D12-D4/D12 ITS Camera Additions
D12 County · est $3.4M
Bid dateThursday, May 9—
D12 County · est $3.4M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 39 more items below.
| Item | Quantity | R1Perram Electric INC | R2Miller Cable Company | R3Bruce & Merrilees Electric CO INC | R4Asplundh Construction LLC | R5Ruhlin Company | % of bid |
|---|---|---|---|---|---|---|---|
| 809E61002 CCTV CONCRETE POLE, 70 FEET | 32 EACH | $53,095 | $48,000 | $49,742 | $50,987 | $84,500 | 43% |
| 809E61090 CCTV LOWERING UNIT | 32 EACH | $8,825 | $9,000 | $10,786 | $8,596 | $10,287 | 7% |
| 809E65000 ITS CABINET - GROUND MOUNTED | 32 EACH | $8,261 | $14,250 | $9,247 | $12,890 | $13,460 | 7% |
| 304E20000 AGGREGATE BASE | 1,375 CY | $150 | $150 | $83.03 | $108 | $128 | 5% |
| 809E60040 CCTV IP-CAMERA SYSTEM, QUAD MULTI-VIEW FIXED WITH | 32 EACH | $6,300 | $6,600 | $8,415 | $6,549 | $8,806 | 5% |
| 625E30700 PULL BOX, 725.08, 18" |
| Item | Quantity | R1Perram Electric INC | R2Miller Cable Company | R3Bruce & Merrilees Electric CO INC | R4Asplundh Construction LLC | R5Ruhlin Company |
|---|---|---|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $7,500 | $31,000 | $8,480 | $8,657 | $7,488 |
| 202E75000 FENCE REMOVED | 14 FT | $10.00 | $65.00 | $130 | $193 | $10.00 |
| 204E10000 SUBGRADE COMPACTION | 6,145 SY | $2.50 | $6.00 | $25.04 | $1.80 | $5.60 |
| 204E45000 PROOF ROLLING | 8 HOUR | $150 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 103 EACH |
| $1,743 |
| $1,250 |
| $1,270 |
| $1,447 |
| $1,005 |
| 5% |
| 809E02000 32" ITS PULL BOX WITH PAD AND STANDARD LID ASSEMBL | 38 EACH | $3,583 | $4,200 | $2,697 | $4,614 | $2,340 | 3% |
| 203E10000 EXCAVATION | 1,375 CY | $95.00 | $110 | $162 | $46.35 | $97.00 | 3% |
| 625E29010 TRENCH, 30" DEEP | 10,502 FT | $9.85 | $17.00 | $9.50 | $11.46 | $10.20 | 3% |
| 633E67101 CABINET FOUNDATION, AS PER PLAN | 32 EACH | $3,215 | $3,700 | $3,401 | $4,266 | $2,880 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $100,000 | $100,000 | $184,047 | $302,575 | $285,000 | 3% |
| 625E98000 LIGHTING, MISC.:STEP-DOWN TRANSFORMER AND SUPPORT | 9 EACH | $9,047 | $11,000 | $3,239 | $22,522 | $9,180 | 2% |
| 625E25900 CONDUIT, JACKED OR DRILLED, 2"725.052, SCHEDULE 80 | 3,632 FT | $19.45 | $31.00 | $47.85 | $17.66 | $25.00 | 2% |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $70,118 | $25,339 | $28,500 | $99,498 | $23,408 | 2% |
| 625E34001 POWER SERVICE, AS PER PLAN, B | 11 EACH | $5,600 | $6,000 | $8,679 | $9,191 | $5,830 | 2% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $59,476 | $66,000 | $193,990 | $91,670 | $173,687 | 2% |
| 809E24500 CONDUIT, 4", MULTICELL, HDPE WITH 4 ? 1? INNERDUCT | 384 FT | $154 | $30.00 | $33.71 | $23.03 | $42.00 | 2% |
| 625E32001 GROUND ROD, AS PER PLAN | 152 EACH | $317 | $255 | $229 | $204 | $275 | 1% |
| 625E34001 POWER SERVICE, AS PER PLAN, A | 6 EACH | $7,115 | $6,500 | $7,193 | $8,939 | $6,950 | 1% |
| 625E25410 CONDUIT, 2", 725.052 | 9,985 FT | $3.68 | $10.00 | $6.06 | $7.93 | $8.00 | 1% |
| $170 |
| $270 |
| $386 |
| $715 |
| 606E15050 GUARDRAIL, TYPE MGS | 112.5 FT | $54.00 | $75.00 | $54.16 | $51.73 | $49.60 |
| 606E26500 ANCHOR ASSEMBLY, TYPE T | 4 EACH | $1,050 | $2,000 | $1,050 | $2,060 | $975 |
| 607E61200 GATE, TYPE CLT | 1 EACH | $3,925 | $5,200 | $3,925 | $1,030 | $3,720 |
| 659E10000 SEEDING AND MULCHING | 7,000 SY | $4.00 | $9.00 | $3.95 | $7.20 | $3.65 |
| 659E20000 COMMERCIAL FERTILIZER | 1 TON | $1,500 | $500 | $600 | $5,811 | $640 |
| 659E35000 WATER | 40 MGAL | $50.00 | $1.00 | $1.00 | $221 | $1.00 |
| 832E30000 EROSION CONTROL | 11,760 EACH | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 625E22900 NO. 1/0 AWG 2400 VOLT DISTRIBUTION CABLE | 4,207 FT | $6.82 | $7.00 | $12.39 | $6.24 | $9.00 |
| 625E22990 NO. 6 AWG 600 VOLT DISTRIBUTION CABLE | 8,940 FT | $2.02 | $3.00 | $2.70 | $2.59 | $2.50 |
| 625E23000 NO. 4 AWG 600 VOLT DISTRIBUTION CABLE | 510 FT | $2.50 | $4.00 | $3.68 | $3.25 | $3.30 |
| 625E23100 NO. 2 AWG 600 VOLT DISTRIBUTION CABLE | 2,090 FT | $3.65 | $5.00 | $4.94 | $3.79 | $4.50 |
| 625E25408 CONDUIT, 2", 725.051 | 222 FT | $5.65 | $9.00 | $4.90 | $9.01 | $11.20 |
| 625E25504 CONDUIT, 3", 725.051 | 704 FT | $9.90 | $15.00 | $7.50 | $9.62 | $10.50 |
| 625E34001 POWER SERVICE, AS PER PLAN, C | 1 EACH | $8,535 | $10,000 | $6,000 | $10,793 | $6,930 |
| 625E34001 POWER SERVICE, AS PER PLAN, D | 3 EACH | $7,020 | $9,500 | $8,147 | $9,290 | $4,735 |
| 625E34001 POWER SERVICE, AS PER PLAN, E | 2 EACH | $5,665 | $4,500 | $5,231 | $5,419 | $5,225 |
| 625E34001 POWER SERVICE, AS PER PLAN, F | 1 EACH | $3,365 | $4,500 | $3,058 | $4,559 | $5,220 |
| 625E34001 POWER SERVICE, AS PER PLAN, G | 1 EACH | $3,465 | $3,500 | $11,227 | $4,559 | $12,920 |
| 625E34001 POWER SERVICE, AS PER PLAN, H | 2 EACH | $4,380 | $5,500 | $3,409 | $4,795 | $5,390 |
| 625E34001 POWER SERVICE, AS PER PLAN, I | 1 EACH | $3,365 | $3,500 | $5,188 | $4,559 | $4,090 |
| 625E34001 POWER SERVICE, AS PER PLAN, J | 1 EACH | $4,380 | $3,500 | $3,597 | $4,795 | $5,060 |
| 625E34001 POWER SERVICE, AS PER PLAN, K | 1 EACH | $3,465 | $3,500 | $9,166 | $4,559 | $4,340 |
| 625E34001 POWER SERVICE, AS PER PLAN, L | 1 EACH | $6,965 | $3,500 | $12,081 | $8,883 | $16,746 |
| 625E34001 POWER SERVICE, AS PER PLAN, M | 1 EACH | $3,465 | $3,500 | $11,604 | $4,559 | $16,802 |
| 625E36010 UNDERGROUND WARNING/MARKING TAPE | 660 FT | $1.60 | $3.00 | $0.14 | $1.19 | $3.00 |
| 625E36011 UNDERGROUND WARNING/MARKING TAPE, AS PER PLAN | 875 FT | $1.65 | $4.00 | $0.14 | $1.28 | $3.50 |
| 632E70400 CONDUIT RISER, 2" DIAMETER | 7 EACH | $925 | $700 | $1,747 | $1,920 | $1,295 |
| 809E02002 32" ITS PULL BOX WITH PAD AND HINGED LID ASSEMBLY | 2 EACH | $5,670 | $5,500 | $4,715 | $5,899 | $4,475 |
| 809E65990 ITS DEVICE, MISC.: REMOVAL OF POLE OR DEVICE | 3 EACH | $2,840 | $3,000 | $5,606 | $2,854 | $695 |
| 809E70050 AS-BUILT CONSTRUCTION PLANS | 1 LS | $16,980 | $5,500 | $100 | $44,154 | $3,080 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 64 HOUR | $80.00 | $120 | $150 | $206 | $120 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 2 SNMT | $1,385 | $1,750 | $3,601 | $6,180 | $3,800 |
| 616E10000 WATER | 1 MGAL | $50.00 | $1.00 | $500 | $2,587 | $1.00 |
| 809E70000 MAINTAINING ITS DURING CONSTRUCTION | 1 LS | $2,530 | $12,000 | $10,228 | $46,170 | $3,847 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $33,160 | $8,500 | $100 | $45,794 | $24,200 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 809E61002 CCTV CONCRETE POLE, 70 FEET | 32 EACH | $53,095 | $1.70M | 40% |
| 809E61090 CCTV LOWERING UNIT | 32 EACH | $8,825 | $282k | 7% |
| 809E65000 ITS CABINET - GROUND MOUNTED | 32 EACH | $8,261 | $264k | 6% |
| 304E20000 AGGREGATE BASE | 1,375 CY | $150 | $206k | 5% |
| 809E60040 CCTV IP-CAMERA SYSTEM, QUAD MULTI-VIEW FIXED WITH | 32 EACH | $6,300 | $202k | 5% |
| 625E30700 PULL BOX, 725.08, 18" | 103 EACH | $1,743 | $180k | 4% |
| 809E02000 32" ITS PULL BOX WITH PAD AND STANDARD LID ASSEMBL | 38 EACH | $3,583 | $136k | 3% |
| 203E10000 EXCAVATION | 1,375 CY | $95 | $131k | 3% |
| 625E29010 TRENCH, 30" DEEP | 10,502 FT | $9.85 | $103k | 2% |
| 633E67101 CABINET FOUNDATION, AS PER PLAN | 32 EACH | $3,215 | $103k | 2% |