D08-TSG-FY2025/FY2026
D08 County · est $1.9M
Bid dateThursday, April 24—
D08 County · est $1.9M
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 102 more items below.
| Item | Quantity | R1Miller Cable Company | R2Complete General Construction Company | R3Bansal Construction INC | % of bid |
|---|---|---|---|---|---|
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 18 EACH | $9,600 | $8,200 | $9,360 | 13% |
| 633E67500 UNINTERRUPTIBLE POWER SUPPLY (UPS), BATTERY REPLAC | 117 EACH | $1,300 | $1,100 | $2,025 | 12% |
| 809E69001 ADVANCE RADAR DETECTION, AS PER PLAN | 14 EACH | $9,900 | $8,600 | $9,705 | 11% |
| 633E65521 CABINET, TYPE 332, AS PER PLAN | 5 EACH | $19,150 | $18,000 | $19,075 | 7% |
| 625E25908 CONDUIT, JACKED OR DRILLED, 725.052, 4" | 1,311 FT | $57.00 | $44.50 | $55.00 | 6% |
| 632E64000 STRAIN POLE FOUNDATION | 8 EACH | $7,100 | $10,000 | $7,750 | 4% |
| 632E86141 STRAIN POLE, TYPE TC-81.11, DESIGN 12, AS PER PLAN |
| Item | Quantity | R1Miller Cable Company | R2Complete General Construction Company | R3Bansal Construction INC |
|---|---|---|---|---|
| 202E30000 WALK REMOVED | 200 SF | $21.00 | $9.00 | $3.51 |
| 202E32000 CURB REMOVED | 50 FT | $60.00 | $9.00 | $11.13 |
| 608E10000 4" CONCRETE WALK | 200 SF | $40.00 | $30.00 | $12.49 |
| 611E00400 4" CONDUIT, TYPE E | 50 FT | $4.00 | $20.00 | $1.00 |
| 625E18100 BRACKET ARM, 12' | 1 EACH | $1,350 | $1,600 | $750 |
| 625E23400 NO. 10 AWG POLE AND BRACKET CABLE |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| 4 EACH |
| $13,300 |
| $12,500 |
| $10,500 |
| 4% |
| 632E86141 STRAIN POLE, TYPE TC-81.11, DESIGN 12, AS PER PLAN | 4 EACH | $13,050 | $13,000 | $10,765 | 4% |
| 632E64010 SIGNAL SUPPORT FOUNDATION | 6 EACH | $8,500 | $11,000 | $8,950 | 4% |
| 608E52001 CURB RAMP, AS PER PLAN | 250 SF | $190 | $35.00 | $24.95 | 4% |
| 632E10101 RELAMP EXISTING SIGNAL SECTION WITH LED LAMP UNIT, | 597 EACH | $75.00 | $70.00 | $70.00 | 3% |
| 632E10101 RELAMP EXISTING SIGNAL SECTION WITH LED LAMP UNIT, | 584 EACH | $75.00 | $70.00 | $70.00 | 3% |
| 632E10101 RELAMP EXISTING SIGNAL SECTION WITH LED LAMP UNIT, | 576 EACH | $75.00 | $70.00 | $70.00 | 3% |
| 632E72141 SIGNAL SUPPORT, TYPE TC-81.22, DESIGN 13, AS PER P | 2 EACH | $21,500 | $22,000 | $18,265 | 3% |
| 632E80700 SIGNAL SUPPORT, MISC.: SIGNAL SUPP TC-12.31 DESIGN | 1 EACH | $42,850 | $44,000 | $35,650 | 3% |
| 624E10000 MOBILIZATION | 1 LS | $40,000 | $40,000 | $100,000 | 3% |
| 633E75001 UNINTERRUPTIBLE POWER SUPPLY (UPS), 1000 WATT, AS | 5 EACH | $7,750 | $9,000 | $8,875 | 3% |
| 632E80700 SIGNAL SUPPORT, MISC.: SIGNAL SUPP TC-12.31 DESIGN | 1 EACH | $36,900 | $39,000 | $35,360 | 3% |
| 632E10101 RELAMP EXISTING SIGNAL SECTION WITH LED LAMP UNIT, | 208 EACH | $175 | $140 | $160 | 3% |
| 632E81700 COMBINATION SIGNAL SUPPORT, MISC.:COMBINATION SIGN | 1 EACH | $31,850 | $33,000 | $30,500 | 2% |
| 89 FT |
| $1.50 |
| $1.50 |
| $1.80 |
| 625E25408 CONDUIT, 2", 725.051 | 419 FT | $11.00 | $12.00 | $5.80 |
| 625E25604 CONDUIT, 4", 725.051 | 469 FT | $18.00 | $12.50 | $11.65 |
| 625E26252 LUMINAIRE, CONVENTIONAL, SOLID STATE (LED), 120V, | 1 EACH | $450 | $600 | $605 |
| 625E29000 TRENCH | 819 FT | $12.00 | $18.00 | $14.75 |
| 625E29400 TRENCH IN PAVED AREA | 100 FT | $33.00 | $52.50 | $75.00 |
| 625E30706 PULL BOX, 725.08, 24" | 26 EACH | $1,200 | $1,400 | $1,260 |
| 625E31510 PULL BOX REMOVED | 24 EACH | $225 | $425 | $100 |
| 625E32000 GROUND ROD | 34 EACH | $265 | $300 | $465 |
| 625E36010 UNDERGROUND WARNING/MARKING TAPE | 819 FT | $2.00 | $1.70 | $1.65 |
| 630E03100 GROUND MOUNTED SUPPORT, NO. 3 POST | 100 FT | $16.50 | $16.50 | $20.61 |
| 630E75000 SIGN ATTACHMENT ASSEMBLY | 8 EACH | $875 | $875 | $824 |
| 630E79000 SIGN HANGER ASSEMBLY, SPAN WIRE | 8 EACH | $485 | $485 | $233 |
| 630E79100 SIGN HANGER ASSEMBLY, MAST ARM | 14 EACH | $395 | $395 | $447 |
| 630E80100 SIGN, FLAT SHEET | 229.1 SF | $20.00 | $20.00 | $22.42 |
| 630E80224 SIGN, OVERHEAD EXTRUSHEET | 266 SF | $25.50 | $25.50 | $33.11 |
| 630E84900 REMOVAL OF GROUND MOUNTED SIGN AND DISPOSAL | 7 EACH | $15.00 | $15.00 | $20.51 |
| 630E86002 REMOVAL OF GROUND MOUNTED POST SUPPORT AND DISPOSA | 6 EACH | $25.00 | $25.00 | $27.35 |
| 630E87400 REMOVAL OF OVERHEAD MOUNTED SIGN AND DISPOSAL | 4 EACH | $245 | $245 | $389 |
| 630E89800 REMOVAL OF OVERHEAD SIGN SUPPORT AND DISPOSAL, TYP | 2 EACH | $1,430 | $1,430 | $1,180 |
| 630E97700 SIGNING, MISC.:SOLAR-POWERED AMISH BUGGY WARNING S | 1 EACH | $9,500 | $34,000 | $9,047 |
| 642E00300 CENTER LINE, TYPE 1 | 0.25 MILE | $12,230 | $5,400 | $5,400 |
| 644E00404 CHANNELIZING LINE, 12" | 50 FT | $6.75 | $1.70 | $1.70 |
| 644E00500 STOP LINE | 100 FT | $22.50 | $4.85 | $4.85 |
| 644E00630 CROSSWALK LINE, 24" | 500 FT | $18.00 | $4.85 | $4.85 |
| 644E00700 TRANSVERSE/DIAGONAL LINE | 100 FT | $22.50 | $4.85 | $4.85 |
| 644E00900 ISLAND MARKING | 100 SF | $13.50 | $4.85 | $4.85 |
| 644E01300 LANE ARROW | 2 EACH | $370 | $125 | $125 |
| 644E30000 REMOVAL OF PAVEMENT MARKING | 200 FT | $19.40 | $4.00 | $4.00 |
| 644E30010 REMOVAL OF PAVEMENT MARKING | 100 SF | $38.80 | $4.00 | $4.00 |
| 644E30020 REMOVAL OF PAVEMENT MARKING | 2 EACH | $535 | $100 | $100 |
| 632E04816 VEHICULAR SIGNAL HEAD, (LED), 1-SECTION, 12" LENS, | 1 EACH | $2,200 | $2,000 | $2,150 |
| 632E05006 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, | 22 EACH | $1,300 | $1,025 | $1,135 |
| 632E05006 VEHICULAR SIGNAL HEAD, (LED), 3-SECTION, 12" LENS, | 19 EACH | $1,300 | $1,025 | $1,130 |
| 632E05064 VEHICULAR SIGNAL HEAD, (LED), 4-SECTION, 12" LENS, | 2 EACH | $1,525 | $1,250 | $1,345 |
| 632E05064 VEHICULAR SIGNAL HEAD, (LED), 4-SECTION, 12" LENS, | 4 EACH | $1,800 | $1,500 | $1,595 |
| 632E05086 VEHICULAR SIGNAL HEAD, (LED), 5-SECTION, 12" LENS, | 10 EACH | $2,125 | $1,800 | $1,910 |
| 632E10101 RELAMP EXISTING SIGNAL SECTION WITH LED LAMP UNIT, | 15 EACH | $185 | $165 | $750 |
| 632E10101 RELAMP EXISTING SIGNAL SECTION WITH LED LAMP UNIT, | 32 EACH | $150 | $210 | $140 |
| 632E10101 RELAMP EXISTING SIGNAL SECTION WITH LED LAMP UNIT, | 237 EACH | $80.00 | $70.00 | $75.00 |
| 632E10101 RELAMP EXISTING SIGNAL SECTION WITH LED LAMP UNIT, | 2 EACH | $95.00 | $100 | $90.00 |
| 632E10101 RELAMP EXISTING SIGNAL SECTION WITH LED LAMP UNIT, | 95 EACH | $80.00 | $70.00 | $75.00 |
| 632E10101 RELAMP EXISTING SIGNAL SECTION WITH LED LAMP UNIT, | 2 EACH | $95.00 | $90.00 | $90.00 |
| 632E10101 RELAMP EXISTING SIGNAL SECTION WITH LED LAMP UNIT, | 211 EACH | $80.00 | $75.00 | $75.00 |
| 632E10101 RELAMP EXISTING SIGNAL SECTION WITH LED LAMP UNIT, | 2 EACH | $95.00 | $90.00 | $90.00 |
| 632E20731 PEDESTRIAN SIGNAL HEAD (LED), TYPE D2, COUNTDOWN, | 10 EACH | $825 | $660 | $690 |
| 632E20750 ACCESSIBLE PEDESTRIAN PUSHBUTTON | 10 EACH | $950 | $850 | $845 |
| 632E25000 COVERING OF VEHICULAR SIGNAL HEAD | 59 EACH | $40.00 | $40.00 | $50.00 |
| 632E25010 COVERING OF PEDESTRIAN SIGNAL HEAD | 10 EACH | $30.00 | $30.00 | $50.00 |
| 632E28200 DISCONNECT SWITCH WITH ENCLOSURE | 2 EACH | $1,000 | $2,250 | $3,725 |
| 632E30200 MESSENGER WIRE, 7 STRAND, 3/8" DIAMETER WITH ACCES | 1,000 FT | $20.00 | $20.00 | $14.15 |
| 632E30600 TETHER WIRE, WITH ACCESSORIES | 1,000 FT | $20.00 | $24.00 | $12.30 |
| 632E40500 SIGNAL CABLE, 5 CONDUCTOR, NO. 14 AWG | 500 FT | $3.00 | $3.00 | $2.20 |
| 632E40700 SIGNAL CABLE, 7 CONDUCTOR, NO. 14 AWG | 9,555 FT | $3.20 | $3.50 | $2.45 |
| 632E64020 PEDESTAL FOUNDATION | 18 EACH | $1,300 | $1,350 | $1,265 |
| 632E64021 PEDESTAL FOUNDATION, AS PER PLAN | 1 EACH | $1,750 | $3,000 | $1,500 |
| 632E64950 TEST HOLE PERFORMED | 6 EACH | $350 | $2,750 | $461 |
| 632E65300 LOOP DETECTOR LEAD-IN CABLE, 2 CONDUCTOR, NO. 14 A | 500 FT | $2.00 | $2.00 | $1.93 |
| 632E68300 POWER CABLE, 3 CONDUCTOR, NO. 6 AWG | 445 FT | $7.50 | $5.00 | $6.65 |
| 632E68400 POWER CABLE, 4 CONDUCTOR, NO. 6 AWG | 200 FT | $9.50 | $6.00 | $8.86 |
| 632E69800 SERVICE CABLE, 3 CONDUCTOR, NO. 6 AWG | 619 FT | $8.00 | $5.00 | $6.65 |
| 632E69910 SERVICE CABLE, 3 CONDUCTOR, WITH GROUND, NO. 4 AWG | 100 FT | $12.00 | $10.00 | $9.27 |
| 632E70001 POWER SERVICE, AS PER PLAN | 6 EACH | $1,900 | $3,500 | $9,907 |
| 632E70400 CONDUIT RISER, 2" DIAMETER | 2 EACH | $500 | $1,250 | $1,512 |
| 632E71388 SIGNAL SUPPORT, TYPE TC-12.31 DESIGN 10 POLE, WITH | 1 EACH | $30,550 | $31,000 | $30,485 |
| 632E89301 WOOD POLE, AS PER PLAN | 2 EACH | $1,600 | $2,500 | $1,980 |
| 632E89400 DOWN GUY | 2 EACH | $435 | $1,000 | $500 |
| 632E89900 PEDESTAL, 8', TRANSFORMER BASE | 10 EACH | $890 | $1,000 | $715 |
| 632E90000 PEDESTAL, 11', TRANSFORMER BASE | 2 EACH | $1,675 | $1,800 | $790 |
| 632E90001 PEDESTAL, 11', TRANSFORMER BASE, AS PER PLAN | 4 EACH | $1,725 | $1,800 | $895 |
| 632E90020 REMOVAL OF MISCELLANEOUS TRAFFIC SIGNAL ITEM: VAR | 5 EACH | $500 | $350 | $100 |
| 632E90100 REMOVAL OF TRAFFIC SIGNAL INSTALLATION | 5 EACH | $3,350 | $10,000 | $5,000 |
| 632E90104 REUSE OF TRAFFIC CONTROL ITEM: FIBER OPTIC TERMIN | 2 EACH | $1,000 | $275 | $250 |
| 632E90104 REUSE OF TRAFFIC CONTROL ITEM: MODEM | 1 EACH | $700 | $1,200 | $250 |
| 632E90104 REUSE OF TRAFFIC CONTROL ITEM: NETWORK SWITCH | 2 EACH | $900 | $1,000 | $250 |
| 632E90104 REUSE OF TRAFFIC CONTROL ITEM: PRE-EMPTION PHASE | 2 EACH | $175 | $250 | $125 |
| 632E90104 REUSE OF TRAFFIC CONTROL ITEM: PRE-EMPTION RECEIV | 2 EACH | $600 | $275 | $125 |
| 632E90104 REUSE OF TRAFFIC CONTROL ITEM: VARIOUS SIGNAL COM | 5 EACH | $600 | $800 | $500 |
| 632E90400 SIGNALIZATION, MISC.: SPANWIRE ADJUSTMENT | 5 EACH | $575 | $2,500 | $1,890 |
| 632E90500 SIGNALIZATION, MISC.: REMOVAL OF LOOP DETECTOR CA | 7,716 FT | $1.00 | $0.75 | $1.50 |
| 632E90500 SIGNALIZATION, MISC.: UNLASH AND RELASH MESSENGER | 300 FT | $5.00 | $10.50 | $10.60 |
| 633E67100 CABINET FOUNDATION | 5 EACH | $2,900 | $5,000 | $1,650 |
| 633E67200 CONTROLLER WORK PAD | 5 EACH | $650 | $1,500 | $1,025 |
| 633E71000 FLASHER CONTROLLER | 1 EACH | $1,674 | $1,250 | $2,060 |
| 804E15010 FIBER OPTIC CABLE, 24 FIBER | 432 FT | $3.00 | $8.00 | $6.00 |
| 804E32012 DROP CABLE, 24 FIBER | 2 EACH | $750 | $1,750 | $2,700 |
| 804E37000 SPLICE ENCLOSURE, BUTT STYLE | 2 EACH | $1,500 | $2,325 | $975 |
| 809E60000 CCTV IP-CAMERA SYSTEM, PTZ | 5 EACH | $6,350 | $8,000 | $6,150 |
| 809E64550 ETHERNET CABLE, OUTDOOR-RATED | 643 FT | $3.00 | $12.00 | $2.30 |
| 809E69123 ATC CONTROLLER, AS PER PLAN | — | $1,100 | $625 | $625 |
| 809E69220 PREEMPT DETECTOR CABLE | 132 FT | $3.50 | $6.00 | $1.85 |
| 809E69241 PREEMPT CONFIRMATION LIGHT, AS PER PLAN, LED | 2 EACH | $725 | $600 | $610 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 40 HOUR | $75.00 | $100 | $75.00 |
| 614E18000 MAINTAINING TRAFFIC, MISC.: MAINTAINING TRAFFIC P | 6 EACH | $3,000 | $3,500 | $2,500 |
| 614E18000 MAINTAINING TRAFFIC, MISC.: MAINTAINING TRAFFIC P | 86 EACH | $170 | $500 | $250 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $8,500 | $9,000 | $13,148 |
| 623E10001 CONSTRUCTION LAYOUT STAKES AND SURVEYING, AS PER P | 1 LS | $17,700 | $10,000 | $10,000 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 809E69101 STOP LINE RADAR DETECTION, AS PER PLAN | 18 EACH | $9,600 | $173k | 9% |
| 633E67500 UNINTERRUPTIBLE POWER SUPPLY (UPS), BATTERY REPLAC | 117 EACH | $1,300 | $152k | 8% |
| 809E69001 ADVANCE RADAR DETECTION, AS PER PLAN | 14 EACH | $9,900 | $139k | 7% |
| 633E65521 CABINET, TYPE 332, AS PER PLAN | 5 EACH | $19,150 | $96k | 5% |
| 625E25908 CONDUIT, JACKED OR DRILLED, 725.052, 4" | 1,311 FT | $57 | $75k | 4% |
| 632E64000 STRAIN POLE FOUNDATION | 8 EACH | $7,100 | $57k | 3% |
| 632E86141 STRAIN POLE, TYPE TC-81.11, DESIGN 12, AS PER PLAN | 4 EACH | $13,300 | $53k | 3% |
| 632E86141 STRAIN POLE, TYPE TC-81.11, DESIGN 12, AS PER PLAN | 4 EACH | $13,050 | $52k | 3% |
| 632E64010 SIGNAL SUPPORT FOUNDATION | 6 EACH | $8,500 | $51k | 3% |
| 608E52001 CURB RAMP, AS PER PLAN | 250 SF | $190 | $48k | 2% |