D08-ITS Maint FY2026
D08 County
Bid dateThursday, July 17—
D08 County
Bid form · ODOT
ODOT bid tab line items with each bidder’s unit price. Top 20items by winning bid’s extended amount · 36 more items below.
| Item | Quantity | R1Bansal Construction INC | R2Capital Electric Line Builders INC | % of bid |
|---|---|---|---|---|
| 809E61040 CCTV POLE, 70' TALL | 4 EACH | $32,500 | $60,163 | 12% |
| 625E29010 TRENCH, 30" DEEP | 4,730 FT | $20.00 | $11.07 | 9% |
| 809E61090 CCTV LOWERING UNIT | 6 EACH | $15,000 | $13,538 | 8% |
| 809E02000 32" ITS PULL BOX WITH PAD AND STANDARD LID ASSEMBL | 22 EACH | $3,390 | $4,115 | 7% |
| 809E65990 ITS DEVICE, MISC.:REMOVAL AND DELIVERY OF WOOD POL | 25 EACH | $2,680 | $3,277 | 6% |
| 809E60040 CCTV IP-CAMERA SYSTEM, QUAD MULTI-VIEW FIXED WITH | 7 EACH | $9,500 | $7,601 | 6% |
| 633E67201 CONTROLLER WORK PAD, AS PER PLAN | 16 EACH | $4,000 | $6,839 | 6% |
| 809E02002 32" ITS PULL BOX WITH PAD AND HINGED LID ASSEMBLY, | 12 EACH | $4,925 | $5,500 | 6% |
| 203E10000 EXCAVATION | 300 CY | $190 | $143 | 5% |
| 304E20000 AGGREGATE BASE | 300 CY | $170 | $245 | 5% |
| 625E31600 PULL BOX, MISC.:MOW PAD | 34 EACH | $1,500 | $1,059 | 5% |
| 614E11000 MAINTAINING TRAFFIC | 1 LS | $50,000 | $57,000 | 5% |
| 624E10000 MOBILIZATION | 1 LS | $48,477 | $45,600 | 5% |
| 625E23308 DISTRIBUTION CABLE, MISC.:INSTALL ONLY | 15,000 FT | $2.50 | $2.64 | 4% |
| 809E25000 CONDUIT, MULTICELL, MISC.:4", JACKED OR DRILLED, I | 500 FT | $50.00 | $45.60 | 2% |
| 633E67101 CABINET FOUNDATION, AS PER PLAN | 12 EACH | $1,950 | $5,927 | 2% |
| 809E65990 ITS DEVICE, MISC.:CCTV STEEL POLE, 70 FEET, REMOVE | 2 EACH | $10,000 | $8,293 | 2% |
| 809E65990 ITS DEVICE, MISC.:REMOVAL AND DELIVERY OF CABINET | 4 EACH | $5,000 | $2,109 | 2% |
| 625E30700 PULL BOX, 725.08, 18" | 17 EACH | $1,150 | $1,560 | 2% |
| 809E65000 ITS CABINET - GROUND MOUNTED | 2 EACH | $9,500 | $9,889 | 2% |
| Item | Quantity | R1Bansal Construction INC | R2Capital Electric Line Builders INC |
|---|---|---|---|
| 201E11000 CLEARING AND GRUBBING | 1 LS | $4,000 | $5,472 |
| 204E10000 SUBGRADE COMPACTION | 1,175 SY | $5.75 | $5.47 |
| 601E21060 TIED CONCRETE BLOCK MAT WITH TYPE 2 UNDERLAYMENT | 150 SY | $110 | $171 |
| 607E23000 FENCE, TYPE CLT | 20 FT | $163 | $3,249 |
| 607E61200 GATE, TYPE CLT | 2 EACH | $3,520 | $3,249 |
| 607E70000 FENCELINE SEEDING AND MULCHING | 20 FT | $12.50 | $1,061 |
| 204E45000 PROOF ROLLING | 8 HOUR |
How to read this. Plan‑pull counts come straight from agency portals. Patterns and confidence scores are derived from comparable lettings (same county, same category, three‑year basis). Confidence is a calibration of past correctness on signals of this shape — not a guarantee of this bid’s outcome. We never round up. More on what Cassandri does →
| $380 |
| $285 |
| 832E30000 EROSION CONTROL | 2,000 EACH | $1.00 | $1.00 |
| 625E00480 CONNECTION, UNFUSED PERMANENT | 12 EACH | $100 | $106 |
| 625E14600 LIGHT POLE FOUNDATION, MISC.:CCTV POLE, 70' STEEL | 1 EACH | $7,980 | $16,019 |
| 625E25410 CONDUIT, 2", 725.052 | 1,320 FT | $5.10 | $2.31 |
| 625E25506 CONDUIT, 3", 725.052 | 200 FT | $7.10 | $2.46 |
| 625E31511 PULL BOX REMOVED, AS PER PLAN | 7 EACH | $500 | $905 |
| 625E32001 GROUND ROD, AS PER PLAN | 24 EACH | $485 | $237 |
| 625E36010 UNDERGROUND WARNING/MARKING TAPE | 4,730 FT | $1.65 | $1.33 |
| 625E75511 POWER SERVICE REMOVED, AS PER PLAN | 1 EACH | $2,500 | $2,223 |
| 625E75550 DISTRIBUTION CABLE REMOVED | 750 FT | $2.00 | $1.32 |
| 632E64000 STRAIN POLE FOUNDATION | 1 EACH | $9,850 | $16,019 |
| 632E86131 STRAIN POLE, TYPE TC-81.11, DESIGN 10, AS PER PLAN | 1 EACH | $17,500 | $14,269 |
| 809E25000 CONDUIT, MULTICELL, MISC.:4", INSTALL ONLY | 500 FT | $8.00 | $5.54 |
| 809E25000 CONDUIT, MULTICELL, MISC.:INSTALL ONLY THROUGH EXI | 500 FT | $4.00 | $10.54 |
| 809E51000 ITS POWER SERVICE, GROUND MOUNTED, 120/240V, 60 AM | 1 EACH | $7,000 | $15,617 |
| 809E52000 ITS POWER SERVICE, GROUND MOUNTED, 240/480V, 60 AM | 1 EACH | $9,000 | $27,017 |
| 809E55000 ITS POWER SERVICE, POLE MOUNTED, 120/240V, 60 AMP | 1 EACH | $7,500 | $15,617 |
| 809E56000 ITS POWER SERVICE, POLE MOUNTED, 240/480V, 60 AMP | 1 EACH | $9,500 | $27,017 |
| 809E64550 ETHERNET CABLE, OUTDOOR-RATED | 1,400 FT | $3.00 | $2.18 |
| 809E65990 ITS DEVICE, MISC.:MAINTENANCE OF EXISTING POWER SE | 1 EACH | $10,000 | $27,017 |
| 809E65990 ITS DEVICE, MISC.:REMOVAL AND DELIVERY OF CCTV AND | 3 EACH | $2,500 | $2,109 |
| 809E65990 ITS DEVICE, MISC.:REMOVAL AND DELIVERY OF STEEL PO | 3 EACH | $2,500 | $3,277 |
| 809E65990 ITS DEVICE, MISC.:REMOVAL AND DELIVERY OF STRAIN P | 3 EACH | $2,500 | $3,277 |
| 625E25930 CONDUIT, MISC.:CONDUIT REPAIR | 1 EACH | $1,325 | $2,679 |
| 625E31600 PULL BOX, MISC.:INSTALL ONLY | 6 EACH | $2,150 | $2,679 |
| 614E11110 LAW ENFORCEMENT OFFICER WITH PATROL CAR FOR ASSIST | 20 HOUR | $95.00 | $91.20 |
| 614E18601 PORTABLE CHANGEABLE MESSAGE SIGN, AS PER PLAN | 2 SNMT | $1,155 | $2,194 |
| 103E05000 PREMIUM FOR CONTRACT PERFORMANCE BOND AND FOR PAYM | 1 LS | $9,684 | $11,106 |
| 623E10000 CONSTRUCTION LAYOUT STAKES AND SURVEYING | 1 LS | $15,000 | $11,400 |
| Item | Qty | Unit price | Extended | % |
|---|---|---|---|---|
| 809E61040 CCTV POLE, 70' TALL | 4 EACH | $32,500 | $130k | 10% |
| 625E29010 TRENCH, 30" DEEP | 4,730 FT | $20 | $95k | 7% |
| 809E61090 CCTV LOWERING UNIT | 6 EACH | $15,000 | $90k | 7% |
| 809E02000 32" ITS PULL BOX WITH PAD AND STANDARD LID ASSEMBL | 22 EACH | $3,390 | $75k | 6% |
| 809E65990 ITS DEVICE, MISC.:REMOVAL AND DELIVERY OF WOOD POL | 25 EACH | $2,680 | $67k | 5% |
| 809E60040 CCTV IP-CAMERA SYSTEM, QUAD MULTI-VIEW FIXED WITH | 7 EACH | $9,500 | $67k | 5% |
| 633E67201 CONTROLLER WORK PAD, AS PER PLAN | 16 EACH | $4,000 | $64k | 5% |
| 809E02002 32" ITS PULL BOX WITH PAD AND HINGED LID ASSEMBLY, | 12 EACH | $4,925 | $59k | 5% |
| 203E10000 EXCAVATION | 300 CY | $190 | $57k | 4% |
| 304E20000 AGGREGATE BASE | 300 CY | $170 | $51k | 4% |