D08-TSG-SIGNALS W R/W
D08 County · est $1.5M
Bid dateThursday, May 23—
D08 County · est $1.5M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 76 more items below.
| Item | Quantity | R1Bansal Construction INC | R2Complete General Construction Company | % of bid |
|---|---|---|---|---|
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 18 EACH | $9,950 | $8,500 | 16% |
| 809E69001 ADVANCE RADAR DETECTION, AS PER PLAN | 12 EACH | $10,300 | $8,800 | 11% |
| 632E64011 SIGNAL SUPPORT FOUNDATION, AS PER PLAN | 15 EACH | $7,980 | $11,500 | 11% |
| 625E25908 CONDUIT, JACKED OR DRILLED, 725.052, 4" | 1,118 FT | $90.00 | $60.00 | 9% |
| 633E65521 CABINET, TYPE 332, AS PER PLAN | 5 EACH | $16,335 | $15,000 | 7% |
| 632E05006 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, | 43 EACH | $1,190 | $1,100 | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $50,000 | $40,000 | 4% |
| 633E75001 UNINTERRUPTIBLE POWER SUPPLY (UPS), 1000 WATT, AS | 5 EACH | $8,575 | $7,500 | 4% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $50,000 | 4% |
| AA2 632E71493 SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 12 POLE, WITH | 1 EACH | $37,160 | $44,000 | 3% |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $35,000 | $10,000 | 3% |
| 608E52000 CURB RAMP | 837 SF | $38.50 | $23.00 | 3% |
| AA2 632E79131 COMBINATION SIGNAL SUPPORT, TYPE TC-81.22, DESIGN | 2 EACH | $15,735 | $20,000 | 3% |
| AA2 632E79301 COMBINATION SIGNAL SUPPORT, TYPE TC-81.22 DESIGN 4 | 2 EACH | $15,500 | $20,000 | 3% |
| 632E64020 PEDESTAL FOUNDATION | 17 EACH | $1,750 | $2,000 | 3% |
| AA2 632E71369 SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 10 POLE, WITH | 1 EACH | $29,380 | $39,000 | 3% |
| 625E34001 POWER SERVICE, AS PER PLAN | 5 EACH | $5,720 | $3,000 | 3% |
| 809E60000 CCTV IP-CAMERA SYSTEM, PTZ | 5 EACH | $5,600 | $6,000 | 2% |
| 632E90101 REMOVAL OF TRAFFIC SIGNAL INSTALLATION, AS PER PLA | 5 EACH | $5,000 | $6,000 | 2% |
| 625E30706 PULL BOX, 725.08, 24" | 20 EACH | $1,225 | $1,200 | 2% |
| Item | Quantity | R1Bansal Construction INC | R2Complete General Construction Company |
|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $1,950 | $1,000 |
| 202E23000 PAVEMENT REMOVED | 40 SY | $49.50 | $140 |
| 202E30000 WALK REMOVED | 818 SF | $7.70 | $10.00 |
| 202E32000 CURB REMOVED | 161 FT | $16.50 | $9.00 |
| 209E10000 DITCH CLEANOUT | 23 FT | $27.50 | $55.00 |
| 253E02000 PAVEMENT REPAIR | 13.6 CY | $275 | $2,100 |
| 304E20000 AGGREGATE BASE | 3.3 CY | $110 |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $2,000 |
| 407E10000 TACK COAT | 0.8 GAL | $110 | $50.00 |
| 441E70500 ASPHALT CONCRETE SURFACE COURSE, TYPE 1, (449) | — | $825 | $6,500 |
| 441E70700 ASPHALT CONCRETE INTERMEDIATE COURSE, TYPE 2 | 449 (0.7 CY | $825 | $6,500 |
| 608E10000 4" CONCRETE WALK | 554 SF | $27.50 | $16.00 |
| 609E26000 CURB, TYPE 6 | 89 FT | $93.50 | $100 |
| 611E00400 4" CONDUIT, TYPE E | 100 FT | $1.00 | $25.00 |
| 611E04900 12" CONDUIT, TYPE D | 36 FT | $275 | $116 |
| 659E00300 TOPSOIL | 100 CY | $140 | $73.50 |
| 659E10000 SEEDING AND MULCHING | 898 SY | $5.00 | $5.00 |
| 659E14000 REPAIR SEEDING AND MULCHING | 45 SY | $1.00 | $1.00 |
| 659E20000 COMMERCIAL FERTILIZER | 0.21 TON | $1,500 | $1,500 |
| 659E31000 LIME | 0.19 ACRE | $200 | $200 |
| 659E35000 WATER | 8 MGAL | $1.00 | $1.00 |
| 832E30000 EROSION CONTROL | 7,500 EACH | $1.00 | $1.00 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 154 FT | $15.18 | $16.00 |
| 630E79100 SIGN HANGER ASSEMBLY, MAST ARM | 40 EACH | $411 | $415 |
| 630E79500 SIGN SUPPORT ASSEMBLY, POLE MOUNTED | 14 EACH | $132 | $135 |
| 630E80100 SIGN, FLAT SHEET | 409 SF | $17.56 | $18.00 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 9 EACH | $25.51 | $30.00 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 11 EACH | $34.01 | $35.00 |
| 630E87500 REMOVAL OF POLE MOUNTED SIGN AND DISPOSAL | 4 EACH | $25.51 | $26.00 |
| 642E30000 REMOVAL OF PAVEMENT MARKING | 1,758 FT | $3.90 | $4.00 |
| 642E30020 REMOVAL OF PAVEMENT MARKING | 14 EACH | $63.00 | $63.00 |
| 644E00300 CENTER LINE | 0.04 MILE | $8,545 | $8,545 |
| 644E00400 CHANNELIZING LINE, 8" | 100 FT | $3.20 | $3.20 |
| 644E00500 STOP LINE | 357 FT | $10.70 | $10.70 |
| 644E00630 CROSSWALK LINE, 24" | 696 FT | $8.55 | $8.55 |
| 644E01300 LANE ARROW | 6 EACH | $169 | $169 |
| 625E23306 NO. 10 AWG 600 VOLT DISTRIBUTION CABLE | 2,811 FT | $1.85 | $2.00 |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE | 1,217 FT | $1.85 | $2.50 |
| 625E25408 CONDUIT, 2", 725.051 | 274 FT | $4.60 | $12.00 |
| 625E25604 CONDUIT, 4", 725.051 | 235 FT | $10.50 | $20.00 |
| 625E26253 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED), AS PER | 7 EACH | $625 | $600 |
| 625E29000 TRENCH | 372 FT | $12.50 | $15.00 |
| 625E29400 TRENCH IN PAVED AREA | 50 FT | $75.00 | $40.00 |
| 625E32000 GROUND ROD | 37 EACH | $465 | $350 |
| 625E36010 UNDERGROUND WARNING/MARKING TAPE | 372 FT | $1.65 | $3.00 |
| 632E05086 VEHICULAR SIGNAL HEAD, (LED), 5-SECTION, 12" LENS, | 7 EACH | $1,940 | $1,625 |
| 632E20731 PEDESTRIAN SIGNAL HEAD (LED), TYPE D2, COUNTDOWN, | 22 EACH | $650 | $575 |
| 632E20750 ACCESSIBLE PEDESTRIAN PUSHBUTTON | 22 EACH | $1,035 | $1,000 |
| 632E25000 COVERING OF VEHICULAR SIGNAL HEAD | 50 EACH | $75.00 | $40.00 |
| 632E25010 COVERING OF PEDESTRIAN SIGNAL HEAD | 22 EACH | $75.00 | $30.00 |
| 632E40200 SIGNAL CABLE, 2 CONDUCTOR, NO. 14 AWG | 2,912 FT | $2.00 | $2.50 |
| 632E40500 SIGNAL CABLE, 5 CONDUCTOR, NO. 14 AWG | 10,448 FT | $2.25 | $3.00 |
| 632E40700 SIGNAL CABLE, 7 CONDUCTOR, NO. 14 AWG | 1,303 FT | $2.50 | $3.25 |
| 632E64950 TEST HOLE PERFORMED | 5 EACH | $1,380 | $6,000 |
| 632E68300 POWER CABLE, 3 CONDUCTOR, NO. 6 AWG | 377 FT | $6.75 | $7.00 |
| 632E69800 SERVICE CABLE, 3 CONDUCTOR, NO. 6 AWG | 167 FT | $6.75 | $7.00 |
| 632E78240 COMBINATION SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 6 | 1 EACH | $19,750 | $35,000 |
| 632E90020 REMOVAL OF MISCELLANEOUS TRAFFIC SIGNAL ITEM: FOUN | 2 EACH | $1,490 | $1,500 |
| 632E90104 REUSE OF TRAFFIC CONTROL ITEM: MODEM | 5 EACH | $250 | $500 |
| 633E67100 CABINET FOUNDATION | 5 EACH | $1,660 | $5,000 |
| 633E67200 CONTROLLER WORK PAD | 5 EACH | $940 | $3,000 |
| 809E69123 ATC CONTROLLER, AS PER PLAN | 5 EACH | $660 | $1,000 |
| 625E18200 BRACKET ARM, 15' | 1 EACH | $1,245 | $1,200 |
| 632E72110 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 4 | 1 EACH | $11,920 | $14,000 |
| 632E72130 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 12 | 1 EACH | $15,630 | $16,000 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 40 HOUR | $75.00 | $90.00 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $11,054 | $8,500 |
| AA2 625E18001 BRACKET ARM, 10', AS PER PLAN | 2 EACH | $698 | $1,500 |
| AA2 625E18201 BRACKET ARM, 15', AS PER PLAN | 4 EACH | $735 | $1,550 |
| AA2 632E72111 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 4, AS PER PL | 1 EACH | $12,445 | $16,000 |
| AA2 632E72131 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 12, AS PER P | 1 EACH | $14,810 | $18,000 |
| AA2 632E72141 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 13, AS PER P | 1 EACH | $17,740 | $21,000 |
| AA2 632E79101 COMBINATION SIGNAL SUPPORT, TYPE TC-81.22, DESIGN | 1 EACH | $11,910 | $11,000 |
| AA2 632E79111 COMBINATION SIGNAL SUPPORT, TYPE TC-81.22, DESIGN | 1 EACH | $13,800 | $17,000 |
| AA2 632E79141 COMBINATION SIGNAL SUPPORT, TYPE TC-81.22, DESIGN | 1 EACH | $19,000 | $23,000 |
| AA2 632E89901 PEDESTAL, 8', TRANSFORMER BASE, AS PER PLAN | 16 EACH | $540 | $2,000 |
| AA2 632E90010 PEDESTAL, MISC.: PEDESTAL, 15' TRANSFORMER BASE, | 1 EACH | $850 | $2,500 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 18 EACH | $9,950 | $179k | 11% |
| 809E69001 ADVANCE RADAR DETECTION, AS PER PLAN | 12 EACH | $10,300 | $124k | 8% |
| 632E64011 SIGNAL SUPPORT FOUNDATION, AS PER PLAN | 15 EACH | $7,980 | $120k | 8% |
| 625E25908 CONDUIT, JACKED OR DRILLED, 725.052, 4" | 1,118 FT | $90 | $101k | 6% |
| 633E65521 CABINET, TYPE 332, AS PER PLAN | 5 EACH | $16,335 | $82k | 5% |
| 632E05006 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, | 43 EACH | $1,190 | $51k | 3% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $50,000 | $50k | 3% |
| 633E75001 UNINTERRUPTIBLE POWER SUPPLY (UPS), 1000 WATT, AS | 5 EACH | $8,575 | $43k | 3% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40k | 3% |
| AA2 632E71493 SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 12 POLE, WITH | 1 EACH | $37,160 | $37k | 2% |