $15.00 | $45.00 | $55.00 | $16.00 |
| 642E30020 REMOVAL OF PAVEMENT MARKING | 2 EACH | $150 | $150 | $150 | $150 |
| 644E00500 STOP LINE | 48 FT | $20.00 | $20.00 | $20.00 | $20.00 |
| 644E01300 LANE ARROW | 2 EACH | $250 | $200 | $200 | $200 |
| 625E32000 GROUND ROD | 3 EACH | $245 | $310 | $310 | $400 |
| 632E05086 VEHICULAR SIGNAL HEAD, (LED), 5-SECTION, 12" LENS, | 1 EACH | $1,700 | $1,650 | $1,835 | $2,355 |
| 632E25000 COVERING OF VEHICULAR SIGNAL HEAD | 6 EACH | $70.00 | $25.00 | $10.00 | $65.00 |
| 632E40400 SIGNAL CABLE, 4 CONDUCTOR, NO. 14 AWG | 569 FT | $2.80 | $2.65 | $2.40 | $4.00 |
| 632E40700 SIGNAL CABLE, 7 CONDUCTOR, NO. 14 AWG | 583 FT | $3.00 | $3.10 | $2.65 | $5.00 |
| 632E66104 POWER CABLE, 3 CONDUCTOR, NO. 10 AWG | 44 FT | $5.00 | $3.85 | $5.15 | $5.50 |
| 632E69700 SERVICE CABLE, 3 CONDUCTOR, NO. 8 AWG | 90 FT | $6.00 | $5.40 | $3.85 | $7.50 |
| 632E70001 POWER SERVICE, AS PER PLAN | 1 EACH | $1,800 | $1,900 | $1,945 | $3,000 |
| 633E67200 CONTROLLER WORK PAD | 1 EACH | $600 | $500 | $470 | $2,800 |
| 809E69201 EMERGENCY VEHICLE PREEMPTION, AS PER PLAN | 1 EACH | $820 | $900 | $800 | $1,500 |
| 809E69211 PREEMPT RECEIVING UNIT, AS PER PLAN | 3 EACH | $1,000 | $960 | $1,020 | $1,200 |
| 809E69221 PREEMPT DETECTOR CABLE, AS PER PLAN | 569 FT | $4.00 | $3.00 | $3.25 | $4.50 |
| 809E69241 PREEMPT CONFIRMATION LIGHT, AS PER PLAN | 3 EACH | $625 | $480 | $565 | $650 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 24 HOUR | $76.00 | $70.00 | $70.00 | $90.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $2,379 | $7,850 | $4,210 | $1,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 632E64010 SIGNAL SUPPORT FOUNDATION | 3 EACH | $9,100 | $27k | 11% |
| 632E78361 COMBINATION SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 1 | 1 EACH | $23,500 | $24k | 9% |
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 3 EACH | $7,700 | $23k | 9% |
| 632E72151 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 14, AS PER P | 1 EACH | $22,500 | $23k | 9% |
| 632E72131 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 12, AS PER P | 1 EACH | $18,750 | $19k | 7% |
| 633E65511 CABINET, TYPE TS-2, AS PER PLAN | 1 EACH | $16,500 | $17k | 7% |
| 809E69001 ADVANCE RADAR DETECTION, AS PER PLAN | 2 EACH | $8,000 | $16k | 6% |
| 624E10000 MOBILIZATION | 1 LS | $10,000 | $10k | 4% |
| 625E25908 CONDUIT, JACKED OR DRILLED, 725.052, 4" | 146 FT | $56 | $8k | 3% |
| 633E74001 UNINTERRUPTIBLE POWER SUPPLY (UPS), AS PER PLAN | 1 EACH | $6,000 | $6k | 2% |